A Coordinated Electric System Interconnection Review—the utility’s deep-dive on technical and cost impacts of your project.

Challenge: Frequent false tripping using conventional electromechanical relays
Solution: SEL-487E integration with multi-terminal differential protection and dynamic inrush restraint
Result: 90% reduction in false trips, saving over $250,000 in downtime

The three operating regions you have to design to

Device Output vs voltage Response Best suited to Main limitations
Mechanically switched capacitor or reactor Proportional to voltage squared Seconds; discrete steps; limited switching operations per day Steady-state reactive supply, voltage profile, loss reduction No dynamic capability; step voltage change on switching; capability collapses when most needed
Static var compensator Capacitive branches proportional to voltage squared A few cycles; continuously controllable Continuous control where cost matters and deep voltage support is not the driver Square-law capability loss; harmonic filters are part of the plant and interact with the network
STATCOM Approximately proportional to voltage — constant current capability One to two cycles closed loop; converter response faster still Voltage stability margin, weak interconnections, fast disturbance recovery, flicker and unbalance compensation Higher capital cost; converter losses; adds a converter and its control dynamics to the network
Synchronous condenser Governed by machine capability and excitation Excitation response in the hundreds of milliseconds; inherent inertial response instantaneous System strength and inertia, short-circuit contribution, black start support Rotating plant with maintenance and losses; slower controlled response than a converter
STATCOM with energy storage Reactive as a STATCOM, plus real power within the storage rating As STATCOM for reactive; real power limited by storage Where a real power deficiency is part of the problem Cost and complexity of the storage; different failure and maintenance profile
Stage Keentel scope Outcome
Screening Series-compensation proximity, radial contingency review, UIF and short-circuit ratio screening, frequency scans Early identification of which SSO types apply
Detailed studies PSCAD/EMTDC EMT studies with vendor real-code models, impedance-based and frequency-scan analysis Clear evidence of stability margins or risk
Model quality EMT model review, benchmarking against positive-sequence models, model acceptance support Models that system operators accept
Mitigation Control retuning recommendations with vendors, SSDC and bypass logic requirements, protection and monitoring specifications Practical, coordinated solutions
Interconnection support SSR and SSO study reports for ISO and utility requirements, response to reviewer comments Fewer delays in the interconnection process

Resilience: designing CDUs to the facility Tier objective


Liquid cooling makes heat removal more critical, not less. Cold plates hold only seconds of thermal buffer. If TCS flow stops, processors throttle or shut down very quickly. Resilience design must therefore cover:


  • Pump redundancy: N+1 pumps at minimum, with automatic changeover.
  • CDU redundancy: N+1 CDUs on a common TCS header, or 2N CDUs serving A and B manifolds for fault-tolerant designs.
  • Power to CDUs: dual-corded CDUs fed from A and B sources, with pumps and controls on UPS power so coolant keeps flowing through a utility failure and generator start. This is the liquid-cooling equivalent of continuous cooling.
  • Facility water continuity: chilled water or condenser water must also continue, through thermal storage, UPS-backed pumps or a high enough FWS temperature that the TCS can coast on stored thermal mass for the transfer period.
  • Concurrent maintainability: isolation valves so any CDU, pump, filter or manifold section can be serviced without stopping the others.
  • Leak management: leak detection, drip trays, automatic isolation valves and procedures for fluid spills.


Electrical engineering considerations


CDUs and liquid-cooling plants are electrical loads with their own design requirements:


  • Pump motors and VFDs. Large CDUs use variable-frequency drives on their pump motors. These introduce harmonic current that must be included in the facility's harmonic study and IEEE 519 evaluation.
  • Critical mechanical load on UPS. Putting CDU pumps on UPS increases UPS and battery sizing. The mechanical UPS load must be included in redundancy and ride-through calculations.
  • Feeder and protection design. Dual feeds, automatic transfer, selective coordination and arc-flash labelling apply to CDU power distribution just as they do to IT power.
  • Generator transient response. CDU pumps restarting together after a transfer create motor inrush on the generators. Staged restarts and soft acceleration reduce the step load.
  • Load dynamics. AI training loads can swing rapidly between high and low power. Cooling controls must track those swings without temperature overshoot, and electrical systems must handle both the IT and the cooling load changes.


Commissioning a liquid-cooled data hall


  1. Flush and clean the TCS piping and manifolds to the specified cleanliness, using high-purity flush water.
  2. Fill and vent with the specified coolant, verifying glycol concentration and chemistry.
  3. Pressure test for leaks at design and test pressures, including quick-disconnect fittings.
  4. Verify sensors and controls: flow meters, temperature sensors, pressure transmitters, leak detection and BMS points.
  5. Load test with heat load banks connected through the cold-plate interfaces or rack manifolds, across the operating range.
  6. Prove the heat balance on both loops at several load steps, and the approach temperature against the design.
  7. Test failure scenarios: pump failure, CDU failure, power transfer to generator, valve failure and loss of facility water, confirming temperatures stay within the IT vendor's limits.


How Keentel Engineering helps


Keentel Engineering supports data center owners, developers and EPCs with the electrical engineering that liquid-cooled facilities depend on, and coordinates with the mechanical engineer of record and cooling vendors on the integrated design.


AI Data Center Cooling Plants: Evaporative vs Hybrid vs Dry Cooling, Energy Efficiency and Grid Impact

Data Center Cooling Plants: Evaporative vs Hybrid vs Dry
Calendar icon. D

November 26, 2026 | Blog

Part A — AI Data Center Heat Rejection at a Glance

Every watt that enters an AI data center leaves it as heat. A 100 MW campus running current-generation GPU racks has to move roughly 100 MW of heat out of the building, through a water loop, and into the outdoor air, every hour of the year, including the hottest afternoon of the hottest summer on record. The equipment that does the last step — cooling towers, hybrid coolers or dry coolers, with their pumps, fans and sometimes trim chillers — is called the heat-rejection plant.

For most of the history of enterprise data centers, the heat-rejection plant was a mechanical engineering choice made late in design. For AI campuses at 100 MW and beyond, it has become one of the first decisions that shapes the whole project. It sets how much water the site must secure and discharge, how much land the yard occupies, how loud the property line will be, how much electricity the plant draws on a 105 °F afternoon, and therefore how many megawatts the utility must deliver, how many generators the site must install, and how the facility behaves on the grid.

This guide is Keentel Engineering's in-depth comparison of the three architectures now used for liquid-cooled AI facilities: evaporative cooling towers, hybrid dry coolers with adiabatic or evaporative assist, and closed-loop dry coolers. It covers the thermodynamics, the water balance, the energy balance, and, in more depth than most comparisons, the electrical and grid consequences of each choice. Every major point is backed by a worked example calculated on one reference facility, using US units (°F, gpm, tons, feet and acres) with SI values in parentheses where they help.

Keentel's position. Keentel Engineering is an independent electrical, power systems and MEP engineering firm. We do not sell cooling equipment. We design the electrical systems that feed heat-rejection plants, size utility services and on-site generation for them, study their effect on the grid, and act as owner's engineer on data center projects from 4 kV to 765 kV. That is why this guide treats cooling-plant selection as an electrical, water and permitting decision as much as a mechanical one.

Who this guide is for

Data center developers and owners choosing a site and a cooling strategy before land, water and power are committed.

MEP design teams and owner's engineers who must coordinate mechanical selections with electrical capacity, generator sizing and utility service.

Utilities and transmission planners studying large-load requests whose summer peak depends on the cooling plant.

Municipal water and permitting staff evaluating water supply, discharge and noise for new campuses.

Lenders and investors who need to understand how water, energy and grid risk differ across cooling options.

Operations teams taking over a plant that must stay concurrently maintainable and fault tolerant.

