A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.

Challenge: Frequent false tripping using conventional electromechanical relays
Solution: SEL-487E integration with multi-terminal differential protection and dynamic inrush restraint
Result: 90% reduction in false trips, saving over $250,000 in downtime

Navigating PRC-029-1 and NOGRR245: A Guide to Inverter-Based Resource Compliance

Calendar icon. D

July 31, 2025 | Blog

Power grid illustration: solar panel, wind turbines, power lines, and batteries connected by a blue energy flow.

Introduction

In the evolving world of inverter-based resources (IBRs), staying compliant with NERC and ERCOT requirements is no longer just about following the standards—it’s about understanding how these standards are converging. The PRC-029-1 & NOGRR245 Comparison and Category 2 Registration Practice blog offers a deep dive into this convergence, helping Generator Owners, Operators, and planners understand and act on the latest regulatory expectations.


Overview: Aligning PRC-029-1 with IEEE 2800 and NOGRR245

Both PRC-029-1, a NERC standard, and ERCOT’s NOGRR245 have undergone recent revisions to align with IEEE Std 2800-2022. While their scopes differ—PRC-029-1 applies broadly to the Bulk Electric System (BES), and NOGRR245 governs ERCOT's grid—the technical requirements are beginning to mirror each other in significant ways, particularly in voltage and frequency ride-through (VRT/FRT) capabilities.


Voltage Ride-Through (VRT) Requirements: What Changed?

PRC-029-1 R1–R2:

  • Mandates that Generator Owners ensure their IBRs can ride through voltage excursions within defined limits.
  • Provides detailed operational zones—continuous, mandatory, and permissive—and corresponding behavior expectations.
  • Real and reactive power priorities are defined based on voltage thresholds and operational limitations.

NOGRR245 Section 2.9.1:

  • Applies to IBRs with SGIAs after August 1, 2024.
  • Requires adherence to IEEE 2800 Sections 5 (voltage control), 7 (response to system abnormalities), and 9 (protection).
  • Clearly differentiates between WGRs (Wind Generation Resources) and PVGRs (Photovoltaic Generation Resources), establishing tailored ride-through curves.
  • ERCOT preserves portions of the legacy ride-through curve while integrating IEEE 2800 standards.

Frequency Ride-Through (FRT): Reinforcing Grid Stability

PRC-029-1 R3:

  • Enforces mandatory frequency ride-through in the “must ride-through zone” if RoCoF is ≤5 Hz/s.
  • Defines a symmetrical treatment for low- and high-frequency events using a 299-second threshold (e.g., between 61.2 and 58.8 Hz).

NOGRR245 Sections 2.6.2.1 & 2.6.2.2:

  • Introduces longer ride-through durations (up to 540 seconds) for frequency events.
  • Adds stepped timing and applies different expectations for transmission-connected versus distribution-connected DERs and BESS.
  • ERCOT’s extended steps, offering more flexibility and granularity compared to NERC's flat 299s rule.

Hardware Limitations and Exemptions: A Stricter Path

PRC-029-1 R4:

Outlines exemption processes for in-service IBRs unable to meet the new ride-through criteria due to hardware limitations:

  • Requires full documentation within 12 months of effective date.
  • Allows only hardware-based exemptions (not software/setting-based).
  • Involves Compliance Enforcement Authority (CEA) approval.

In contrast, NOGRR245 includes:

  • Additional procedural steps under Sections 2.11 and 2.12.
  • Flexibility for extensions in some cases.
  • Application of SGIA date cutoffs (e.g., August 1, 2024).

Category 2 IBR Registration: New Requirements for Non-BES Units

A significant part of the blog also focuses on the Category 2 IBR Registration initiative. The ERO Enterprise webinar (scheduled for March 3, 2025) aims to educate stakeholders on registration criteria targeting previously unregistered non-BES IBRs with:

  • Aggregate capacity ≥20 MVA,
  • Connected at voltage ≥60 kV.

