A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.

Challenge: Frequent false tripping using conventional electromechanical relays
Solution: SEL-487E integration with multi-terminal differential protection and dynamic inrush restraint
Result: 90% reduction in false trips, saving over $250,000 in downtime

CenterPoint Energy Interconnection

Requirements for Large Data-Center Loads

Grid interconnection feasibility and transmission planning
Calendar icon. D

June 26, 2026 | Blog

1.  Executive Summary


CenterPoint Energy (CNP) governs how large electrical loads connect to its distribution system through a set of published specifications. For a large data-center development, four of these documents are central: the specification for MV primary service ,the specification for limitation of harmonic distortion , the specification for customer emergency generation and secondary load transfer , and the Motor Start Review process. Together they define how the service is configured and protected, how harmonic distortion is limited, how backup generation is interconnected, and how large motors are reviewed.


This white paper distills those requirements into a single, project-oriented reference for a large data-center development in the CenterPoint Energy service area. It explains each requirement, highlights the thresholds and rules that most affect a large, electronically-fed data-center load, and closes with a detailed FAQ, a glossary, and a register of the governing documents. The intent is to give a project team a clear, shared understanding of what CenterPoint expects and why — so the engineering, schedule, and budget decisions can be made on a sound basis.


Key takeaway: 


A data-center load is large enough to trigger CenterPoint’s service-splitting and circuit-breaker thresholds, and it is dominated by non-linear electronic equipment that makes harmonic compliance (IEEE 519-2014) a real design driver rather than a formality. These two facts shape nearly every requirement discussed below.


2.  Purpose & Scope

This document is a technical reference, not a design or a contract. It summarizes and interprets CenterPoint’s published requirements as they apply to a large data-center load and organizes them for quick reference by the project team. Where specific clauses are cited (for example, “Article 4.8.1”), they refer to the corresponding CenterPoint specification listed in Section 13.


The scope covers: the primary-service configuration and protection rules; the harmonic distortion limits and the customer’s modeling and mitigation obligations; the requirements for emergency / backup generation and secondary load transfer; the motor-start review process; the Article 9.0 submittal package required before energization; and CenterPoint’s design-stage process, including how and when the need for a substation is determined. It does not reproduce the specifications in full, and in any conflict the governing CenterPoint documents and CNP-approved project drawings control.


3.  CenterPoint’s Role & the Governing Standards

CenterPoint Energy owns and operates the electric delivery system in its service territory and sets the technical conditions under which a customer may interconnect. CNP reserves the right to refuse to energize any service that fails to meet its specifications or its approved project drawings, and any deviation requires the written approval of CNP’s Manager of Power Quality Engineering or a designated representative. Where a specification and an approved drawing conflict, the drawing governs.


CenterPoint’s requirements sit on top of, and incorporate, broader codes and standards. Customer installations must comply with the National Electrical Code (NEC), the National Electrical Safety Code (NESC) / ANSI-IEEE C2, and local authority requirements. Harmonic control is governed by IEEE 519-2014 and Public Utility Commission of Texas (PUCT) Substantive Rule 25.51. Parallel and closed-transition generation is governed by PUCT Substantive Rules 25.211 and 25.212 and CNP’s customer-generation specification .


4.  Primary Service Requirements 

This specification defines the minimum requirements for primary service at 12,470Y/7,200 V (“12 kV primary service”) and 34,500Y/19,920 V (“35 kV primary service”), both three-phase, four-wire, grounded-neutral. The customer generally furnishes the equipment, and the customer’s first structure on which CNP conductors dead-end is the “Primary Service Pole.”


4.1  Service Voltage & Configuration



Service is provided at 12 kV or 35 kV. For a large load, the higher 35 kV voltage carries less current for the same power and can reduce the number of separate services required. Three-wire utilization equipment is permitted on 12 kV service (bonded to the CNP system neutral) but is not permitted on 35 kV service.