The reference facility used in this guide

All worked examples use one illustrative US campus. The numbers are Keentel's modeling assumptions, not data from any specific site.

Item Value (illustrative)
IT load 100 MW, predominantly direct-to-chip liquid cooling through CDUs
Heat rejected by the facility water plant 103 MW (IT plus pump, CDU and residual air-side heat)
Facility water temperatures 86 °F (30 °C) supply, 104 °F (40 °C) return, an 18 °F (10 K) range — ASHRAE class W32
Average load factor 85% of design IT load over the year
Climates studied Three synthetic hourly climates: hot-humid ("Dallas-like"), hot-dry ("Phoenix-like") and mild-humid ("Ashburn-like")
Utility service 230 kV transmission service, 34.5 kV and 13.8 kV medium-voltage distribution, 480 V mechanical switchboards, 60 Hz
Electricity price $70/MWh (illustrative)

The synthetic climates are smooth models built for comparison; they are not ASHRAE design data. Any real project must use ASHRAE climatic design conditions and multi-year hourly weather files for the actual site.

Key facts at a glance

Item Value or practice Basis
US data center electricity use About 4.4% of US electricity in 2023, rising to an estimated 6.7–12% by 2028 LBNL, 2024 United States Data Center Energy Usage Report (December 2024)
US data center direct water use On the order of 17 billion gallons in 2023, with substantial growth projected (confirm current figures against the report) LBNL 2024 report and coverage of it
Water metric Water usage effectiveness (WUE) = annual site water use (liters) ÷ IT energy (kWh) The Green Grid; ISO/IEC 30134-9:2022
Energy metric Power usage effectiveness (PUE) = total facility energy ÷ IT energy The Green Grid; ISO/IEC 30134-2
Liquid-cooling water classes W17, W27, W32, W40, W45 and W+ (maximum facility water supply temperature in °C) ASHRAE TC 9.9, Thermal Guidelines for Data Processing Environments, 5th edition
Energy standard for data centers ASHRAE Standard 90.4-2022, including a mechanical load component (MLC) compliance path ASHRAE
Legionella risk management ASHRAE Standard 188 (water management programs for building water systems, including cooling towers) ASHRAE
Cooling tower thermal testing CTI ATC-105 (open towers) and ATC-105S (closed-circuit coolers); CTI STD-201 thermal certification Cooling Technology Institute
Cooling tower water-efficiency guidance Raise cycles of concentration, meter makeup and blowdown, control conductivity EPA WaterSense at Work §6.3; DOE FEMP Best Management Practice #10
Typical evaporation in a cooling tower About 1% of circulating flow for each 10 °F of range EPA WaterSense; industry rule of thumb
Grid behavior of large loads NERC has published an incident review of a large voltage-sensitive load loss and guidance on large-load integration NERC (2025)

The core ideas in one table

Idea What it means for an AI campus
Heat leaves either as evaporated water or as warmed air Towers reject most heat as latent heat (water vapor); dry coolers reject it as sensible heat (warmer air). Hybrids switch between the two.
Wet-bulb sets the tower's limit; dry-bulb sets the dry cooler's On a 105 °F dry afternoon the wet-bulb may be 75 °F. A tower can still deliver cool water; a dry cooler cannot get below the air temperature.
Water and energy trade against each other Each gallon not evaporated must be paid for with more fan energy, more coil area, warmer water, or chiller energy.
The facility water temperature is the master variable Moving from W32 (86 °F supply) to W40 (104 °F) can eliminate most trim-chiller hours in many US climates.
The worst hour sizes the electrical system Utility service, transformers and generators must carry the cooling plant on the design-day peak, which is exactly when dry plants work hardest.
Consumption is not withdrawal Evaporated water leaves the watershed; blowdown returns to the sewer. Permits and public debate care about both.
Liquid cooling makes the loop critical Direct-to-chip racks overheat in seconds without flow, so pumps, controls and parts of the plant need uninterruptible power and redundancy.
No architecture is best everywhere Climate, water availability, discharge rules, noise limits, grid capacity and tariffs decide the right answer for each site.

Fact check: what common comparisons get right and what they leave out

Comparisons of evaporative, hybrid and closed-loop plants circulate widely, often as a three-row table with site areas in hectares and temperatures in Celsius. The broad conclusions are sound. Several points need correction or expansion for US engineering practice.

Common statement Keentel's engineering check
"Evaporative plants have high efficiency." True for heat-rejection energy: fans run less and water can be colder because towers follow wet-bulb. But towers need larger condenser-water pumps (open-loop static lift) and the water itself carries an energy and cost footprint upstream. "Efficient" should be stated as kW per ton of heat rejected and gallons per MWh, side by side.
"Dry coolers use near-zero water." Near-zero routine evaporative water, yes. But in hot climates a dry plant designed for W32 water needs trim chillers on many hours, and those chillers' electricity has its own water footprint at the power plant. The water saving is real on site; the system-wide picture depends on the grid mix.
"Hybrid uses water only during high ambient." Correct in principle, but the switch-over point is a design choice, not a constant. A hybrid designed for warmer facility water uses far less water than one held to W32. Hybrid pads and sprays also need water treatment and periodic flushing.
"Site area ~0.5–1.2 ha for 100 MW." These figures (about 1.2–3.0 acres) are plausible for the heat-rejection yard alone but exclude setbacks, noise barriers, water storage and treatment, electrical rooms, generator yards and maintenance access. Dry coolers usually need more coil face area than towers for the same heat, not less; compact dry layouts depend on stacking or V-bank designs and on warmer water.
"Warm water ~32–40 °C, cooled ~24–30 °C." Reasonable for many direct-to-chip designs, but these are application-dependent. ASHRAE W-classes and the IT vendor's coolant supply limits govern. A 6–10 K range is typical; a wider range reduces flow and pump energy.
"Plume: yes / limited / no." Plume is mostly a visual and icing issue, but it can matter for permitting near airports and roads. Towers can be specified with plume abatement.
Missing: Legionella Any wet system — towers and the wetted parts of hybrids — needs a water management program under ASHRAE Standard 188 and local health codes.
Missing: electrical and grid impact The cooling plant's summer peak demand differs by a factor of five or more between options. That changes utility service size, generator count and, at campus scale, the transmission study.
Missing: noise Dry coolers move far more air and carry many more fans. Property-line noise often limits dry and hybrid yards more than footprint does.

Eight findings for decision makers

1. The facility water temperature matters more than the brand of cooler. In Keentel's model, raising the supply from 86 °F (W32) to 104 °F (W40) cut a hybrid plant's design-day demand in the hot-humid climate from about 11.3 MW to 2.6 MW, because it eliminated the trim chillers.

2. Evaporative towers remain the lowest-energy option almost everywhere, at the cost of roughly 1.0–1.3 million gallons of makeup water per day for a 100 MW IT load at full output.

3. Hybrid plants recover 80–94% of the water a tower would use in the three climates we modeled, while keeping peak electrical demand close to a tower plant if they are designed for warm water.

4. Dry plants held to W32 water in hot climates are the worst case for the grid, with design-day cooling demand above 20 MW in our model, almost all of it trim chillers that run exactly when the utility's system peaks.

5. The electrical system must be sized for the worst hour, not the annual average. Annual PUE differences of a few hundredths can hide peak-demand differences of 20 MW.

6. Water is now a permitting and public-acceptance issue, with states and Congress examining data center water reporting. Site selection should treat water rights, discharge permits and drought plans as early as power.

7. Liquid cooling makes the cooling loop part of the critical power path. Pumps and controls need uninterruptible power and redundancy aligned with the facility's Tier objective.

8. The right answer is site-specific, and the comparison must be done in one consistent model that includes water, energy, peak demand, noise, footprint and lifecycle cost.

