A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.

PJM Dynamic Modeling & Interconnection Case Studies

Calendar icon. D

May 9, 2025 | Blog

Control room with people monitoring screens, a large display, and power lines in the background.

At Keentel Engineering, our proven dynamic modeling and interconnection expertise has supported utility-scale solar, battery energy storage systems (BESS), hybrid Solar + BESS facilities, and synchronous generator repowering projects across PJM’s footprint. Leveraging Siemens PSS®E and PSCAD simulations, user-defined model (UDM) development, and strict adherence to NERC and PJM criteria, we deliver audit-ready submissions that eliminate resubmittals, accelerate queue approvals, and ensure Bulk Electric System reliability. Explore how our tailored solutions—from PSS®E flat-start studies to hybrid inverter coordination—have achieved first‐pass acceptance and on-time energization for our clients.


Case Study 1

Dynamic Modeling for a 150 MW Solar PV Plant (Confidential Project A – New Jersey)

Challenge

A utility-scale solar developer submitted a 150 MW New Service Request to PJM with an aggressive timeline to secure queue placement. They faced a challenge in preparing dynamic models that complied with PJM’s strict inverter‐based resource (IBR) modeling criteria, particularly regarding momentary cessation and power factor control.

Keentel Engineering Solution

  • Developed compliant  .idv  and  .dyr  files using REGCA1, REECA1, and REPCA1 models tailored to the specific inverter type.
  • Conducted full flat start, VRT, and primary frequency response simulations using Siemens PSS®E v35.3.2.
  • Eliminated momentary cessation per Section 7.5 and validated Qmax/Qmin from PQ curves at 95 °F ambient temperature.

Outcome

PJM accepted the submission without any data deficiency flags. The developer avoided resubmission delays, and Keentel’s documentation package met all deliverables under Section 8 of the guidelines.


Case Study 2

As-Built Model Resubmission with UDM for a 50 MW BESS (Confidential Project B – Pennsylvania)

Challenge

A 50 MW standalone battery storage project had commissioned with a proprietary inverter model not covered by PJM’s approved library models. The developer faced rejection of their As-Built submission due to lack of a validated user-defined model (UDM).

Keentel Engineering Solution

  • Worked with inverter OEM to extract control logic, DLLs, and source code for the BESS inverter dynamic behavior.
  • Created and tested UDMs with REECC1 and REGCBU1 modules to represent grid-charging behavior per REECC guidelines.
  • Generated a complete UDM documentation packet including block diagrams, parameter explanations, and test logs.

Outcome

The As-Built submission passed PJM review. The FAT report, required under Section 8 for main power transformers, was integrated into the submission. Project achieved interconnection compliance within 30 days of re-submission.


Case Study 3

Multi-Inverter Model for Hybrid Solar + BESS Facility (Confidential Project C – Maryland)

Challenge

A hybrid facility with 120 MW solar and 40 MW BESS had different inverter types and control logics. PJM required a detailed model that accurately represented both technologies using multi-generator equivalents, and plant-level coordination via PLNTBU1.

Keentel Engineering Solution:

  • Developed separate REGC and REEC modules for each inverter type and integrated PLNTBU1 for coordinated control.
  • Modeled PQ curves with inverter-specific data for accurate Qmax/Qmin limits.
  • Included VTGTPAT and FRQTPAT relay models with protection curves compliant with NERC PRC-024-3.

Outcome

The hybrid project submission was approved in the first cycle with no supplemental data requests. The model was lauded for clearly representing shared POI behavior and frequency ride‐through settings, making it a PJM internal example for hybrid configurations.


Case Study 4

Repowering of Existing Synchronous Generator (Confidential Project D – West Virginia)

Challenge

An older 100 MW coal-fired synchronous unit was being upgraded with new excitation and governor systems. The repowered unit required an updated dynamic model that matched current operating characteristics and included necessary power factor and saturation curve validation.

Keentel Engineering Solution:

  • Replaced legacy GENCLS and SEXS models with GENSAL and EXST1 for detailed generator behavior.
  • Integrated PSS (Power System Stabilizer) and AVR limiter models to enhance transient stability representation.
  • Completed MFO and power factor assessments per Section 7.1 and 7.2, including summer and winter operating conditions.

Outcome

The updated model allowed the facility to be requalified under its interconnection agreement. PJM approved the repowering study without requiring a PSCAD model, accelerating re-energization approvals.


Want to learn more? Check out our Power System Studies and POI Interconnection Engineering Support services for details on our dynamic and interconnection capabilities.



A smiling man with glasses and a beard wearing a blue blazer stands in front of server racks in a data center.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.

Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads 51 engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering

Four workers in safety vests and helmets stand with arms crossed near wind turbines.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads 51 engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering

Leave a Comment

Related Posts

12.47 kV pole-mounted distribution transformer assembly designed for U.S. IEEE and NESC utility stan
By SANDIP R PATEL August 20, 2026
Learn U.S. pole-mounted transformer design requirements, including IEEE, ANSI, and NESC standards, voltage classes, grounding, protection, and DER considerations.
PRC-023-6 BESS relay loadability compliance guide
By SANDIP R PATEL August 19, 2026
Understand PRC-023-6 for utility-scale BESS: applicability, the 39-month rule, relay loadability, setting criteria, Category 2 IBRs, and audit evidence.
PRC-029-1 voltage ride-through envelope for inverter-based resources.
By SANDIP R PATEL August 18, 2026
Learn PRC-029-1 compliance requirements for inverter-based resources, including voltage and frequency ride-through, EMT studies, protection settings, and testing.
Solar plant electrical testing and commissioning for utility-scale PV systems
By SANDIP R PATEL August 17, 2026
A technical guide to solar plant electrical testing, commissioning, I-V curves, thermography, insulation testing, cable tests and performance acceptance.
Alt Text: Gas-insulated substation engineering guide covering GIS safety, reliability, VFTO, partial
By SANDIP R PATEL August 16, 2026
Explore GIS substation engineering, including design, SF6 safety, VFTO, grounding, commissioning, testing, GIS vs AIS, and IEEE/IEC standards.
Cable testing before energization engineering guide
By SANDIP R PATEL August 16, 2026
Learn the correct cable testing sequence before energization, including VLF, AC/DC withstand, sheath testing, partial discharge, tan delta, and standards.
substation drawing sets
By SANDIP R PATEL August 16, 2026
Explore how substation drawing sets are developed, reviewed and controlled through engineering studies, design milestones, QA/QC and final construction release.
Grid-forming vs grid-following BESS inverters
By SANDIP R PATEL August 15, 2026
Compare grid-forming vs grid-following BESS inverters, control loops, weak-grid stability, protection, compliance, and interconnection study impacts.
MOD-025 and MOD-026 post-COD verification testing with PSS E and PSCAD dynamic model validation
By SANDIP R PATEL August 15, 2026
Learn MOD-025 and MOD-026 post-COD requirements for generator capability verification, PSS®E and PSCAD model validation, IBR testing, and NERC compliance.