A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.

Challenge: Frequent false tripping using conventional electromechanical relays
Solution: SEL-487E integration with multi-terminal differential protection and dynamic inrush restraint
Result: 90% reduction in false trips, saving over $250,000 in downtime

FERC Order 2023 Explained: Transforming Generator Interconnection for the Future Grid A Technical Deep Dive by Keentel Engineering

FERC Order 2023 interconnection process diagram showing power generation
Calendar icon. D

May 1, 2026 | Blog

Introduction

The U.S. electric grid is undergoing one of the most significant transformations in its history. The rapid integration of renewable energy, battery storage, and inverter-based resources (IBRs) has exposed fundamental limitations in legacy generator interconnection processes.


To address these challenges, the Federal Energy Regulatory Commission (FERC) issued Order No. 2023, a landmark reform aimed at improving generator interconnection procedures, reducing queue backlogs, and enabling faster deployment of new generation resources. 


At Keentel Engineering, we specialize in helping developers, utilities, and asset owners navigate these evolving regulatory frameworks through advanced engineering design, interconnection studies, and compliance services.


1. Why FERC Order 2023 Was Necessary

1.1 Interconnection Queue Crisis


  • Over 10,000 active projects (~2000 GW) in queues nationwide 
  • Only ~25% of projects reach commercial operation 
  • Study delays exceeding 3–5 years 


This backlog has led to:


  • Increased project uncertainty 
  • Escalating interconnection costs 
  • Delayed renewable deployment 
  • Reliability risks 


FERC concluded that existing procedures are:


“insufficient to ensure reliable, efficient, transparent, and timely interconnection” 


2. Core Reforms Introduced by FERC Order 2023

2.1 Shift to “First-Ready, First-Served”


Old Model: First-Come, First-Served
New Model: First-Ready, First-Served (Cluster-Based)


Key Features:


  • Projects grouped into clusters 
  • Equal priority within clusters 
  • Progress based on project readiness 


Result:


  • Eliminates speculative queue clogging 
  • Prioritizes viable projects 


2.2 Cluster Study Process


Replaces serial studies with:


  • Cluster Feasibility 
  • Cluster System Impact 
  • Cluster Facilities Study 


Benefits:


  • Reduced redundant studies 
  • Better system-wide optimization 
  • Lower cumulative study cost 


2.3 Increased Financial Commitments


Developers must now provide:


  • Study deposits 
  • Commercial readiness deposits 
  • Site control evidence 


Impact:


  • Filters speculative projects early 
  • Improves queue quality 


2.4 Cost Allocation Reform


  • Cluster study costs: Shared (pro-rata + per capita) 
  • Network upgrade costs: Based on proportional impact 


Major Shift:


Moves away from “first mover pays everything”


2.5 Penalties and Accountability


  • Transmission providers penalized for missed deadlines 
  • Removal of “reasonable efforts” standard 
  • Withdrawal penalties for developers 


Outcome:


  • Stronger accountability on both sides 

3. Technology Integration Reforms

3.1 Co-Located and Hybrid Resources


  • Multiple generators can share one POI 
  • Supports solar + storage hybrid systems 


3.2 Energy Storage Modeling


  • New rules allow realistic operating assumptions 
  • Prevents overestimation of network upgrades 


3.3 Alternative Transmission Technologies (ATTs)


Examples:


  • Dynamic line ratings 
  • Advanced power flow controllers 
  • Topology optimization

 

These reduce:


  • Upgrade costs 
  • Construction timelines 


3.4 Ride-Through and Modeling Requirements


For inverter-based resources:


  • Mandatory dynamic models 
  • Voltage ride-through capability 
  • Reactive power support 


Critical for grid stability


4. Engineering Challenges Created by Order 2023

4.1 Increased Study Complexity


  • Larger datasets 
  • Multi-project interactions 
  • EMT + RMS modeling requirements 


4.2 Data Transparency Requirements


  • Public posting of interconnection data 
  • Greater need for data analytics 


4.3 Affected System Coordination


  • Multi-ISO and utility coordination required 
  • Often major source of delays 

5. How Keentel Engineering Supports Clients

Keentel Engineering provides end-to-end interconnection and compliance services aligned with FERC Order 2023.


5.1 Interconnection Studies


  • PSSE, PSCAD, TSAT modeling 
  • Cluster study participation support 
  • EMT + RMS validation 


5.2 Grid Code Compliance



5.3 Cost Optimization


  • Network upgrade mitigation strategies 
  • Alternative transmission technology analysis 


5.4 Project Development Advisory


  • Site selection using grid analytics 
  • Queue strategy optimization 
  • Risk assessment 

6. Strategic Implications for Developers

Developers must:


  • Enter queues only when “ready” 
  • Invest more upfront capital 
  • Use advanced modeling early 


Utilities must:


  • Improve study timelines 
  • Enhance transparency 
  • Adopt modern technologies 

7. Future Outlook

FERC Order 2023 is just the beginning.


Expected next steps:




Conclusion

FERC Order 2023 represents a paradigm shift in generator interconnection:


  • From reactive → proactive 
  • From speculative → committed 
  • From slow → structured 


At Keentel Engineering we help clients not just comply but gain a competitive advantage in this new regulatory environment.


25 Technical FAQs (Detailed)

  • 1. What is the biggest change in FERC Order 2023?

