A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.

Challenge: Frequent false tripping using conventional electromechanical relays
Solution: SEL-487E integration with multi-terminal differential protection and dynamic inrush restraint
Result: 90% reduction in false trips, saving over $250,000 in downtime

Category Metric
VPP capacity (Lunar Energy) 650 MW
Lunar funding raised US$232 million
Data center BESS example 31 MW / 62 MWh
ERCOT grid-scale batteries 15+ GW
LDES tenders (H1 2026) Up to 9.3 GW
Lithium-ion share of LDES by 2030 77%
FEOC initial threshold 55%
BESS tariff rate (2026) ~55%
Capacity gain from analytics 5–15%

FERC Order 1920-B: Transforming Long-Term Regional Transmission Planning in the United States

Keentel Engineering transmission infrastructure project with utility truck, construction loader, and high voltage transmission towers during power line installation work.
Calendar icon. D

March 13, 2026  | blog

Introduction

The U.S. electric grid is undergoing one of the most significant transitions in its history. The rapid growth of renewable energy, electrification of transportation and industry, and increasing extreme weather events are placing unprecedented demands on transmission infrastructure.


To address these challenges, the Federal Energy Regulatory Commission (FERC) issued Order No. 1920, followed by Order No. 1920-A and Order No. 1920-B, establishing sweeping reforms to regional transmission planning and cost allocation across the United States.


These reforms require transmission providers to perform long-term regional transmission planning that anticipates grid needs decades into the future, ensuring that transmission expansion is efficient, cost-effective, and aligned with evolving energy policies. 



For utilities, developers, and grid operators, understanding these reforms is critical. Engineering firms like Keentel Engineering play an essential role in helping stakeholders navigate these regulatory changes through power system studies, transmission planning, and compliance support.


Why FERC Order 1920 Was Needed

Historically, transmission planning processes focused primarily on near-term reliability needs rather than long-term system evolution.


FERC determined that existing planning frameworks were insufficient because they did not:


  • Conduct sufficiently long-term assessments of transmission needs
  • Consider future resource mix changes
  • Evaluate broader benefits of regional transmission projects
  • Provide adequate mechanisms for cost allocation across regions 


These shortcomings created barriers to building the large-scale transmission infrastructure needed to integrate renewable generation and maintain grid reliability.


Core Objective of Order 1920

The fundamental goal of Order 1920 is to ensure that transmission providers conduct long-term regional transmission planning capable of identifying and developing cost-effective transmission solutions.



FERC requires that regional planning processes:


  1. Identify Long-Term Transmission Needs
  2. Evaluate regional transmission solutions
  3. Quantify system benefits
  4. Select projects based on cost-effectiveness
  5. Allocate project costs fairly across beneficiaries

Long-Term Regional Transmission Planning

Planning Horizon

A key feature of the new rule is the requirement for long-term planning horizons, typically covering 20 years or more.


Transmission providers must evaluate how system conditions may evolve due to:


  • Load growth
  • Resource retirements
  • Renewable generation expansion
  • public policy changes
  • electrification trends
  • reliability risks


This approach ensures that transmission infrastructure is designed for the future grid, not just current conditions.


Scenario-Based Planning

Order 1920 requires transmission planners to develop multiple plausible future scenarios when assessing transmission needs.

Each planning region must evaluate at least three diverse long-term scenarios, incorporating key drivers of grid transformation. 


These scenarios must consider factors such as:


  • Resource mix changes
  • Load growth
  • electrification
  • fuel price uncertainty
  • policy mandates
  • extreme weather impacts


Scenario analysis enables planners to identify transmission investments that remain valuable across multiple future outcomes.


Long-Term Transmission Needs

A central concept introduced by the rule is Long-Term Transmission Needs, which represent system requirements identified through forward-looking planning.


These needs may arise from:


  • Generation shifts toward renewable energy
  • interconnection of large energy resources
  • reliability constraints
  • congestion management
  • resilience improvements



Transmission facilities selected through this process are known as Long-Term Regional Transmission Facilities.


Regional Transmission Cost Allocation

Cost allocation has historically been one of the most contentious issues in transmission planning.


Order 1920 introduces reforms to ensure that costs are assigned based on beneficiary-pays principles.


Transmission providers must develop ex-ante cost allocation methods that determine how costs are distributed before projects are selected. 



This improves transparency and reduces disputes during project development.


Role of State Regulators

One of the most significant reforms in Order 1920 is the expanded role of states.


