A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.

PSCAD Power System Studies: Four Real-World Case Studies

Calendar icon. D

May 5, 2025 | Blog

Person looking at two computer monitors displaying technical diagrams and graphs.

PSCAD (Power Systems Computer Aided Design) is the industry standard for high-fidelity electromagnetic transient (EMT) and dynamic studies. At Keentel Engineering, our PSCAD modeling services help utilities, renewable developers, and independent power producers validate grid interconnection performance, ensure ride-through compliance, and optimize protection schemes. Below are four detailed case studies showcasing how our PSCAD-driven power system studies delivered actionable insights and millions in cost savings.


Case Study 1
Transient Stability Analysis for a 345 kV Renewable Interconnection

Client: Confidential Renewable Energy Developer (Midwest, USA)
Scope: 600 MW combined wind + BESS interconnection at a 345 kV POI adjacent to a weak grid.
Challenge: Verify ride-through capability, critical clearing times, and voltage recovery under fault conditions per NERC PRC-024-2.

Keentel Solution

  • Developed detailed PSCAD models for wind turbines, BESS converters, collector system, and substation.
  • Simulated three-phase, single-line-to-ground, and double-line-to-ground faults.
  • Determined breaker critical clearing times and evaluated dynamic reactive support needs.

Results

  • Demonstrated full compliance without adding reactive support equipment.
  • Saved the client $2 million in avoided hardware upgrades.

Case Study 2
EMT Simulation of Inverter-Based Resources in a Weak 115 kV Grid

Client: Confidential Utility Company (Southwest, USA)
Scope: 200 MW solar PV plant interconnection to a low-SCR 115 kV network.
Challenge: Identify sub-synchronous oscillations and high-frequency instabilities that RMS tools couldn’t capture.

Keentel Solution

  • Built a full EMT PSCAD model of PV inverters, plant controller, and grid-tie transformer.
  • Conducted VSC interaction and high-frequency stability analyses.
  • Developed mitigation strategies: PLL tuning and passive damping filters.

Results

  • Detected and neutralized damaging resonances early.
  • Kept the project on schedule without costly reactive power over-design.

Case Study 3
PSCAD Lightning Surge Study for a 500 kV Transmission Line

Client: Confidential Transmission Owner (Southeast, USA)
Scope: Validate insulation coordination for new 500 kV line and associated substations under direct lightning and back-flashover.
Challenge: Ultra-high voltage levels required precise energy-absorption modeling beyond standard arrester sizing.

Keentel Solution

  • Created a PSCAD model including tower geometry, insulator strings, and ground wire.
  • Simulated lightning strikes and storm variations across different soil resistivities.
  • Optimized surge arrester ratings and insulation levels.

Results

  • Reduced equipment capital cost by 8% while improving surge protection margins.
  • Minimized outage risk from lightning events.

Case Study 4
Controlled-Switching & TRV Analysis for 345 kV Circuit Breakers

Client: Confidential IPP (Texas, USA)
Scope: Evaluate transformer inrush, transient recovery voltage (TRV), and restrike risk at a new 345 kV/138 kV switching station.
Challenge: Insurance underwriter required proof that controlled switching would mitigate high inrush currents and TRV stresses.

Keentel Solution

  • Modeled station transformers, reactors, and breakers in PSCAD.
  • Ran point-on-wave switching simulations per IEEE C37.011 and IEC 62271-100.
  • Tuned controlled-switching device parameters and specified mitigation hardware.

Results

  • Achieved a 40% reduction in inrush current and guaranteed TRV compliance.
  • Secured favorable insurance terms and avoided costly breaker upgrades.

Our Service

Learn more about our full PSCAD Modeling Services and how we can tailor dynamic, EMT, and transient analyses to your project’s needs.


Next Steps

Ready to leverage PSCAD for your next interconnection or protection study?



A smiling man with glasses and a beard wearing a blue blazer stands in front of server racks in a data center.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.

His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.

Four workers in safety vests and helmets stand with arms crossed near wind turbines.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.

Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.

His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.

Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.

Leave a Comment

Related Posts

PRC-028 PRC-029 and PRC-030 NERC IBR compliance guide
By SANDIP R PATEL • October 3, 2026
Engineering guide to PRC-028 disturbance recording, PRC-029 ride-through and PRC-030 event detection for inverter-based resources.
Keentel Engineering graphic showing damped and undamped subsynchronous oscillations.
By SANDIP R PATEL • October 3, 2026
A practical guide to SSO classification, SSR, PEDI, Wind-SSCI, EMT analysis, mitigation and protection based on CIGRE TB 909.
PV String I-V Curve Testing for Solar Performance Loss
By SANDIP R PATEL • October 3, 2026
Learn how PV string I-V curve testing identifies hidden solar performance losses, including soiling, shading, mismatch, degradation, and wiring faults.
Active harmonic filter reducing VFD current harmonics and grid THDi.
By SANDIP R PATEL • October 3, 2026
Learn how active harmonic filters work, how to size AHF systems, reduce VFD harmonics, calculate losses, and meet IEEE 519 TDD limits at the PCC.
BESS grid stability with frequency response and POI interconnection.
By SANDIP R PATEL • October 3, 2026
Learn how BESS supports grid stability through fast frequency response, voltage support, oscillation damping, black start, grid-forming controls and EMT studies.
Motor Protection & Relay Coordination TCC Guide
By SANDIP R PATEL • October 3, 2026
Learn motor protection and relay coordination using TCC curves, IEEE standards, transformer damage limits, CTI settings and a 138/13.8 kV example.
NERC and ERCOT compliance guide for natural gas power plants showing power system diagram and grid c
By SANDIP R PATEL • September 30, 2026
Learn NERC and ERCOT compliance requirements for natural gas power plants, including GO/GOP obligations, O&P standards, GADS reporting, and audits.
Data center and high-voltage transmission grid illustrating a large-load interconnection application
By SANDIP R PATEL • September 26, 2026
Learn how to prepare a MISO large-load interconnection package, including PSS®E models, BESS smoothing, harmonic data and transmission-owner requirements.
800 VDC AI data center storage architecture with battery systems, DC power distribution, and electri
By SANDIP R PATEL • September 26, 2026
Learn where storage belongs in an 800 VDC AI data center, including capacitors, flywheels, BESS, fault current, protection, grounding, and EMT design.