Requirement 12 kV Service 35 kV Serviceme
Nominal voltage (3Ø, 4-wire, grounded wye) 12,470Y / 7,200 V 34,500Y / 19,920 V
Overhead equipment BIL (minimum) 110 kV 150 kV
Underground (pad-mounted) BIL (minimum) 95 kV 150 kV
Three-wire utilization equipment Permitted (bonded to neutral) Not permitted

4.2  Service Capacity & Service Splitting


Two capacity thresholds are decisive for a large load. First, a service whose connected transformer capacity exceeds 4 MVA at 12 kV or 6 MVA at 35 kV may be required by CNP to be split into two or more separate services, and an Operational Agreement is required when a customer is served from multiple services. Second, the choice between fuses and a circuit breaker as the main protective device is set by capacity (see Section 4.3). Because these thresholds are far below a data-center-scale load, multiple services, a circuit-breaker main device, and one or more Operational Agreements should be anticipated.

Threshold 12 kV 35 kV Consequence
Service may be split into multiple services > 4 MVA > 6 MVA Multiple services; Operational Agreement
Circuit breaker required (vs. fuses) > 4,320 kVA > 11,950 kVA Breaker / recloser main device
Single-phase service limit 500 kVA 500 kVA
Two-phase service limit 1,000 kVA 1,000 kVA Balanced between phases

4.3  Main Protective Device


Every primary-service customer must provide, install, and maintain a main protective device — either a single group of three fuses or an electronically / electromechanically controlled circuit breaker (hydraulic breakers are not allowed). Fuses may be used only when demand or connected transformer capacity is at or below the thresholds in Section 4.2; above 4,320 kVA at 12 kV or 11,950 kVA at 35 kV, a three-phase circuit breaker (pole-mounted recloser, pad-mounted, or indoor) is required. Important rules for breaker installations include:


  • Automatic reclosing is not permitted.
  • The customer determines and sets the relay settings, performs functional testing, and provides the settings in an electronic data file plus certified test reports; CNP verifies coordination and loading before energization.
  • The breaker control must be accessible to CNP at all times and arranged for both CNP and customer locks.
  • A three-phase, gang-operated bypass switch is recommended; if omitted, maintenance outages must be scheduled with CNP under the Operational Agreement.
  • Bushing CTs must be on the source side with relay accuracy of C100 or better, and the breaker must have capacitor-trip or battery backup for trip power.


4.4  Disconnecting
Device, Overvoltage Protection & BIL


A disconnecting device may be required in addition to the main protective device (for example, when the main device is a pad-mounted breaker). It must be rated for the maximum expected load and fault duty and meet the same BIL minimums as the service. Lightning arresters are recommended on the Primary Service Pole, must be tested to ANSI/IEEE C62.11, and must include a ground-lead isolator; where the main device is pole-mounted, arresters connect on its load side.


4.5  Transformer Connection Rules


Two winding-connection restrictions apply to the customer’s medium-voltage system and must be reflected in the one-line and transformer selections:


  • Grounded-wye primary to delta secondary transformers shall not be used on the customer’s 12 kV or 35 kV distribution system.
  • Transformers with ungrounded primary connections (delta or ungrounded wye) shall not be used on the customer’s 35 kV distribution system.


4.6  Capacitor Banks


A customer wishing to install a 12 kV or 35 kV capacitor bank must submit a description of the bank and its control to CNP, and CNP may require load- or power-factor-sensitive switching. Customers with harmonic-producing loads may be required to install harmonic filters in accordance with the harmonic specification . Because capacitors can create resonance with harmonic sources, capacitor application on a data-center system must be coordinated with the harmonic evaluation.


4.7  Overhead vs. Underground Primary Service


Overhead service centers on the customer’s Primary Service Pole, which must be designed for CNP’s adopted extreme-wind loading (110 mph north of US 59 / Hwy 90, 132 mph south of US 59 / Hwy 90) and located a minimum of 50 feet from the CNP metering pole with all-weather truck access.