Key terms

Term Meaning
Heat-rejection plant Equipment that moves heat from the facility water loop to the outdoor air: towers, hybrid coolers, dry coolers, trim chillers, pumps and controls
Facility water system (FWS) The primary loop between the heat-rejection plant and the CDUs
Technology cooling system (TCS) The secondary loop between the CDUs and the IT equipment
CDU Coolant distribution unit, which transfers heat from the TCS to the FWS through a heat exchanger
Range Temperature drop of the water across the heat-rejection equipment (return minus supply)
Approach Leaving water temperature minus the ambient temperature the equipment works against (wet-bulb for towers, dry-bulb for dry coolers)
Wet-bulb temperature The lowest temperature air can reach by evaporating water into it; the limit for evaporative cooling
Cycles of concentration (COC) Ratio of dissolved solids in tower water to those in makeup water; higher cycles mean less blowdown
Blowdown Water deliberately drained from a tower to control dissolved solids
Makeup Water added to replace evaporation, blowdown and drift
Adiabatic precooling Wetting pads or spraying mist into the air entering a dry coil so it approaches the wet-bulb temperature
Trim chiller A mechanical chiller that cools the water the rest of the way when the dry or hybrid plant cannot reach the setpoint
WUE Water usage effectiveness: site water (L) ÷ IT energy (kWh)
PUE Power usage effectiveness: total facility energy ÷ IT energy
Design day The hot (and humid) condition used to size equipment, typically from ASHRAE 0.4% or more severe design data, or an owner-specified extreme

Part B — The Engineering Guide to Heat-Rejection Plant Selection

1. Why heat rejection is now an electrical, water and grid decision

An air-cooled enterprise data center of the 2010s typically ran at 5–10 kW per rack and used chilled water or direct-expansion units at 45–55 °F. The heat-rejection plant was a set of chillers with cooling towers or air-cooled condensers, chosen mainly on first cost and efficiency. Its electrical demand was a fixed slice of the facility load.

AI training and inference racks changed three things at once.

Density. Racks have moved from tens of kilowatts to well over 100 kW each, and roadmaps go higher. Air cannot carry that heat economically, so direct-to-chip liquid cooling has become the default for high-density AI halls. Keentel's companion guide on coolant distribution units explains the CDU and the two-loop arrangement in detail.

Temperature. Liquid cooling lets the facility water run much warmer than chilled water. Supply temperatures of 77–95 °F (25–35 °C), and in some designs above 104 °F (40 °C), are now common. Warm water can often be cooled by outdoor air alone, which opens the door to chiller-free plants.

Scale. A single campus can now ask a utility for hundreds of megawatts. At that scale the cooling plant's own demand — and how it varies with weather — is large enough to matter to transmission planning.

The result is that the heat-rejection plant now sets several of the project's hardest constraints:

Constraint How the cooling plant drives it
Water supply and discharge Towers need about 1 million gallons a day per 100 MW of IT at full output; dry plants need almost none
Utility service size Design-day cooling demand ranges from about 2–4 MW to more than 20 MW per 100 MW of IT across the options
Generator plant Every megawatt of cooling demand on the design day must also be carried by standby generation
Land and layout Yard area, spacing for air recirculation, noise setbacks and maintenance access
Permits and public acceptance Water rights, discharge permits, noise ordinances, plume and visual impact
Reliability For liquid-cooled racks, loss of flow becomes a thermal event in seconds
Operating cost Energy, water, sewer, chemicals and maintenance differ by millions of dollars a year

How Keentel Engineering helps here. Keentel starts every data center cooling engagement with a constraints map: available water and discharge capacity, utility service and interconnection timeline, generator strategy, noise and setback limits, and the owner's Tier and sustainability targets. The cooling architecture is then selected against those constraints rather than in isolation.

2. The heat-rejection chain, from chip to atmosphere

Heat in a liquid-cooled AI hall moves through five stages:

1. Chip to cold plate. Processors and accelerators conduct heat into cold plates.

2. Cold plate to TCS coolant. The technology cooling system coolant, often 25% propylene glycol or treated water, carries the heat to the CDU.

3. CDU heat exchanger. A plate heat exchanger transfers heat to the facility water system. Its approach (TCS supply minus FWS supply) is typically 4–9 °F (2–5 K).

4. Facility water to the plant. Pumps carry facility water to the heat-rejection yard.

5. Plant to atmosphere. Towers, hybrid coolers or dry coolers reject the heat. Trim chillers, where installed, close the gap on hot hours.

ASHRAE TC 9.9's thermal guidelines classify facility water by its maximum supply temperature.

ASHRAE class Maximum facility water supply Typical heat rejection in US climates
W17 63 °F (17 °C) Chillers, with economizers
W27 81 °F (27 °C) Chillers with economizers; cooling towers in dry climates
W32 90 °F (32 °C) Cooling towers; dry coolers in mild climates with trim
W40 104 °F (40 °C) Dry coolers or hybrids in most climates, chiller-free most hours
W45 113 °F (45 °C) Dry coolers almost everywhere; heat reuse becomes practical
W+ Above 113 °F Heat reuse, district heating

The class the facility can accept is set by the IT equipment: the coolant temperature the server maker allows at the cold plate, minus the CDU approach, minus any margin the owner wants. Choosing the class is therefore a joint decision between the IT, mechanical and electrical teams. It is the single largest lever in this guide.

Worked example 1 — Converting the IT load to heat-rejection duty

The heat-rejection plant must reject the IT heat plus the heat added by pumps, CDUs and residual air-side equipment. For the reference facility, Keentel assumes 3 MW of such heat on top of 100 MW of IT:

Keentel engineering diagram 1

Keentel engineering diagram 2

The IT load alone would be about 28,400 tons. The difference matters: forgetting pump and auxiliary heat undersizes the plant by about 3%, which is the kind of margin a plant needs on the design day.

Worked example 2 — Facility water flow

Water flow for a given heat load and range follows the standard water-side equation, where 500 is the constant for water in gpm, Btu/h and °F:

Keentel engineering diagram 3

Range (ΔT) Facility water flow Notes
15 °F (8.3 K) 46,860 gpm More flow, larger pipes and pumps
18 °F (10 K) 39,050 gpm (about 2,460 L/s) Reference design
20 °F (11.1 K) 35,145 gpm Less flow, but requires warmer return water

A wider range cuts flow and pumping energy, and it helps dry coolers by raising the average water temperature in the coil. It is limited by the IT coolant temperature rise the CDUs can deliver.

How Keentel Engineering helps here. Keentel's MEP and electrical teams build a single heat and flow balance from chip to atmosphere, so the IT vendor's coolant limits, CDU approach, facility water class, pipe sizes and pump motors are all consistent. That balance becomes the basis of design for both the mechanical selections and the electrical load list.

3. Evaporative cooling towers: how they work

A cooling tower brings warm facility water into direct contact with outdoor air. A small fraction of the water evaporates, and the latent heat of evaporation cools the rest. Because evaporation is limited by how much moisture the air can absorb, a tower's leaving water temperature approaches the wet-bulb temperature, not the dry-bulb.

Two performance terms describe a tower:

Range — return water temperature minus supply water temperature (18 °F in our reference design).

Approach — supply water temperature minus the entering air wet-bulb temperature. Practical towers are selected for approaches of about 5–10 °F; smaller approaches need much larger towers.

For the reference facility at 86 °F supply and a 7 °F approach, the tower can deliver design water whenever the wet-bulb is at or below 79 °F. Many US locations rarely exceed that wet-bulb, which is why towers can serve W32 water with little or no trim chiller support.

