A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.

PSCAD Power System Studies: Four Real-World Case Studies

Calendar icon. D

May 5, 2025 | Blog

Person looking at two computer monitors displaying technical diagrams and graphs.

PSCAD (Power Systems Computer Aided Design) is the industry standard for high-fidelity electromagnetic transient (EMT) and dynamic studies. At Keentel Engineering, our PSCAD modeling services help utilities, renewable developers, and independent power producers validate grid interconnection performance, ensure ride-through compliance, and optimize protection schemes. Below are four detailed case studies showcasing how our PSCAD-driven power system studies delivered actionable insights and millions in cost savings.


Case Study 1
Transient Stability Analysis for a 345 kV Renewable Interconnection

Client: Confidential Renewable Energy Developer (Midwest, USA)
Scope: 600 MW combined wind + BESS interconnection at a 345 kV POI adjacent to a weak grid.
Challenge: Verify ride-through capability, critical clearing times, and voltage recovery under fault conditions per NERC PRC-024-2.

Keentel Solution

  • Developed detailed PSCAD models for wind turbines, BESS converters, collector system, and substation.
  • Simulated three-phase, single-line-to-ground, and double-line-to-ground faults.
  • Determined breaker critical clearing times and evaluated dynamic reactive support needs.

Results

  • Demonstrated full compliance without adding reactive support equipment.
  • Saved the client $2 million in avoided hardware upgrades.

Case Study 2
EMT Simulation of Inverter-Based Resources in a Weak 115 kV Grid

Client: Confidential Utility Company (Southwest, USA)
Scope: 200 MW solar PV plant interconnection to a low-SCR 115 kV network.
Challenge: Identify sub-synchronous oscillations and high-frequency instabilities that RMS tools couldn’t capture.

Keentel Solution

  • Built a full EMT PSCAD model of PV inverters, plant controller, and grid-tie transformer.
  • Conducted VSC interaction and high-frequency stability analyses.
  • Developed mitigation strategies: PLL tuning and passive damping filters.

Results

  • Detected and neutralized damaging resonances early.
  • Kept the project on schedule without costly reactive power over-design.

Case Study 3
PSCAD Lightning Surge Study for a 500 kV Transmission Line

Client: Confidential Transmission Owner (Southeast, USA)
Scope: Validate insulation coordination for new 500 kV line and associated substations under direct lightning and back-flashover.
Challenge: Ultra-high voltage levels required precise energy-absorption modeling beyond standard arrester sizing.

Keentel Solution

  • Created a PSCAD model including tower geometry, insulator strings, and ground wire.
  • Simulated lightning strikes and storm variations across different soil resistivities.
  • Optimized surge arrester ratings and insulation levels.

Results

  • Reduced equipment capital cost by 8% while improving surge protection margins.
  • Minimized outage risk from lightning events.

Case Study 4
Controlled-Switching & TRV Analysis for 345 kV Circuit Breakers

Client: Confidential IPP (Texas, USA)
Scope: Evaluate transformer inrush, transient recovery voltage (TRV), and restrike risk at a new 345 kV/138 kV switching station.
Challenge: Insurance underwriter required proof that controlled switching would mitigate high inrush currents and TRV stresses.

Keentel Solution

  • Modeled station transformers, reactors, and breakers in PSCAD.
  • Ran point-on-wave switching simulations per IEEE C37.011 and IEC 62271-100.
  • Tuned controlled-switching device parameters and specified mitigation hardware.

Results

  • Achieved a 40% reduction in inrush current and guaranteed TRV compliance.
  • Secured favorable insurance terms and avoided costly breaker upgrades.

Our Service

Learn more about our full PSCAD Modeling Services and how we can tailor dynamic, EMT, and transient analyses to your project’s needs.


Next Steps

Ready to leverage PSCAD for your next interconnection or protection study?



A smiling man with glasses and a beard wearing a blue blazer stands in front of server racks in a data center.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.

Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads 51 engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering

Four workers in safety vests and helmets stand with arms crossed near wind turbines.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads 51 engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering

Leave a Comment

Related Posts

12.47 kV pole-mounted distribution transformer assembly designed for U.S. IEEE and NESC utility stan
By SANDIP R PATEL August 20, 2026
Learn U.S. pole-mounted transformer design requirements, including IEEE, ANSI, and NESC standards, voltage classes, grounding, protection, and DER considerations.
Neutral grounding resistor sizing guide for HRG and LRG power system grounding applications
By SANDIP R PATEL August 20, 2026
Learn how to size neutral grounding resistors using IEEE and NEC practices, including HRG/LRG selection, fault current calculations, duty ratings, and examples.
PRC-023-6 BESS relay loadability compliance guide
By SANDIP R PATEL August 19, 2026
Understand PRC-023-6 for utility-scale BESS: applicability, the 39-month rule, relay loadability, setting criteria, Category 2 IBRs, and audit evidence.
PRC-029-1 voltage ride-through envelope for inverter-based resources.
By SANDIP R PATEL August 18, 2026
Learn PRC-029-1 compliance requirements for inverter-based resources, including voltage and frequency ride-through, EMT studies, protection settings, and testing.
Solar plant electrical testing and commissioning for utility-scale PV systems
By SANDIP R PATEL August 17, 2026
A technical guide to solar plant electrical testing, commissioning, I-V curves, thermography, insulation testing, cable tests and performance acceptance.
Alt Text: Gas-insulated substation engineering guide covering GIS safety, reliability, VFTO, partial
By SANDIP R PATEL August 16, 2026
Explore GIS substation engineering, including design, SF6 safety, VFTO, grounding, commissioning, testing, GIS vs AIS, and IEEE/IEC standards.
Cable testing before energization engineering guide
By SANDIP R PATEL August 16, 2026
Learn the correct cable testing sequence before energization, including VLF, AC/DC withstand, sheath testing, partial discharge, tan delta, and standards.
substation drawing sets
By SANDIP R PATEL August 16, 2026
Explore how substation drawing sets are developed, reviewed and controlled through engineering studies, design milestones, QA/QC and final construction release.
Grid-forming vs grid-following BESS inverters
By SANDIP R PATEL August 15, 2026
Compare grid-forming vs grid-following BESS inverters, control loops, weak-grid stability, protection, compliance, and interconnection study impacts.