A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.
Challenge: Frequent false tripping using conventional electromechanical relays
Solution: SEL-487E integration with multi-terminal differential protection and dynamic inrush restraint
Result: 90% reduction in false trips, saving over $250,000 in downtime
| Category | Metric |
|---|---|
| VPP capacity (Lunar Energy) | 650 MW |
| Lunar funding raised | US$232 million |
| Data center BESS example | 31 MW / 62 MWh |
| ERCOT grid-scale batteries | 15+ GW |
| LDES tenders (H1 2026) | Up to 9.3 GW |
| Lithium-ion share of LDES by 2030 | 77% |
| FEOC initial threshold | 55% |
| BESS tariff rate (2026) | ~55% |
| Capacity gain from analytics | 5–15% |
PJM’s Distribution-Level Interconnection Reform:Eliminating “First Use” in the Era of FERC Order 2222
Apr 7, 2026 | blog
Introduction
The U.S. power grid is undergoing a structural transformation driven by the rapid growth of Distributed Energy Resources (DERs) such as solar PV, battery storage, EVs, and demand response technologies. To accommodate this shift, PJM Interconnection has proposed a major regulatory reform: elimination of the “First Use” rule for distribution-level interconnections.
Filed with FERC in October 2025 and supported unanimously by stakeholders, this reform is designed to:
- Simplify interconnection pathways
- Reduce regulatory overlap
- Accelerate DER deployment
- Align PJM processes with FERC Order No. 2222
This article provides a deep technical and regulatory breakdown of PJM’s proposal, its engineering implications, and how it reshapes the future of DER integration.
Background: DER Growth and FERC Order No. 2222
What is FERC Order 2222?
FERC Order No. 2222 (2020) was a landmark ruling aimed at:
- Enabling aggregated DER participation in wholesale markets
- Removing barriers for small-scale distributed resources
- Promoting grid flexibility, reliability, and competition
DERs include:
- Rooftop solar
- Battery energy storage systems (BESS)
- Electric vehicles and charging infrastructure
- Smart thermostats and demand response systems
- Energy efficiency and thermal storage systems
Because individual DERs are often too small, Order 2222 allows them to aggregate into a single market participant, enabling participation in:
- Energy markets
- Capacity markets
- Ancillary services markets
Why This Matters for PJM
PJM, as an RTO, must integrate:
- Thousands of small DERs
- Increasing interconnection requests
- Complex coordination between:
- Transmission systems (FERC jurisdiction)
- Distribution systems (state/local jurisdiction)
This complexity exposed limitations in PJM’s existing framework especially the “First Use” rule.
The “First Use” Rule: A Legacy Constraint
How It Works
The “First Use” rule determines jurisdiction over interconnection facilities:
- First generator connecting to a distribution line:
- Uses state/local interconnection agreement + WMPA
- Subsequent generators:
- Facility becomes “dual-use”
- Requires PJM GIA (FERC jurisdiction)
As illustrated in the diagram on page 3, once wholesale power flows through a distribution facility, it triggers federal oversight for all future interconnections.
Key Problems Identified
1. Regulatory Confusion
Developers struggle to determine whether:
- PJM (FERC) rules apply
- Or state/local interconnection rules apply
2. Inefficiency
Small projects (even <5 MW) are forced into:
- Full PJM interconnection queue
- Lengthy study processes
3. Operational Burden
- Transmission Owners (TOs) must track “dual-use” assets
- PJM queue congestion increases
4. Misalignment with DER Policy
FERC Order 2222 explicitly supports:
- State/local control for DER interconnections
- Aggregated participation without unnecessary barriers
PJM’s Proposed Reform: Elimination of “First Use”
Core Concept
PJM proposes that:
- All distribution-level resources interconnect through state/local processes and use WMPA for market participation instead of PJM GIA.
Confirmed in page 2 (Key Takeaway) of the presentation.
What Changes?
| Aspect | Current (First Use) | Proposed Reform |
|---|---|---|
| Jurisdiction | Mixed (state + FERC) | Clearly defined |
| Small DER Projects | PJM GIA required (often) | State/local IA only |
| Market Access | Via GIA | Via WMPA |
| Complexity | High | Reduced |
Bright-Line Test: Engineering-Based Jurisdiction
To remove ambiguity, PJM introduces a voltage-based classification :
- ≥ 69 kV → Transmission → PJM GIA (FERC jurisdiction)
- < 69 kV → Distribution → State/local IA + WMPA
Clearly shown on page 6 of the PDF.
Why This Matters (Engineering Perspective)
This aligns jurisdiction with physical system characteristics:
- Transmission systems → Bulk power transfer
- Distribution systems → Local load and DER integration
It simplifies:
- Study scope
- Protection coordination responsibility
- Planning authority
Alignment with Order 2222: A Critical Link
FERC Order 2222 states:
- DER interconnections to distribution systems should not fall under transmission interconnection rules
- Aggregations should enable participation without overburdening RTO processes
PJM’s compliance language (page 4) confirms:
- DER interconnections are governed by state/local law
- PJM focuses on market participation, not physical interconnection
Operational Benefits of the Reform
1. Faster Interconnection Timelines
- Removes PJM queue delays for small projects
- Enables faster deployment of solar + BESS
2. PJM Resource Optimization
- Staff can focus on:
- Large transmission projects
- Reliability-critical studies
3. Increased DER Penetration
- Simplified entry for:
- Community solar
- Behind-the-meter systems
- Microgrids
4. Improved Cost Transparency
- Developers gain early clarity on:
- Upgrade costs
- Scope
- Timeline
Dispute Resolution and Governance
PJM includes a structured dispute framework:
- Resolution options:
- Bilateral agreements
- State/local processes
- PJM tariff mechanisms
- Must be resolved before Phase I studies
Detailed in page 7 of the presentation.
What Is Not Affected
1. PURPA Qualifying Facilities (QFs)
- Governed under separate federal law
2. DER Aggregation Model (Order 2222)
- Aggregations:
- Use DAPSA agreements
- Do not enter PJM interconnection queue
Confirmed on page 9.
Engineering Implications for Developers and Utilities
This reform fundamentally changes project execution strategy:
For Developers
- Focus shifts to:
- Utility distribution studies
- Hosting capacity analysis
- Protection coordinatio
For Engineers (Keentel Perspective)
Critical studies will include:
- Distribution load flow
- Short circuit analysis
- Protection coordination
- Voltage regulation and flicker
- DER integration studies
For Utilities
- Increased responsibility for:
- Interconnection approval
- Grid impact studies
- Local reliability
Implementation Timeline
- PJM Filing: October 1, 2025
- Stakeholder Approval: September 25, 2025
- Expected Effective Date: April 28, 2026
Conclusion
PJM’s elimination of the “First Use” rule represents a paradigm shift in interconnection policy. It aligns regulatory structure with:
- The decentralized nature of DERs
- FERC Order 2222 objectives
- Modern grid operational realities
This reform will:
- Reduce interconnection bottlenecks
- Accelerate renewable deployment
- Improve coordination between RTOs and utilities
For engineering firms like Keentel Engineering this opens opportunities in:
- Distribution-level studies
- DER integration
- Utility coordination
- Compliance and interconnection support
Technical FAQ (Enhanced – SEO Ready)
1. What is the First Use rule in PJM?
A regulatory test determining when a distribution facility becomes subject to FERC jurisdiction after initial wholesale use.
2. Why is PJM eliminating First Use?
To reduce complexity, improve efficiency, and align with DER-focused policies under FERC Order 2222.
3. What is FERC Order 2222?
A rule enabling aggregated DERs to participate in wholesale electricity markets through RTOs.
4. What are DERs?
Small-scale energy resources such as solar, battery storage, EVs, and demand response systems.
5. What is a DER aggregation?
A grouping of multiple small DERs combined to meet market participation requirements.
6. What is a WMPA?
A Wholesale Market Participation Agreement that allows resources to participate in PJM markets without a full GIA.
7. What is the Bright-Line test?
A voltage-based rule:
- ≥69 kV → Transmission
- <69 kV → Distribution
8. How does this impact solar and BESS projects?
They will benefit from faster and simpler interconnection processes.
9. Will projects still need system studies?
Yes, but primarily at the distribution utility level, not PJM.
10. What markets can DERs participate in?
- Energy
- Capacity
- Ancillary services
11. Does this reduce PJM queue congestion?
Yes, by removing smaller distribution-level projects from the queue.
12. Who regulates distribution interconnections?
State and local regulatory authorities.
13. What is DAPSA?
DER Aggregator Participation Service Agreement used for aggregated DER participation.
14. When will PJM implement this change?
Expected April 28, 2026, pending FERC approval.
15. What should developers do now?
- Engage with utilities early
- Understand state interconnection processes
- Prepare for DER aggregation opportunities
Conclusion
Solid-State Transformers are redefining how power is delivered especially in data centers. But their successful deployment depends on accurate, validated modeling across both RMS and EMT domains.
Keentel Engineering brings the expertise, tools, and experience needed to deliver high-fidelity
modeling solutions that enable confidence, compliance, and scalability.