Open towers and closed-circuit coolers
Type How it works Data center use
Open (direct-contact) tower Facility or condenser water flows over fill in direct contact with air Common; normally isolated from the CDUs through a plate heat exchanger so tower water never reaches the IT loop
Closed-circuit cooler (fluid cooler) Facility water flows inside a coil; a separate spray water circuit wets the outside of the coil Keeps the facility loop clean and sealed; larger and more costly per ton
Tower plus plate heat exchanger Open tower water on one side, clean closed facility loop on the other The usual arrangement for liquid-cooled AI halls; adds a few degrees of approach

Keeping the tower water physically separate from the facility loop is standard practice for liquid-cooled IT. Tower water picks up dust, organic material and biological growth; the facility loop and CDUs need clean, chemically stable water.

The water balance of a tower

Makeup water replaces three losses: evaporation (E), blowdown (B) and drift (D). Drift from modern towers with drift eliminators is very small and is neglected here.

Evaporation can be estimated from the heat load. With about 1,000 Btu absorbed per pound of water evaporated, and roughly 85% of the heat rejected as latent heat (the rest is sensible heating of the air):

Keentel engineering diagram 4

The widely used rule of thumb — about 1% of the circulating flow for every 10 °F of range, or roughly 0.00085 × gpm × range in °F — gives the same answer for our reference plant.

Blowdown controls dissolved solids. If the makeup water carries a given concentration of minerals and the tower water is allowed to reach COC times that concentration:

Keentel engineering diagram 5

Worked example 3 — Makeup water for a 100 MW IT load

With 103 MW of heat at full output, evaporation is about 597 gpm. Blowdown and makeup then depend on the cycles of concentration the water chemistry allows:

Cycles of concentration Blowdown Makeup Makeup per day at full load
3 298 gpm 895 gpm 1.29 million gallons
4 199 gpm 796 gpm 1.15 million gallons
6 119 gpm 716 gpm 1.03 million gallons
8 85 gpm 682 gpm 0.98 million gallons

Over a year at an 85% average load factor, the reference plant at 4 cycles uses about 356 million gallons of makeup — roughly 1,090 acre-feet — and at 6 cycles about 320 million gallons (980 acre-feet).

The lesson is that most of a tower's water is evaporated, and evaporation is set by physics. Raising cycles from 3 to 8 saves about a quarter of the makeup, but no chemistry program can eliminate evaporation. The only ways to use much less water are to reject heat sensibly (dry or hybrid) or to reject less heat.

Worked example 4 — Water usage effectiveness

WUE is defined by The Green Grid and in ISO/IEC 30134-9 as annual site water use divided by IT energy:

Keentel engineering diagram 6

For the reference tower plant at 4 cycles, annual makeup is about 1.35 billion liters against 745 million kWh of IT energy (100 MW × 8,760 h × 0.85), so WUE ≈ 1.81 L/kWh(about 478 gallons per MWh). At 6 cycles it is about 1.63 L/kWh. These values sit in the range commonly reported for tower-cooled facilities, which is why WUE alone often decides public perception of a project.

Keentel Study Spotlight — Water and energy balance study. For each candidate site, Keentel builds an hour-by-hour model of the facility water loop, the heat-rejection plant and the IT load profile using the site's real weather files. The study reports annual and peak water use, WUE, PUE, design-day electrical demand, trim-chiller hours and lifecycle cost for each architecture, on one consistent basis that the owner, the utility and the water provider can all review.

4. Water chemistry, Legionella and discharge

Every wet heat-rejection system — open towers, closed-circuit coolers and the wetted media of hybrid coolers — is a building water system with public-health obligations.

Water treatment program elements
Element Purpose
Conductivity-controlled blowdown Holds dissolved solids at the target cycles of concentration
Scale inhibition and pH control Prevents calcium carbonate and silica scale on fill and coils
Corrosion inhibition Protects steel, copper and galvanized surfaces
Biocide program (oxidizing and non-oxidizing) Controls bacteria, algae and biofilm
Filtration (side-stream) Removes suspended solids and dust
Makeup pretreatment Softening or reverse osmosis where makeup water is hard or high in silica, allowing higher cycles
Metering Separate meters on makeup and blowdown for water accounting and sewer credits
Legionella

ASHRAE Standard 188 requires a water management program for building water systems, including cooling towers, built around a hazard analysis, control locations, control limits, monitoring and corrective actions. Many states and cities add their own cooling tower registration and testing rules. For hybrid coolers, the spray or pad water is also a potential source of aerosols and must be included in the program, with drain-down and flushing when the wet mode is idle.

Discharge

Blowdown is wastewater. It typically goes to the municipal sewer under an industrial user permit, sometimes after treatment. Large campuses may face limits on total dissolved solids, temperature, and the chemicals in the treatment program, and some municipalities apply sewer charges that exceed the water charge. In water-scarce regions, zero-liquid-discharge treatment or reuse of blowdown may be required, adding electrical load and cost.

Worked example 5 — Annual water and sewer cost

For the reference tower plant at 4 cycles and an 85% load factor, Keentel's model gives about 355.6 million gallons of makeup (355,600 kgal) and 88.9 million gallons of blowdown (88,900 kgal) per year. With illustrative rates of $6.00/kgal for water, $8.00/kgal for sewer and $0.90/kgal for treatment chemicals:

Item Annual quantity Illustrative cost
Makeup water 355,600 kgal $2.13 million
Sewer on blowdown 88,900 kgal $0.71 million
Treatment chemicals Per kgal of makeup $0.32 million
Total About $3.2 million per year

Water costs vary widely across the US, and some utilities offer evaporation credits on sewer charges if evaporation is metered. Even so, at campus scale water is a seven-figure annual line item, comparable to the electricity cost difference between architectures.

How Keentel Engineering helps here. Keentel coordinates the electrical side of water treatment and metering — chemical feed panels, reverse-osmosis skids, side-stream filters, conductivity and flow instrumentation on the SCADA or building management system — and supports owners in documenting water use for permits, sustainability reporting and emerging state disclosure requirements.

5. Hybrid coolers: dry most of the year, wet when it counts

A hybrid cooler is a dry finned-coil heat exchanger with a way to use water only when the air is too hot. There are two common arrangements:

Adiabatic precooling. Wetted pads or fine sprays sit in front of the coil. Water evaporates into the entering air, cooling it toward the wet-bulb before it reaches the dry coil. The coil itself stays dry.

Evaporative (wet) assist. Water is sprayed onto the coil surface, so the coil behaves like a closed-circuit cooler during hot hours.

In both cases the cooler runs dry whenever the outdoor dry-bulb is low enough to meet the setpoint, then switches to wet operation as the temperature rises. The control strategy — when to switch, how many units to wet, and how to stage fans — determines how much water and energy the plant actually uses.

Operating modes
Mode When it runs Water Fan energy
Dry, reduced fan speed Cool hours with ample margin None Low (fan power falls with roughly the cube of speed)
Dry, full fan speed Warm hours near the dry limit None High
Adiabatic or wet assist Hot hours where dry-bulb plus approach exceeds the setpoint Moderate High
Wet assist plus trim chiller Extreme hours beyond the adiabatic limit Moderate High, plus chiller energy

A key engineering decision is the switch-over temperature. Switching early saves fan energy but uses water; switching late saves water but runs fans at full speed. Owners with strict water targets choose a late switch-over; owners with tight peak-demand limits choose an earlier one.

Worked example 6 — Hybrid plant operating hours and annual water

Keentel modeled a hybrid plant serving W32 water (86 °F supply) with a 12 °F dry approach and 80% adiabatic effectiveness. In adiabatic mode, water use per hour was taken as 45% of a tower's evaporation at the same load, plus 10% for pad bleed. These are illustrative modeling assumptions, not manufacturer data.