Underground service is handled by CNP’s Major Underground Engineering group, may be served from outdoor (pad-mounted) or indoor facilities, and is delivered with a project-specific Terms & Conditions package; cable from the metering cabinet or vault must be in concrete-encased conduit (direct burial is not permitted). For a large campus, the design stage typically develops a primary overhead route into the site with major underground utilities on site connecting to the overhead system.


5.  Harmonic Distortion Control (Spec 083, Rev. 3)


This specification places responsibility for limiting harmonic flow into the CNP system on the customer and reflects IEEE 519-2014 and PUCT Rule 25.51. CNP may refuse to energize a non-compliant service and may measure the customer’s harmonic injection at the point of common coupling (PCC) at any time. Measurement instruments follow IEC 61000-4-7 and IEC 61000-4-30.


5.1  Why It Matters for a Data Center


A data center is dominated by non-linear electronic loads — UPS rectifiers, switch-mode power supplies, and variable-frequency-drive cooling — that draw current in a non-sinusoidal manner. CenterPoint notes that electronic power converters typically create current distortion on the order of 20–30% of rating for three-phase equipment. Left unmanaged, that distortion can exceed CNP’s limits, disrupt other customers, and prevent energization. Harmonic compliance is therefore a substantive design task, not a check-the-box item.


5.2  Current Distortion Limits (Iₛₜ/Iₗ and TDD)


Allowable harmonic current injection is expressed as a percentage of the maximum demand load current (Iₗ), and the allowance grows as the short-circuit-to-load ratio (Iₛₜ/Iₗ) at the PCC grows. The table below reproduces CNP’s current distortion limits (from IEEE 519-2014, Table 2). Even-order harmonics are limited to 25% of the odd-order limits, and — importantly for backup generation — all power-generation equipment is held to the most stringent (“< 20”) row regardless of the actual Iₛₜ/Iₗ. Distortions that produce a DC offset (e.g., half-wave converters) are not allowed.

Iₛₜ / Iₗ 3≤h<11 11≤h<17 17≤h<23 23≤h<35 35≤h<50 TDD
< 20 4.0 2.0 1.5 0.6 0.3 5.0
20 – 50 7.0 3.5 2.5 1.0 0.5 8.0
50 – 100 10.0 4.5 4.0 1.5 0.7 12.0
100 – 1000 12.0 5.5 5.0 2.0 1.0 15.0
> 1000 15.0 7.0 6.0 2.5 1.4 20.0

6.  Emergency Generation & Secondary Load Transfer (Spec 082, Rev. 1)


6.1  Emergency / Backup Generation


Customer-owned emergency generation must connect to the customer’s load through either an open-transition transfer switch or a key-interlocked two-breaker / switch arrangement that prevents any electrical or physical connection between the CNP system and the customer’s generator bus. Standby generators must sit on the load side of the meter, behind the main device; no transfer switch is allowed on the high (CNP) side of the meter. The generator and its exhaust must be located where they do not interfere with CNP personnel or equipment, and the location must be approved by CNP.


Operating a generator in parallel with the CNP system (closed transition) is an exception that is granted only when the customer installs protective devices in accordance with PUCT Substantive Rule 25.212 and CNP’s customer-generation specification (007-231-76) at the interconnection point, and when generator voltage and current distortion comply with IEEE 519. Customers served from a CNP secondary network may not parallel generators with CNP at all. Recall also that, under the harmonic specification, generation equipment is held to the most stringent harmonic-distortion category.


6.2  Secondary Load Transfer


Where a customer’s split load is served from two CNP feeds, the buses from each feed must be electrically isolated from one another, and load transfers must be performed manually using open-transition transfer switches or breakers — automatic transfer by the customer is not permitted without CNP Engineering approval. Before transferring, the customer must shed an equal or greater amount of pre-approved load on the receiving feed so the normal load level is never exceeded. Secondary load transfer is offered only under separate contractual arrangements, requires submission of a load-transfer schedule, and is documented in an Operational Agreement.