    The transition from first-come-first-served to first-ready-first-served cluster study process, prioritizing project maturity over queue position.


  • 2. Why were cluster studies introduced?

    To eliminate repetitive restudies and handle multiple projects simultaneously, improving efficiency and reducing delays.


  • 3. How are network upgrade costs allocated now?

    Using a proportional impact methodology, rather than assigning full cost to early entrants.


  • 4. What is “site control” requirement?

    Developers must prove ownership/lease rights before entering the queue, reducing speculative entries.


  • 5. What replaces the “reasonable efforts” standard?

    Strict deadlines with financial penalties for transmission providers.


  • 6. What are affected system studies?

    Studies assessing impact on neighboring systems outside the host utility.


  • 7. Why are affected systems a bottleneck?

    Lack of standardized procedures causes delays and coordination issues.


  • 8. What modeling is required for inverter-based resources?

    • RMS dynamic models 
    • EMT models (if applicable) 
    • Validated parameters 

  • 9. What is ride-through capability?

    Ability of generators to stay connected during faults and support grid stability.


  • 10. How does Order 2023 affect battery storage?

    Allows realistic charging/discharging assumptions, reducing unnecessary upgrades.


  • 11. What are Alternative Transmission Technologies?

    Technologies that improve grid capacity without building new lines.


  • 12. Why are ATTs important?

    They reduce cost, environmental impact, and deployment time.


  • 13. What is a cluster study deposit?

    A financial commitment required to participate in cluster studies.


  • 14. What happens if a developer withdraws?

    They may face withdrawal penalties depending on timing.


  • 15. What is surplus interconnection service?

    Allows new projects to use unused capacity of existing interconnections.


  • 16. What is co-location?

    Multiple generation resources sharing one interconnection point.


  • 17. How does Order 2023 impact timelines?

    Aims to reduce timelines but requires better upfront preparation.


  • 18. Why are study delays so common?

    Complex modeling, coordination issues, and resource constraints.


  • 19. What role does data transparency play?

    Improves decision-making and reduces speculative entries.


  • 20. How does this affect renewable energy growth?

    Accelerates deployment by removing interconnection bottlenecks.


  • 21. What software tools are needed?

    • PSSE 
    • PSCAD 
    • TSAT 
    • PowerFactory 

  • 22. What is EMT modeling?

    High-fidelity simulation for inverter-based resource dynamics.


  • 23. How can developers reduce interconnection costs?

    • Optimal siting 
    • Using ATTs 
    • Early modeling studies 

  • 24. What risks do developers face under Order 2023?

    Higher upfront costs, stricter deadlines, and financial penalties.


  • 25. How can Keentel Engineering help?

    By providing:

    • Interconnection studies 
    • Compliance support 
    • Cost optimization 
    • Advanced modeling



A smiling man with glasses and a beard wearing a blue blazer stands in front of server racks in a data center.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.

His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.

Four workers in safety vests and helmets stand with arms crossed near wind turbines.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.

Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.

His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.

Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.

Leave a Comment

Related Posts

Cyber-physical resilience model showing DER attack detection and grid load recovery
By SANDIP R PATEL • October 26, 2026
Explore cyber-physical resilience for the Energy Internet, including DER attacks, false data injection, BESS readiness, AI detection, and NERC CIP compliance.
Buchholz and sudden pressure relay transformer protection comparison
By SANDIP R PATEL • October 24, 2026
Learn how Buchholz and sudden pressure relays protect transformers, detect internal faults, and meet NERC PRC-005-6 maintenance requirements.
Digital twin pump failure simulation showing GPU temperature response after a secondary cooling pump
By SANDIP R PATEL • October 24, 2026
Explore digital twin pump failure simulation for liquid-cooled AI data centers, including GPU temperatures, standby pump failover, UPS and workload recovery.
PSCAD custom component parameters showing plant controller voltage response
By SANDIP R PATEL • October 24, 2026
Learn PSCAD custom component parameters, field types, Literal, Constant and Variable settings, Fortran coding, and EMT model validation for grid studies.
800 VDC rack fault protection showing DC bus voltage response to circuit breakers and fuses
By Team 2 Dexora • October 24, 2026
Explore 800 VDC rack fault protection for AI data centers, including solid-state breakers, DC short circuits, selectivity, arc flash, and NEC/UL standards.
VSC-HVDC outer-loop control showing DC voltage response during an AC fault
October 24, 2026
Explore VSC-HVDC outer-loop control for P, Q, DC voltage, weak-grid stability, fault ride-through and power oscillation damping with engineering models.
Grid-forming BESS transitions showing 13.8 kV microgrid islanding, GFL to GFM control transfer, and
By SANDIP R PATEL • October 23, 2026
Explore grid-forming BESS initialization, GFL-to-GFM transitions, seamless islanding, EMT simulations, current limiting and microgrid protection.
Ferranti effect in a 345 kV transmission line showing receiving-end voltage rise, shunt reactor comp
By SANDIP R PATEL • October 23, 2026
Explore the Ferranti effect in EHV transmission lines: voltage rise, 345 kV examples, switching overvoltages, shunt reactor sizing and mitigation.
Cluster interconnection studies under FERC Order 2023 showing Keentel Engineering's analysis of 23 p
By SANDIP R PATEL • October 23, 2026
Explore cluster interconnection studies under FERC Order 2023, including network upgrades, cost allocation, withdrawal penalties and developer strategy.