Synthetic climate Dry hours Adiabatic hours Hours needing trim beyond adiabatic Annual water Saving vs. tower at 4 cycles
Ashburn-like (mild-humid) 7,296 999 465 22.1 million gal 94%
Dallas-like (hot-humid) 5,764 1,598 1,398 45.2 million gal 87%
Phoenix-like (hot-dry) 4,021 3,251 1,488 71.4 million gal 80%

Two results stand out. First, a hybrid plant saves most of a tower's water in every climate we modeled. Second, at W32 water the hybrid still needs mechanical trim on 465 to 1,488 hours a year. Those are the hottest hours, and they set the plant's peak electrical demand, as Section 11 shows.

How Keentel Engineering helps here. Keentel reviews hybrid control sequences together with the electrical design, so the switch-over and fan-staging logic respects the owner's water budget and the site's peak-demand limit, and so the controls, sensors and valves needed for wet operation are on the correct power sources.

6. Closed-loop dry coolers and trim chillers

A dry cooler is a finned-tube coil with fans. Facility water (or a water-glycol mixture) flows inside the tubes and is cooled by outdoor air passing over the fins. No water is evaporated in routine operation. Because heat leaves only as sensible heat, the coolest water a dry cooler can deliver is the outdoor dry-bulb temperature plus its approach, typically 8–15 °F at full load.

Strengths and limits
Strength Limit
No routine water use, no blowdown, no plume, no Legionella exposure from the coil Leaving water can never be colder than the air; on a 105 °F afternoon the water is at least 113–120 °F
Sealed loop stays clean; simple water treatment Much larger coil face area and many more fans than towers for the same heat
Well suited to warm-water liquid cooling (W40, W45) Highest fan energy per ton, and highest property-line noise
Fewer operating staff and chemicals Needs trim chillers if the facility water class is too cold for the climate
Glycol

In climates with freezing weather, dry cooler loops often use propylene or ethylene glycol to protect the coils. Glycol lowers specific heat and raises viscosity, so the loop needs more flow for the same heat and the coil transfers heat less effectively.

Worked example 7 — Glycol flow penalty

Using approximate properties near 100 °F for about 30% propylene glycol (specific heat about 0.93 Btu/lb·°F and density about 63.4 lb/ft³, versus 1.00 and 62.0 for water), Keentel's estimate is that the loop needs about 5% more volumetric flow to carry the same heat at the same range. Coil heat transfer also falls because of higher viscosity. The exact derate depends on the coil design, concentration and temperature, so it must come from the manufacturer's selection at the actual fluid. Many designs avoid glycol in the main facility loop by using an intermediate heat exchanger or drain-down freeze protection.

Trim chillers

A trim chiller cools the facility water the rest of the way when the dry coolers cannot reach the setpoint. In a W32 design in a hot climate, trim chillers may carry a large share of the heat on design day. In a W40 or W45 design they may run only a few hours a year, or not at all. Their electrical demand is the single biggest driver of the dry plant's peak load.

How Keentel Engineering helps here. Trim chillers are large motor loads with starting currents, harmonics and power-quality behavior that must be coordinated with the medium-voltage system and the generators. Keentel sizes their feeders and transformers, studies their starting and restart sequences, and includes them in the generator and utility service calculations.

7. Climate: why the same plant behaves differently in Dallas, Phoenix and Ashburn

The choice between evaporative and dry heat rejection is ultimately a choice about which air temperature the plant works against.

Towers work against the wet-bulb. In the US, design wet-bulbs fall in a fairly narrow band (roughly the mid-70s to low-80s °F for most populated regions).

Dry coolers work against the dry-bulb, which varies far more: design dry-bulbs range from the high 80s in the mid-Atlantic to around 110 °F or more in the desert Southwest.

Hybrids work against something in between, depending on how much water they are allowed to use.

ASHRAE publishes climatic design conditions, including 0.4%, 1% and 2% annual cooling dry-bulb and evaporation wet-bulb values, in Chapter 14 of the ASHRAE Handbook — Fundamentals. Data center designs often go beyond the 0.4% values to an owner-specified extreme (for example, an N-year return-period maximum) because the facility must keep running on the hottest day, not just on 99.6% of hours.

Worked example 8 — Design conditions in the three synthetic climates
Synthetic climate 99.6th percentile dry-bulb 99.6th percentile wet-bulb Highest hour in the model
Ashburn-like 88.6 °F 76.7 °F 94.1 °F
Dallas-like 96.6 °F 80.6 °F 101.7 °F
Phoenix-like 108.9 °F 78.9 °F 115.2 °F

These values come from Keentel's synthetic model, not from ASHRAE. Real design values for those regions differ, and actual projects must use the ASHRAE tables and site-specific weather files. The model is useful because it captures the pattern: the Phoenix-like climate has the hottest dry-bulb but not the hottest wet-bulb, which is why towers work well in hot-dry climates and dry coolers struggle there.

Keentel engineering diagram 7

Figure 1. The three heat-rejection architectures compared in this guide, drawn by Keentel . Temperatures are indicative for direct-to-chip liquid cooling and depend on the IT equipment's coolant limits.

8. The facility water temperature is the master variable

If one decision deserves to be made first, it is the facility water class. The warmer the water the IT equipment can accept, the fewer hours any plant needs water or chillers.

Worked example 9 — How much trim does a dry plant need on the design day?

For a dry cooler with a 12 °F approach, the leaving water temperature on the design day is the design dry-bulb plus 12 °F. With an 18 °F range, the trim chiller must remove the heat between that temperature and the setpoint. Keentel's model gives the share of design-day heat that the trim chillers must carry:

Synthetic climate Dry cooler leaving water on design day W32 (86 °F supply) W40 (104 °F supply) W45 (113 °F supply)
Ashburn-like 100.6 °F 81% 0% 0%
Dallas-like 108.6 °F 100% 26% 0%
Phoenix-like 120.9 °F 100% 94% 44%

The table explains much of the industry's move toward warm-water liquid cooling. In a mild climate, moving from W32 to W40 eliminates trim chillers on the design day entirely. In a hot-humid climate, W45 does the same. In the desert Southwest, even W45 leaves a large trim requirement for a pure dry plant, which is why hybrids or towers often remain the practical answer there.

What limits the water temperature

IT equipment limits. The server maker's maximum coolant inlet temperature at the cold plate, often expressed in the ASHRAE W-class the equipment supports.

CDU approach. Each degree of CDU approach reduces the facility water temperature available.

Air-side loads. Even liquid-cooled halls usually have some air-cooled equipment (power supplies, storage, network) needing colder water or separate cooling.

Reliability margin. Owners often hold a few degrees in reserve for fouling, sensor error and future IT generations.

Heat reuse. Warmer return water makes heat reuse for district heating or industrial processes more practical.

Keentel Study Spotlight — Facility water class optimization. Keentel evaluates W27, W32, W40 and W45 options against the IT roadmap, the climate file and the utility tariff, and reports the effect of each on trim-chiller capacity, annual energy, water, generator sizing and the utility service request. Owners see in one table what each degree of warmer water is worth.

9. Energy: fans, pumps, chillers and PUE

The heat-rejection plant consumes electricity in three places: fans, pumps and, where installed, trim chillers.

Fans

Fan power at full speed depends on airflow and static pressure. Towers move the least air per ton because evaporation carries most of the heat; dry coolers move the most because air must warm up by enough degrees to carry all of it sensibly. With variable-frequency drives, fan power falls roughly with the cube of speed (the fan affinity laws):

Keentel engineering diagram 8

At 70% speed a fan draws about 34% of its full-speed power. That is why oversizing dry-cooler coil area and running more fans slower is a common and effective energy strategy, at the cost of land and capital.