About the Author:
Sonny Patel P.E. EC
IEEE Senior Member
In 1995, Sandip (Sonny) R. Patel earned his Electrical Engineering degree from the University of Illinois, specializing in Electrical Engineering . But degrees don’t build legacies—action does. For three decades, he’s been shaping the future of engineering, not just as a licensed Professional Engineer across multiple states (Florida, California, New York, West Virginia, and Minnesota), but as a doer. A builder. A leader. Not just an engineer. A Licensed Electrical Contractor in Florida with an Unlimited EC license. Not just an executive. The founder and CEO of KEENTEL LLC—where expertise meets execution. Three decades. Multiple states. Endless impact.
Services

Let's Discuss Your Project
Let's book a call to discuss your electrical engineering project that we can help you with.

About the Author:
Sonny Patel P.E. EC
IEEE Senior Member
In 1995, Sandip (Sonny) R. Patel earned his Electrical Engineering degree from the University of Illinois, specializing in Electrical Engineering . But degrees don’t build legacies—action does. For three decades, he’s been shaping the future of engineering, not just as a licensed Professional Engineer across multiple states (Florida, California, New York, West Virginia, and Minnesota), but as a doer. A builder. A leader. Not just an engineer. A Licensed Electrical Contractor in Florida with an Unlimited EC license. Not just an executive. The founder and CEO of KEENTEL LLC—where expertise meets execution. Three decades. Multiple states. Endless impact.
Leave a Comment
We will get back to you as soon as possible.
Please try again later.
