State regulatory bodies called Relevant State Entities play a critical role in:


  • negotiating cost allocation approaches
  • participating in planning processes
  • ensuring alignment with state energy policies


Transmission providers must engage with these entities during a six-month engagement period, allowing states to propose cost allocation methodologies. 



This collaboration ensures that transmission planning reflects both regional grid needs and state policy objectives.


Coordination with Non-Jurisdictional Utilities

The rule clarifies how transmission planning should address the needs of non-jurisdictional utilities such as municipal utilities and cooperatives.


Transmission providers are not required to plan for these entities unless they participate in the regional planning process and agree to cost allocation rules. 


However, voluntary participation arrangements remain possible if they comply with cost-causation principles.


Implications for the U.S. Grid

FERC Order 1920 represents a fundamental shift toward proactive transmission expansion.


Key expected outcomes include:

1. Faster Transmission Development


Better planning reduces project delays and improves interregional coordination.


2. Renewable Integration


The rule facilitates transmission development needed to connect large renewable resources.


3. Grid Reliability


Forward-looking planning helps address extreme weather risks and resource adequacy.


4. Economic Efficiency


Regional projects may reduce congestion costs and lower electricity prices.


Role of Engineering Firms in Order 1920 Implementation

The complexity of long-term planning and regulatory compliance creates a strong demand for specialized engineering expertise.


Consulting firms like Keentel Engineering support utilities and developers through services including:


  • Transmission planning studies
  • Production cost modeling
  • Power flow and contingency analysis
  • Dynamic stability analysis
  • Renewable integration studies
  • Interconnection studies
  • NERC compliance assessments
  • regulatory compliance support


Advanced modeling tools commonly used include:


  • PSSE
  • PSCAD
  • TSAT
  • PowerFactory
  • PLEXOS
  • MATLAB/Simulink


These tools enable accurate modeling of future grid conditions under the long-term scenarios required by Order 1920.


How Keentel Engineering Supports Utilities

Keentel Engineering provides comprehensive services to support compliance with modern grid planning regulations.


These services include:


Transmission Planning Studies


Long-term scenario modeling aligned with FERC Order 1920 requirements.


Power System Modeling


High-fidelity dynamic and steady-state modeling.


Cost-Benefit Analysis


Evaluation of transmission alternatives and benefit metrics.


Interconnection and Integration Studies


Assessment of renewable and inverter-based resource impacts.


Regulatory Advisory



Technical support for regulatory filings and compliance.


Conclusion

FERC Order 1920-B represents one of the most consequential reforms in U.S. transmission policy in decades. By requiring long-term regional transmission planning and improved cost allocation processes, the rule aims to modernize grid planning and accelerate the development of transmission infrastructure needed for the future energy system.


As utilities and grid operators implement these reforms, engineering expertise will be essential to navigate planning requirements, conduct complex studies, and support regulatory compliance.


Firms like Keentel Engineering provide the technical expertise necessary to help utilities, developers, and system operators successfully adapt to this evolving regulatory landscape.


FAQ – FERC Order 1920 and Transmission Planning

  • 1. What is FERC Order 1920?

    FERC Order 1920 establishes new requirements for long-term regional transmission planning and cost allocation across the United States.


  • 2. Why did FERC issue Order 1920?

    FERC determined that existing transmission planning processes did not adequately identify long-term transmission needs or evaluate the broader benefits of regional transmission projects. 


  • 3. What are Long-Term Transmission Needs?

    These are system requirements identified through long-term planning scenarios that reflect future grid conditions.


  • 4. What is Long-Term Regional Transmission Planning?

    It is a planning process designed to identify transmission solutions over long time horizons using forward-looking analysis.


  • 5. How many planning scenarios are required?

    Transmission providers must evaluate at least three diverse long-term scenarios to assess potential future grid conditions. 


  • 6. What are Long-Term Regional Transmission Facilities?

    These are transmission projects identified through long-term planning processes that address future transmission needs.


  • 7. What role do states play in Order 1920?

    States participate through Relevant State Entities, which can help develop cost allocation methodologies.


  • 8. What is the Engagement Period?

    A six-month negotiation period where states and transmission providers collaborate on cost allocation frameworks.


  • 9. Does Order 1920 require planning for non-jurisdictional utilities?

    No. Transmission providers are not required to plan for those utilities unless they enroll in the regional planning process.


  • 10. What is cost causation in transmission planning?

    It is the principle that entities benefiting from transmission projects should share the project costs.