For the reference facility, Keentel used illustrative full-speed fan demand of 8 kW per MW of heat for towers, 14 kW/MW for hybrids and 20 kW/MW for dry coolers:

Architecture Fan demand at full speed (103 MW of heat)
Evaporative towers About 824 kW
Hybrid coolers About 1,442 kW
Dry coolers About 2,060 kW
Pumps

Pump power follows the standard hydraulic relation, with flow in gpm, head in feet and η the pump efficiency:

Keentel engineering diagram 9

Worked example 10 — Facility water pump power

For 39,050 gpm, a pump efficiency of 75% and a motor efficiency of 95%:

Loop Total head Electrical input
Closed facility loop serving dry or hybrid coolers 110 ft About 1,135 kW
Open tower loop, including static lift to the tower distribution basin and the plate heat exchanger 140 ft About 1,445 kW

Open towers lose part of their fan-energy advantage to the extra pumping head. In practice designers often separate the condenser-water pumps (tower side) from the facility pumps (CDU side) across a plate heat exchanger, and the two sets together set the plant's pump demand.

Worked example 11 — Annual heat-rejection energy and PUE in the hot-humid climate

Keentel's hour-by-hour model for the Dallas-like climate at W32 water, with VFD fan control and trim chillers at a coefficient of performance of 6, gives:

Architecture Fans and pumps Trim chillers Annual energy cost at $70/MWh Facility PUE (model)
Evaporative towers 13,190 MWh 110 MWh About $0.93 million 1.078
Hybrid coolers 14,580 MWh 4,160 MWh About $1.31 million 1.085
Dry coolers 17,970 MWh 21,050 MWh About $2.73 million 1.112

The PUE values include an assumed 4.5% for electrical distribution losses (transformers, UPS and cables) and 1.5% for lighting, controls and residual air-side cooling, so the heat-rejection plant is the only thing varying between rows.

Two observations follow. First, every option produces a very good PUE by historical standards, because warm-water liquid cooling removes the large chiller loads of older designs. Second, the spread between options — about 26,000 MWh a year, or about $1.8 million at the illustrative price — is driven mostly by trim chillers, not fans. Raising the water to W40 changes the picture: the model then gives about 10,930 MWh and zero trim hours for the hybrid, and about 12,330 MWh for the dry plant.

ASHRAE Standard 90.4

ASHRAE 90.4-2022, Energy Standard for Data Centers , sets minimum efficiency through a mechanical load component (MLC) and an electrical loss component (ELC), rather than a single PUE target. Many states and cities adopt 90.4 through their energy codes (often by reference from ASHRAE 90.1 or the International Energy Conservation Code). Designers should confirm which edition the authority having jurisdiction has adopted and run the compliance calculation early, because the choice of heat-rejection plant directly sets the MLC.

How Keentel Engineering helps here. Keentel's energy calculations use the same load list as the electrical design, so the annual PUE, the ASHRAE 90.4 compliance calculation, the utility demand estimate and the generator sizing are all drawn from one consistent model rather than from separate spreadsheets that drift apart during design.

10. Water: consumption, withdrawal and the new reporting landscape

Consumption versus withdrawal

Water professionals distinguish between withdrawal(water taken from a source) and consumption(water that does not return to the local watershed). Evaporation is consumption. Blowdown is withdrawn but returned to the sewer and, after treatment, usually to the watershed. For the reference tower plant at 4 cycles, about 75% of the makeup is consumed through evaporation and about 25% is returned as blowdown.

That distinction matters in public debate. A facility reporting "1 million gallons a day" may be describing withdrawal, consumption or both. Clear reporting builds trust.

Indirect water

Electricity generation also uses water, particularly thermoelectric plants with evaporative cooling. A dry cooling plant that leans on trim chillers shifts part of its water footprint upstream to the power plant. The size of that indirect footprint depends heavily on the regional generation mix and is outside the site's control, but sophisticated sustainability reporting increasingly includes it.

The reporting and policy landscape

Water use by data centers has become a legislative topic:

The Congressional Research Service published Data Centers and Water: Frequently Asked Questions (report R49057), summarizing federal and state issues.

Several states have reviewed data center water use and permitting; for example, Texas Senate committees examined data center water use in 2026, and state legislative research offices have published overviews of state data center policies.

Proposed federal legislation has sought standardized reporting of data center energy and water use.

Rules are changing quickly, so owners should treat water reporting as a design requirement: meter makeup, blowdown and any adiabatic water separately, log them in the building management system, and keep the data auditable.

Worked example 12 — Hybrid water in context

For the Dallas-like climate, the hybrid plant at W32 uses about 45 million gallons a year against about 356 million gallons for towers at 4 cycles. On a WUE basis that is roughly 0.23 L/kWh against 1.81 L/kWh. Designed for W40 water, the same hybrid would wet its coils on far fewer hours and use less still. For a community water utility, the difference between the two plants is roughly the annual use of a few thousand households (based on typical US household use of the order of 100,000 gallons a year), which is often the number that decides a public hearing.

How Keentel Engineering helps here. Keentel helps owners prepare the technical basis for water supply agreements and discharge permits: peak-day and annual demand, sensitivity to cycles of concentration and to the facility water class, metering design and the data trail regulators increasingly expect.

11. Electrical consequences: the design day sets the service size

The annual energy comparison in Section 9 understates the difference between options. Electrical equipment, utility service and generators must be sized for the worst hour, and for dry plants the worst hour is far worse than the average.

Worked example 13 — Design-day heat-rejection plant demand

Keentel calculated fan, pump and trim-chiller demand at each synthetic climate's design condition, using 0.55–0.75 kW per ton for trim chillers depending on lift. Results in MW of electrical demand for 100 MW of IT:

Architecture and water class Ashburn-like Dallas-like Phoenix-like
Evaporative towers, W32 2.3 3.7 2.3
Hybrid, W32 7.1 11.3 12.3
Hybrid, W40 2.6 2.6 2.6
Dry, W32 21.0 25.2 25.2
Dry, W40 3.2 8.1 21.1
Dry, W45 3.2 3.2 10.9

Keentel engineering diagram 10

Figure 2. Design-day electrical demand of the heat-rejection plant for 100 MW of IT, by architecture, facility water class and synthetic climate ( Keentel model, illustrative).

The spread is a factor of ten. A dry plant held to W32 water adds more than 20 MW of design-day demand — about a fifth of the IT load — and almost all of it is trim chillers running on the hottest afternoons, which are often the utility's system peak hours.

Worked example 14 — What that demand means at medium voltage

At 0.92 power factor, Keentel's conversions are:

Cooling-plant demand Apparent power Current at 13.8 kV Current at 34.5 kV
2.6 MW (hybrid at W40) 2.83 MVA 118 A 47 A
9.0 MW 9.78 MVA 409 A 164 A
22.0 MW (dry at W32, hot climate) 23.9 MVA 1,000 A 400 A

A 22 MW cooling plant is not a few extra breakers. It is a dedicated 13.8 kV feeder system or an additional 34.5/13.8 kV transformer, more switchgear lineups, larger generator plant and a larger request to the utility. For a campus already near the limit of an interconnection or a transformer delivery slot, choosing a warmer water class or a hybrid can be the difference between fitting in the available service and waiting years for a larger one.

Interconnection and transmission planning

Utilities study large loads at their requested peak demand. If the cooling plant's design-day demand is 20 MW higher than necessary, the utility will plan for it, allocate upgrade costs against it and, under some tariffs, charge demand or reservation fees on it. Conversely, a utility may ask the customer how its load behaves on extreme days, during voltage disturbances and when cooling equipment restarts. Keentel's guide on studying large loads and generation together covers how those studies work.

Keentel Study Spotlight — Cooling-driven load profile for the utility. Keentel prepares the large-load data utilities now request: an hourly load profile for typical and extreme years, design-day peak with the cooling plant's contribution separated, ramp rates, motor starting and restart behavior, and power quality. Presenting a credible, weather-driven profile often shortens the utility's study and avoids overbuilding the service.