This moveaddresses reliability risks posed by “invisible” IBRs and represents a proactive registration approach to ensure they comply with relevant Reliability Standards.


Key Takeaways for Developers, Owners, and Operators

  1. Align Early with IEEE 2800-2022: Both PRC-029-1 and NOGRR245 directly reference IEEE 2800, making it essential to design new projects with its requirements embedded.

  2. Don’t Ignore Non-BES IBRs: With NERC seeking to register Category 2 IBRs, even resources historically outside its purview will come under scrutiny.

  3. Document and Report Hardware Limits Promptly: For legacy IBRs, ensure exemption requests are supported with detailed, verifiable evidence and shared with the required authorities.

  4. Evaluate Controller Settings: Real/reactive power priorities and restart logic (e.g., 5-cycle recovery post-blocking mode) must match grid expectations.

  5. Register for the Webinar: The future ERO  sessions will clarify many gray areas around registration criteria and practical compliance pathways.

Conclusion

The harmonization of PRC-029-1 with ERCOT’s NOGRR245 reflects a larger industry trend: bringing all inverter-based generation—whether bulk or distribution-connected—under a common reliability framework. The dual emphasis on voltage and frequency ride-through, backed by IEEE 2800, underscores the importance of resilient and predictable IBR behavior under grid disturbances.

For owners, operators, and engineers, now is the time to review project designs, audit legacy assets, and prepare for upcoming compliance expectations


Related Blogs



A smiling man with glasses and a beard wearing a blue blazer stands in front of server racks in a data center.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.

Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads 51 engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering

Four workers in safety vests and helmets stand with arms crossed near wind turbines.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads 51 engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering

Leave a Comment

Related Posts

Structure height and voltage in transmission line design guide by Keentel Engineering with power tow
By SANDIP R PATEL August 22, 2026
Learn how transmission structure height is calculated using NESC clearance rules, sag-tension analysis, voltage classes, terrain, span length, and IEEE standards.
Gas-insulated substation design and engineering diagram.
By SANDIP R PATEL August 22, 2026
Explore gas-insulated substations (GIS), including design, GIS vs AIS, SF₆ alternatives, grounding, VFTO, safety, and key IEEE and IEC standards.
Sizing AC cables in a utility-scale solar PV plant technical guide by Keentel Engineering, showing N
By SANDIP R PATEL August 22, 2026
Learn NEC-based AC cable sizing for utility-scale solar PV plants, including ampacity, voltage drop, derating factors, short-circuit checks, and inverter examples.
By SANDIP R PATEL August 22, 2026
Learn how NERC's new data center rules affect registration, modeling, protection, compliance, and what computational load operators should do now.
POI interconnection engineering for large loads and data centers.
By SANDIP R PATEL August 20, 2026
2026 guide to POI interconnection for data centers and large loads. Explore ISO/RTO requirements, grid studies, PSCAD modeling, costs, timelines and NERC rules.
Solar and battery storage shared bus resonance diagram
By SANDIP R PATEL August 20, 2026
Learn how shared 480 V solar and BESS buses create resonance, harmonic, grounding, and transformer issues—and how proper engineering prevents failures.
12.47 kV pole-mounted distribution transformer assembly designed for U.S. IEEE and NESC utility stan
By SANDIP R PATEL August 20, 2026
Learn U.S. pole-mounted transformer design requirements, including IEEE, ANSI, and NESC standards, voltage classes, grounding, protection, and DER considerations.
Neutral grounding resistor sizing guide for HRG and LRG power system grounding applications
By SANDIP R PATEL August 20, 2026
Learn how to size neutral grounding resistors using IEEE and NEC practices, including HRG/LRG selection, fault current calculations, duty ratings, and examples.
PRC-023-6 BESS relay loadability compliance guide
By SANDIP R PATEL August 19, 2026
Understand PRC-023-6 for utility-scale BESS: applicability, the 39-month rule, relay loadability, setting criteria, Category 2 IBRs, and audit evidence.