7.  Motor Starting Review

Any motor rated 250 HP or larger must be reviewed by CNP’s power-quality engineer using the Motor Start Review Form. The form captures service information (service name and address, circuit and section, transformer GLN, service voltage, transformer type), present and future kVA demand, and — for each motor or motor group — a data table including the number of motors, horsepower, phase, voltage, full-load amps, locked-rotor amps, code letter (locked-rotor kVA per HP), required starting frequency, whether the motor starts under load, and the starting method. Recognized starting methods are full-voltage / across-the-line (FVS), auto-transformer reduced-voltage (ATRF), capacitor start (CAPS), star-start delta-run (SSDR), and other (OTHR). Where motors start simultaneously, a description of the scheme must be attached. For a data center, large chillers and pumps are the most likely candidates to trigger this review.


8.  The Article 9.0 Submittal Package


Before any construction to serve the customer may begin, CenterPoint requires a submittal package to be reviewed and approved. CNP typically identifies the following items (per Article 9.0 and project-specific guidance):

Submittal Item Applies When
Basic primary one-line showing the main protective device and all primary-connected transformers (kVA + winding configurations) Always
All electrical equipment downstream of the CNP interconnection Always
Load analysis listing conventional loads and harmonic-producing loads (kVA), with harmonic-compliance documentation (per 083) Always
Detail of harmonic-producing loads Always
Customer plot plan of property and facilities Always
Primary service pole profile with main protective device and clearances Overhead service
Major equipment data (manufacturer, catalog, specs) — service pole / underground arrangement Always
Capacitor bank information (Article 8.0) If capacitors used
Motor starting information — motors ≥ 250 HP (Motor Start Review Form) If applicable
Emergency backup generator information (per 082) If generators used

9.  The Design-Stage Process & the Substation Question


CenterPoint has advised that the design stage is approximately a three-to-six-month process. During this stage, CNP develops the primary overhead design into the site and the major underground utilities on site that connect to the overhead system. Critically, if a substation is required to serve the load, that requirement is identified during this stage. In parallel, CNP’s power-quality engineer reviews and approves the customer’s major equipment and prepares the Operational Agreement. Only after these steps are complete does CNP finalize its construction costs; payment then allows construction to commence.


Because a data-center-scale load sits well above the single-service thresholds, the central engineering question of the design stage is whether the load can be served from existing infrastructure through multiple primary services or whether dedicated substation infrastructure is the controlling path. Producing a defensible answer early — grounded in the load analysis, service-voltage selection, and CNP’s feedback — is one of the most valuable outcomes of this phase.


Operational Agreement triggers.  An Operational Agreement is required when the customer uses a circuit breaker as the main protective device, does not install a bypass switch on the Primary Service Pole, operates generation in parallel with CNP, or receives service from two CNP feeds with the ability to transfer load. A large data-center service is likely to trigger more than one of these.



10.  What This Means for a Large Data-Center Project


Bringing the requirements together, several implications follow directly for a large data-center load in the CenterPoint service area:


  • Service configuration: at roughly an order of magnitude above the single-service splitting thresholds, the facility should anticipate multiple primary services and/or dedicated substation infrastructure; 35 kV service merits evaluation to reduce current and service count.
  • Protection: a circuit-breaker main device (not fuses) will be required, with customer-set, CNP-verified relay coordination, no automatic reclosing, and one or more Operational Agreements.
  • Harmonics: the UPS / rectifier / VFD load makes IEEE 519 compliance a real design driver; a harmonic model and, likely, a mitigation strategy will be needed, and any capacitors must be coordinated to avoid resonance.
  • Transformers: winding connections must respect the prohibitions (no grounded-wye / delta on the customer system; no ungrounded primary at 35 kV).
  • Backup generation: open-transition or key-interlocked connection on the load side of the meter, with the stricter generation harmonic category, and additional protection if parallel operation is ever desired.
  • Large motors: chillers or pumps rated 250 HP and larger will trigger the Motor Start Review.
  • Process: the substation determination, equipment approval, and Operational Agreement are CNP-controlled and occur over the three-to-six-month design stage before final costs are set.