12. Electrical design of the heat-rejection plant

Whatever architecture is chosen, the heat-rejection plant is a large collection of motors: fans, pumps, compressors, chemical feed and controls. Its electrical design deserves the same rigor as the IT power path.

Typical electrical arrangement
Element Typical US practice for a 100 MW AI campus
Service to the plant 13.8 kV or 34.5 kV feeders from the campus substation, often A and B sources
Transformation 13.8 kV–480Y/277 V unit substations, sized for the design-day plant demand plus spare capacity
Motor control 480 V motor control centers or switchboards with VFDs for fans and pumps
Large chillers 4.16 kV or 13.8 kV medium-voltage motors on large centrifugal machines; 480 V on smaller units
Controls and CDU pumps Uninterruptible power for controls and for loads whose loss would interrupt coolant flow (see Section 13)
Standby Generator-backed distribution for the whole cooling plant
Variable-frequency drives and harmonics

Almost every fan and pump in a modern plant runs on a VFD. Six-pulse drives draw non-sinusoidal current that can raise voltage distortion on the 480 V and medium-voltage buses and at the utility point of common coupling. IEEE Std 519-2022 sets limits on voltage distortion and on total demand distortion (TDD) of current, the latter depending on the ratio of available short-circuit current to load current at the point of common coupling.

Worked example 15 — Harmonic contribution of plant VFDs

Consider a 480 V mechanical switchboard with a 5 MW maximum demand, of which 2 MW is fan and pump VFDs. Approximating TDD as the drives' current distortion weighted by their share of demand:

Drive technology Typical current distortion of the drive Estimated TDD at the switchboard
Standard six-pulse with line reactor About 35–40% About 15%
Active front end or low-harmonic drive About 5% About 2%

A TDD of 15% would exceed common IEEE 519 limits at many points of common coupling. Active-front-end drives, 18-pulse drives or active filters cost more but avoid harmonic heating of transformers, nuisance tripping and resonance with capacitor banks. The decision should come from a harmonic study, not a rule of thumb. Keentel's guide to harmonics in plain English and IEEE 519 explains the limits and their application.

Arc flash and short circuit

A 480 V switchboard fed by a 3,000 kVA unit substation can see available fault currents of 50–65 kA, and the incident energy at fan and pump MCCs depends heavily on the upstream protective device's clearing time. NFPA 70E requires an arc flash risk assessment and equipment labeling, and the NEC requires arc energy reduction for larger circuit breakers. The cooling plant, which operators service frequently and often while energized, deserves particular attention.

Worked example 16 — Generator sizing for the cooling plant

Standby generators must carry the cooling plant on the design day, including motor restart. Using 2.5 MW generator sets and a 25% allowance for motor starting and future margin:

Case Design-day cooling demand Generator sets of 2.5 MW needed for the cooling plant alone
Evaporative towers, Dallas-like 3.7 MW (with trim on extreme hours) 2
Dry plant at W32, Phoenix-like 25.2 MW 13

Eleven additional generator sets per 100 MW of IT — plus their fuel storage, air permits, enclosures, paralleling switchgear and maintenance — is a substantial cost that a cooling comparison based only on PUE would miss. Generator count also affects air-quality permitting, because emergency engines have hours-of-operation and emissions limits.

How Keentel Engineering helps here. Keentel designs the cooling plant's electrical distribution, performs short-circuit, protective-device coordination, arc flash (IEEE 1584 and NFPA 70E) and harmonic (IEEE 519) studies, and sizes generator plants with motor-starting and restart sequences that reflect how the mechanical plant actually recovers after a utility outage.

13. Resilience: when the cooling loop becomes part of the critical path

With air cooling, a short loss of cooling gave operators minutes before IT equipment overheated, thanks to the thermal mass of the room air and chilled water. With direct-to-chip liquid cooling, loss of coolant flow at the cold plates can push accelerators to thermal limits in seconds. Keentel's digital-twin study of pump failures showed throttle thresholds reached within seconds after a total loss of flow.

That changes the resilience design:

Layer Typical approach
TCS pumps in the CDUs Redundant pumps; on uninterruptible power with the IT load
Facility water pumps N+1 or 2N; on a mechanical UPS or with enough loop thermal mass to ride through generator start
Heat-rejection fans Generator-backed; brief interruption tolerable if the loop has thermal mass
Trim chillers Generator-backed with controlled restart; restart times of several minutes must be covered by loop thermal mass or buffer tanks
Controls and sensors Uninterruptible power, redundant controllers, fail-safe valve positions
Water supply (towers) On-site storage for a defined number of hours; redundant makeup sources
Worked example 17 — Thermal ride-through of the facility loop

If heat rejection stops completely while the IT load continues, the facility loop warms at a rate set by its water volume. With 351.5 million Btu/h of heat and water at 8.34 lb/gal:

Keentel engineering diagram 11

Facility loop water volume Temperature rise rate with no heat rejection Time to rise 9 °F (5 K)
150,000 gallons About 4.7 °F per minute About 115 seconds
300,000 gallons About 2.3 °F per minute About 230 seconds

Generator start and transfer typically take 10–30 seconds, but a chiller restart may take several minutes. A plant that depends on trim chillers in summer therefore needs either more loop volume (buffer tanks), chillers with fast-restart features, or IT load capping coordinated with the cooling controls. A tower or warm-water dry plant whose fans and pumps restart in under a minute is inherently easier to ride through.

Water storage for evaporative plants

Towers stop working if makeup water is lost. Owners targeting high availability usually provide on-site storage for a defined period (commonly expressed in hours or days at design evaporation) and two independent makeup sources. At about 800 gpm of makeup for 100 MW of IT, 48 hours of storage is roughly 2.3 million gallons, a significant structure with its own footprint and permitting.

Tier considerations

Uptime Institute Tier objectives apply to the cooling plant as much as to the electrical system. A concurrently maintainable (Tier III) plant needs redundant capacity components and distribution paths so any component can be removed for maintenance; a fault-tolerant (Tier IV) plant must also survive a single failure with automatic response and compartmentalization. Water supply, makeup pumps and treatment for evaporative plants must be included in that analysis. Keentel's guide to data center Tiers for MEP engineers discusses these requirements in depth.

Keentel Study Spotlight — Cooling ride-through and restart study. Keentel models the facility loop, CDUs, pumps, heat-rejection plant and generators through a utility outage, generator start, transfer and staged restart, and reports coolant temperatures at the racks over time. The study identifies which loads must be on UPS, how large buffer tanks must be, and how the restart sequence must be programmed so that motor inrush does not overload the generators.

14. Grid interaction: cooling plants and large-load behavior

At campus scale, the cooling plant affects not only how much power the facility draws but how it behaves on the grid.

Voltage disturbances. NERC has published an incident review of a large loss of voltage-sensitive load and guidance on large-load integration. Data centers that transfer to backup power during a grid fault can drop hundreds of megawatts at once. Cooling-plant drives and controls must ride through the same disturbances as the IT systems, or the facility may lose cooling after the grid has already recovered.

Restart surges. After a transfer back to utility power, staged restart of chillers and fans should be coordinated with the utility to avoid sudden demand swings.

Weather-driven peaks. Dry plants add load on hot afternoons that coincide with system peaks. Utilities may ask large loads to reduce demand in emergencies; a plant with thermal storage or warm-water capability can shed cooling load briefly without affecting IT.

Flexibility. Some campuses are negotiating flexible or interruptible service in exchange for faster interconnection. Cooling plants with buffer tanks, ice or chilled-water storage, or warm-water operation give the operator room to shift load. Keentel's guide to grid flexibility covers those arrangements.

How Keentel Engineering helps here. Keentel studies large-load ride-through and restart behavior, including the cooling plant's drives, chillers and controls, and prepares the technical information utilities and transmission planners now request under evolving NERC and regional large-load requirements.