  • 11. How does Order 1920 affect renewable integration?

    It supports the development of transmission infrastructure needed to integrate large renewable energy resources.


  • 12. What studies are required to support transmission planning?

    Typical studies include power flow, stability analysis, production cost modeling, and scenario planning.


  • 13. Which power system tools are commonly used?

    Common tools include PSSE, PSCAD, PowerFactory, and PLEXOS.


  • 14. What industries are affected by Order 1920?

    Utilities, ISOs/RTOs, renewable developers, transmission developers, and regulators.


  • 15. How can engineering consultants assist with compliance?

    Engineering firms perform planning studies, modeling, regulatory analysis, and technical documentation required for compliance.




Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sonny Patel P.E. EC

IEEE Senior Member

In 1995, Sandip (Sonny) R. Patel earned his Electrical Engineering degree from the University of Illinois, specializing in Electrical Engineering . But degrees don’t build legacies—action does. For three decades, he’s been shaping the future of engineering, not just as a licensed Professional Engineer across multiple states (Florida, California, New York, West Virginia, and Minnesota), but as a doer. A builder. A leader. Not just an engineer. A Licensed Electrical Contractor in Florida with an Unlimited EC license. Not just an executive. The founder and CEO of KEENTEL LLC—where expertise meets execution. Three decades. Multiple states. Endless impact.

Four workers in safety vests and helmets stand with arms crossed near wind turbines.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sonny Patel P.E. EC

IEEE Senior Member

In 1995, Sandip (Sonny) R. Patel earned his Electrical Engineering degree from the University of Illinois, specializing in Electrical Engineering . But degrees don’t build legacies—action does. For three decades, he’s been shaping the future of engineering, not just as a licensed Professional Engineer across multiple states (Florida, California, New York, West Virginia, and Minnesota), but as a doer. A builder. A leader. Not just an engineer. A Licensed Electrical Contractor in Florida with an Unlimited EC license. Not just an executive. The founder and CEO of KEENTEL LLC—where expertise meets execution. Three decades. Multiple states. Endless impact.

Leave a Comment

Related Posts

High voltage electrical substation construction with transmission equipment and switchgear infrastru
By SANDIP R PATEL March 11, 2026
Discover best practices for high-voltage substation construction, including engineering planning, labor productivity benchmarking, equipment installation, and project control strategies.
Large baseload power plant cooling towers connected to high-voltage transmission grid infrastructure
By SANDIP R PATEL March 11, 2026
Engineering guide to grid integration of large baseload power plants covering system stability, substation design, transformer configuration, and reliability requirements.
IEC 61439 low oltage switchgear and controlgear assembly panel
By SANDIP R PATEL March 11, 2026
Learn how IEC 61439 governs low-voltage switchgear assemblies, including design verification, safety requirements, temperature rise limits, and engineering practices for compliant power distribution systems.
Protection relay testing equipment (Omicron CMC 356) used in power plant commissioning and electrica
By SANDIP R PATEL March 11, 2026
Learn the hidden problems in power plant commissioning and how engineering testing, relay verification, and system validation prevent failures.
High-voltage electrical substation with transmission towers, power lines, and switching equipment il
By SANDIP R PATEL March 8, 2026
Explore advanced power system protection and relaying used in modern substations, including SCADA integration, relay coordination, fault detection, and digital protection technologies.
NERC PRC-012-2 compliance for solar, wind, and battery energy storage systems.
By SANDIP R PATEL March 7, 2026
Guide to NERC PRC-012-2 compliance for solar plants, wind farms, and BESS. Understand RAS requirements, generator owner obligations, and testing rules.
Engineer monitoring SCADA system displays in a control room illustrating modern
By SANDIP R PATEL March 7, 2026
High-voltage electrical substation with transmission towers, power lines, and switching equipment illustrating advanced power system protection and relaying in modern substation design.
Engineer inspecting high-voltage substation equipment for FAC-008-5 facility ratings and NERC compli
By SANDIP R PATEL March 5, 2026
Learn how FAC-008-5 defines Facility Ratings for BES equipment. Discover rating methodologies, compliance requirements, and engineering practices for NERC reliability standards.
NYISO power system study scenarios showing Base Case, Contract Case, and Policy Case with PSCAD grid
By SANDIP R PATEL March 5, 2026
Explore NYISO power system modeling for interconnection studies, including PSSE simulations, short-circuit analysis, dynamic stability models, and grid integration requirements for reliable project approval.