A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.

Substation Engineering Case Studies: Design, Protection & System Studies

Date icon D

May 3, 2025 | Blog

Complete Substation Engineering Case Studies: Design, Protection & System Studies

Below are four flagship projects where Keentel Engineering delivered end-to-end substation design (primary, secondary) and comprehensive power system studies to ensure safe, reliable, and standards-compliant installations.


345 kV EHV Greenfield Substation

Project Scope

Design and build of a new 345 kV / 138 kV transmission substation to integrate 400 MW of wind generation into the regional grid.

Primary Design Services

  • Full primary layout (GA) drawings with major equipment placement and conductor routing
  • Transformer, breaker, disconnect switch, CT/VT, and wave-trap specifications
  • 4 000 A tubular aluminum rigid bus design
  • IEEE Std 80™ grounding grid analysis using CDEGS

Secondary Design Services

  • Protection & control single-line diagrams and wiring schematics
  • AC/DC auxiliary systems with IEEE Std 485™ battery sizing
  • RTU/SCADA integration: point mapping and telemetry configuration

Power System Studies

  • Short-circuit (IEEE C37.010)
  • Load flow & reactive power planning
  • Protection coordination (SEL-411L, SEL-351, SEL-487E)
  • Arc-flash hazard analysis (IEEE 1584-2018)
  • Ground grid step/touch voltage assessment

Key Deliverables & Impact

  • 150+ IFC drawing sets & equipment BOM
  • PE-sealed engineering certification in multiple states
  • Successful substation energization with zero safety incidents
  • “Proactive RFI responses” earned ongoing preferred-partner status

230 kV GIS Substation Expansion

Project Scope

Expansion and modernization of an existing 230 kV gas-insulated substation, adding two new feeders and upgrading legacy protection.

Primary Design Services

  • 3D CAD-based GIS bay layout modifications
  • New feeder bay and duct-bank routing
  • Civil coordination for control building enlargement

Secondary Design Services

  • IEC 61850 digital protection scheme design
  • Microprocessor relay replacements (SEL/GE)
  • Digital fault recorder (DFR) installation and disturbance monitoring

Power System Studies

  • Breaker duty analysis
  • Relay coordination & selectivity for transmission line protection
  • Transient stability (NERC TPL)
  • EMTP modeling for breaker TRV assessment

Key Deliverables & Impact

  • Updated one-line, three-line, and P&C schematics
  • Comprehensive settings database
  • Arc-flash labeling across new and retrofitted equipment
  • Expansion completed without any substation outage, earning additional retrofit work

115 kV / 34.5 kV Collector Substation (BESS)

Project Scope

EPC-level design for a 100 MW / 400 MWh battery energy storage collector substation tying into a 115 kV network.

Primary Design Services

  • Space-optimized layout under site constraints
  • Single-bus configuration with future breaker-and-a-half provision
  • 75–125 MVA transformer with on-load tap changer

Secondary Design Services

  • Transformer differential (87T) and bus protection (87B) schemes
  • BMS integration for trip signaling
  • Dual-fiber protection & redundant SCADA architecture

Power System Studies

  • Load flow for capacitor bank optimization
  • Fault analysis including BESS short-circuit contribution
  • Harmonic study for IBR interactions
  • EMT switching transient analysis for inverter protection

Key Deliverables & Impact

  • IFC drawings & FAT support docs
  • Detailed commissioning & relay-setting plans
  • First large-scale BESS substation for the client, delivered in under 12 months
  • Performance exceeded interconnection guarantees

500 kV Bulk Power Substation

Project Scope

Greenfield design of a 500 kV / 230 kV bulk substation on a major interregional corridor, enhancing transfer capability by 1 200 MW.