Large data-center programs are frequently advanced in phases — for example, an initial build served at the distribution-primary level through CenterPoint’s design process described here, and a larger build that crosses into transmission-level service and the ERCOT large-load study process. The requirements in this paper apply principally to the distribution-level work; a transmission-level interconnection introduces additional ERCOT modeling deliverables (load data, dynamic, and PSCAD / EMT models) that are addressed separately.


A smiling man with glasses and a beard wearing a blue blazer stands in front of server racks in a data center.

About the Author:

Sonny Patel P.E. EC

IEEE Senior Member

In 1995, Sandip (Sonny) R. Patel earned his Electrical Engineering degree from the University of Illinois, specializing in Electrical Engineering . But degrees don’t build legacies—action does. For three decades, he’s been shaping the future of engineering, not just as a licensed Professional Engineer across multiple states (Florida, California, New York, West Virginia, and Minnesota), but as a doer. A builder. A leader. Not just an engineer. A Licensed Electrical Contractor in Florida with an Unlimited EC license. Not just an executive. The founder and CEO of KEENTEL LLC—where expertise meets execution. Three decades. Multiple states. Endless impact.

Four workers in safety vests and helmets stand with arms crossed near wind turbines.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sonny Patel P.E. EC

IEEE Senior Member

In 1995, Sandip (Sonny) R. Patel earned his Electrical Engineering degree from the University of Illinois, specializing in Electrical Engineering . But degrees don’t build legacies—action does. For three decades, he’s been shaping the future of engineering, not just as a licensed Professional Engineer across multiple states (Florida, California, New York, West Virginia, and Minnesota), but as a doer. A builder. A leader. Not just an engineer. A Licensed Electrical Contractor in Florida with an Unlimited EC license. Not just an executive. The founder and CEO of KEENTEL LLC—where expertise meets execution. Three decades. Multiple states. Endless impact.

Leave a Comment

Related Posts

Automating PSS®/E with Python for power system studies
By SANDIP R PATEL June 27, 2026
Learn how to automate PSS®/E with Python for power system studies, API scripting, result extraction, and scalable interconnection workflows.
Insulation coordination and switching overvoltage analysis in PSCAD EMTDC
By SANDIP R PATEL June 23, 2026
Learn how switching overvoltage studies, insulation coordination, surge arrester assessment, and PSCAD/EMTDC modeling protect EHV systems.
Parallel EMTDC simulation for large-scale power system studies
By SANDIP R PATEL June 23, 2026
Learn how Concurrent EMTDC uses data parallelism, task parallelism, PSCAD, and high-performance interconnects to accelerate EMT simulation studies.
Substation electrical design engineering workflow
By SANDIP R PATEL June 23, 2026
Learn the complete substation electrical design process, including 30%, 60%, 90%, and IFC deliverables, engineering reviews, grounding, protection, and interconnection requirements.
PJM's Expedited Interconnection Track (EIT) — What 250 MW+ Developers Must Know
By SANDIP R PATEL June 21, 2026
FERC accepted PJM's Expedited Interconnection Track on June 9, 2026. Learn the eligibility rules, financial requirements, state siting commitment, and engineering checklist for the 10-month fast lane to a signed GIA.
Grid interconnection feasibility and transmission planning
By SANDIP R PATEL June 21, 2026
Estimate interconnection costs before entering the queue. Learn how network upgrade costs, POI costs, and feasibility studies impact project success.
Power system resilience performance metrics
By SANDIP R PATEL June 20, 2026
Learn how power system resilience metrics measure grid performance during extreme events. Discover resilience assessment methods and practical applications.
Synchronous condenser protection and control diagram
By SANDIP R PATEL June 20, 2026
Learn synchronous condenser protection, loss of field settings, NERC PRC compliance, and protection philosophy. Discover expert engineering guidance.
PSCAD black-box EMT model development workflow
By SANDIP R PATEL June 20, 2026
Learn how PSCAD Black Box and Independent C Code protect EMT models, secure control IP, and support interconnection-grade studies. Discover more.