Primary Design Services

  • Breaker-and-a-half arrangement
  • 500 kV gas circuit breaker & disconnect switch specifications
  • High-ampacity rigid/strain bus with seismic considerations

Secondary Design Services

  • High-speed fiber-based bus differential protection
  • Line differential & distance protection coordination
  • N-1/N-2 redundant protection zoning

Power System Studies

  • Interconnection SIS modeling
  • EMT study for breaker restrike/TRV risks
  • GIC impact assessment (NERC TPL-007)
  • NERC TPL reliability assessment

Key Deliverables & Impact

  • 400+ page Engineering Study Report & IFC drawings
  • FAT/SAT checklists, commissioning manuals, and staff training
  • Early energization ahead of compliance deadlines, securing client recognition

Why Clients Choose Keentel Engineering

  • Integrated Primary & Secondary Design under one roof
  • Advanced Modeling & Studies: PSSE, PSCAD, EMTP, CDEGS
  • NERC & IEEE Expertise: PRC, TPL, 1584, 80, 485, 2800 compliance
  • First-Time ISO Acceptance with minimal RFIs
  • Repeat Business driven by reliability, responsiveness, and precision

Ready for Your Next Substation Project?

Explore our Electrical Substation Design Services and partner with Keentel Engineering to deliver turnkey, standards-compliant substations—on time and on budget.


A bald man with a beard is wearing a suit and a white shirt.

About the Author:

Sonny Patel P.E. EC

IEEE Senior Member

In 1995, Sandip (Sonny) R. Patel earned his Electrical Engineering degree from the University of Illinois, specializing in Electrical Engineering . But degrees don’t build legacies—action does. For three decades, he’s been shaping the future of engineering, not just as a licensed Professional Engineer across multiple states (Florida, California, New York, West Virginia, and Minnesota), but as a doer. A builder. A leader. Not just an engineer. A Licensed Electrical Contractor in Florida with an Unlimited EC license. Not just an executive. The founder and CEO of KEENTEL LLC—where expertise meets execution. Three decades. Multiple states. Endless impact.

A group of construction workers are standing next to each other with their arms crossed.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

A bald man with a beard is wearing a suit and a white shirt.

About the Author:

Sonny Patel P.E. EC

IEEE Senior Member

In 1995, Sandip (Sonny) R. Patel earned his Electrical Engineering degree from the University of Illinois, specializing in Electrical Engineering . But degrees don’t build legacies—action does. For three decades, he’s been shaping the future of engineering, not just as a licensed Professional Engineer across multiple states (Florida, California, New York, West Virginia, and Minnesota), but as a doer. A builder. A leader. Not just an engineer. A Licensed Electrical Contractor in Florida with an Unlimited EC license. Not just an executive. The founder and CEO of KEENTEL LLC—where expertise meets execution. Three decades. Multiple states. Endless impact.

Leave a Comment

Related Posts

A man in an orange vest is typing on a laptop computer.
By SANDIP R PATEL May 30, 2025
Explore the latest updates from NERC.com and what modernization means for power engineers and grid operators across the U.S.
A row of power lines are silhouetted against a blue sky at sunset.
By SANDIP R PATEL May 30, 2025
Dive deep into power system stability analysis with PSSE, TSAT, and PSCAD/EMTDC—from positive sequence to EMT simulations.
A man wearing a hard hat and safety glasses is using a tablet computer.
By SANDIP R PATEL May 30, 2025
Learn how power system operators can manage data for inverter-based resources (IBRs) using advanced information management practices.
A man is sitting at a desk in front of a computer monitor.
By SANDIP R PATEL May 30, 2025
Understand model accuracy and validation methods in EMT and PSPD simulations for inverter-based resources using top simulation tools.
A man and a woman are looking at a map.
By SANDIP R PATEL May 30, 2025
Explore best practices to ensure design stability in power systems and stay ahead of NERC reporting requirements in upcoming compliance cycles.
Change Management Process in Power Systems
By SANDIP R PATEL May 30, 2025
Discover how structured change management enhances planning and operations in modern power systems for greater reliability and compliance.
PJM Manual 14G Interconnection Services By Keental Engineering
By SANDIP R PATEL May 28, 2025
Navigate PJM generation interconnection with Keentel Engineering. We specialize in queue management, POI support, CIRs, feasibility studies, and SCADA compliance.
NERC Level 3 Alert IBR Generator Owners Compliance Checklist Power System Modeling Model Accuracy
By SANDIP R PATEL May 23, 2025
Get your compliance checklist for NERC Level 3 alerts. Essential reading for IBR generator owners navigating updated NERC requirements.
Integrative Applications of IEEE C57 Series Standards for Reliable and Compliant Substation Design
By SANDIP R PATEL May 21, 2025
Explore how IEEE C57 series standards support transformer reliability, substation diagnostics, and utility compliance in modern substation design.