15. Site layout, noise, plume and permitting

Footprint

The heat-rejection yard must fit not only the coolers but also airflow clearances that prevent hot exhaust air from recirculating into the inlets, maintenance access, piping corridors, electrical rooms, water treatment and, for towers, water storage.

Worked example 18 — Converting typical yard areas to US units
Architecture Typical yard dimensions (100 MW) In feet Yard area
Evaporative towers About 140 m × 60 m About 459 ft × 197 ft About 90,400 ft² (2.1 acres)
Hybrid coolers About 130 m × 55 m About 427 ft × 180 ft About 77,000 ft² (1.8 acres)
Dry coolers About 120 m × 50 m About 394 ft × 164 ft About 64,600 ft² (1.5 acres)

Commonly cited site-area ranges of 0.8–1.2 ha (2.0–3.0 acres) for towers, 0.6–1.0 ha (1.5–2.5 acres) for hybrids and 0.5–0.9 ha (1.2–2.2 acres) for dry coolers should be treated with caution. Dry coolers need more coil area per ton than towers, and the compact dry figures assume warm water, stacked V-bank coolers or rooftop placement. On a real site, setbacks for noise and recirculation often dominate.

Noise

Dry and hybrid yards carry many large fans. Sound power from multiple identical sources adds logarithmically, and sound pressure falls with distance:

Keentel engineering diagram 12

where r is in meters and the second relation is a simple free-field estimate for a point source.

Worked example 19 — Property-line noise screening

A yard with 72 fans, each with a sound power level of 94 dBA, has a total sound power of about 112.6 dBA. Treating the yard as one point source with no barriers or ground effects:

Distance to receiver Estimated sound pressure level
300 ft (91 m) About 62 dBA
600 ft (183 m) About 56 dBA
1,000 ft (305 m) About 52 dBA

Many local ordinances set nighttime limits at residential property lines in the range of 45–55 dBA. On a constrained site, a dry plant may need low-noise fans, barriers, more coolers running slower, or a larger setback. Noise studies should use proper propagation models with the actual layout; this screening only shows the scale of the issue.

Plume and visual impact

Towers and wet-assisted hybrids can produce a visible plume in cool, humid weather. Plume is rarely a safety issue but can affect permitting near airports and highways and can cause icing on nearby surfaces in winter. Plume-abated towers and dry-mode winter operation for hybrids reduce it.

Permitting checklist
Permit area Evaporative Hybrid Dry
Water supply agreement or water rights Major Moderate Minor
Wastewater discharge (blowdown) Major Minor to moderate Minimal
Legionella registration and water management program Required Required for wetted media Generally not for the coils
Noise ordinance Moderate Moderate to major Major
Air permit for generators Smaller generator plant Depends on trim needs Can be largest
Building and energy code (ASHRAE 90.4) Yes Yes Yes
Visual and plume impact Possible Limited None

How Keentel Engineering helps here. Keentel supports permitting with the electrical, energy and load data permit reviewers request, coordinates with acoustical and civil consultants on yard layout and setbacks, and documents generator sizing so that air permits reflect the actual cooling-plant demand rather than conservative guesses.

16. Lifecycle cost and a decision framework

The water–energy trade-off in one picture

Keentel engineering diagram 13

Figure 3. Annual on-site water use against annual heat-rejection electricity for the three architectures in three synthetic climates, 100 MW of IT at W32 water ( Keentel model, illustrative). Towers sit at the high-water, low-energy corner; dry plants at the zero-water, high-energy corner; hybrids in between.
Worked example 20 — Twenty-year lifecycle cost in the hot-humid climate

Keentel compared the three architectures for the Dallas-like climate at W32 water. All inputs are illustrative and chosen to show method, not to predict a particular project's costs:

Installed heat-rejection cost: $130/kW of heat for towers (including plate heat exchangers and water storage), $210/kW for hybrids and $185/kW for dry coolers with trim chillers.

Energy at $70/MWh from Worked example 11.

Water, sewer and chemicals from Worked example 5 for towers; adiabatic water at the hybrid's modeled volume; a small allowance for dry-plant fluid and treatment.

Annual maintenance of $450,000 for towers, $380,000 for hybrids and $220,000 for dry coolers.

7% discount rate over 20 years.

Architecture Capital cost Annual operating cost 20-year present-value cost
Evaporative towers $13.4 million $4.55 million About $61.6 million
Hybrid coolers $21.6 million $2.02 million About $43.0 million
Dry coolers with trim chillers $19.1 million $2.97 million About $50.5 million

With these inputs, the hybrid is the lowest lifecycle cost in a hot-humid climate because it avoids most of the tower's water cost without incurring the dry plant's chiller energy. With lower water prices, the tower wins; with W40 water, the dry plant closes the gap sharply because its trim-chiller cost almost disappears. The capital costs here exclude the electrical and generator differences in Sections 11 and 12, which further penalize plants with high design-day demand. The result is sensitive enough that it must be recalculated for each site.

A decision framework
Question If the answer is… It favors…
Is reliable water available at reasonable cost, with discharge capacity? Yes, plentiful Evaporative towers
Limited or contested Hybrid or dry
What facility water class can the IT roadmap accept? W40 or warmer Dry or hybrid without trim chillers
W32 or colder Towers or hybrids; dry needs large trim
How hot is the design dry-bulb? Below about 95 °F Dry works well with warm water
Above about 105 °F Towers or hybrids
Is the utility service or interconnection constrained? Yes Options with low design-day demand: towers, or hybrid/dry at warm water
Are noise limits strict at the property line? Yes Towers (fewer fans), large setbacks, or low-noise dry coolers
Does the owner have public water commitments? Yes Dry or hybrid, with transparent WUE reporting
Does the site have freezing winters? Yes Glycol or drain-down for dry coils; winter plume control for towers
Is heat reuse planned? Yes Warm-water dry or hybrid plants with higher return temperatures

Keentel Study Spotlight — Cooling architecture selection study. Keentel's selection study combines the water and energy model, design-day electrical demand, generator and utility service impact, noise screening, footprint and a lifecycle cost comparison into one decision matrix weighted by the owner's priorities. The study is designed to be read by the owner's board, the utility and the permitting authority, not just by engineers.

17. Commissioning and acceptance testing

A heat-rejection plant that looks right on paper can still fall short in the field. Commissioning confirms capacity, controls and resilience before the IT load arrives.

Thermal performance testing

Cooling towers. The Cooling Technology Institute's acceptance test code ATC-105 defines how to field-test an open tower's thermal capability; ATC-105S covers closed-circuit coolers. CTI STD-201 provides third-party certification of rated thermal performance. Specifying CTI-certified equipment and a field acceptance test protects the owner against undersized towers.

Dry and hybrid coolers. Performance should be verified against the manufacturer's rated conditions with calibrated temperature, flow and airflow measurements, and with a defined correction method for ambient conditions on test day.

Integrated systems testing (IST)

For liquid-cooled AI halls, integrated testing typically includes:

Test What it proves
Load-bank heat test at stepped loads Plant capacity, approach and control stability at each step
Utility failure and generator transfer Coolant temperature stays within limits through transfer; UPS-backed loads stay running
Staged restart on generators Motor starting does not overload generators; restart sequence is correct
Component failure (pump, fan bank, cooler, chiller) Redundancy works automatically; temperatures stay within limits
Wet/dry mode transition (hybrids) Smooth switch-over without temperature excursions or water hammer
Water supply loss (evaporative) Storage lasts the design duration; alarms and backup makeup sources work
Controls failure Fail-safe positions and redundant controllers behave as designed
Power quality Harmonic distortion and voltage regulation within limits with all drives running

How Keentel Engineering helps here. Keentel writes and witnesses the electrical portions of integrated systems tests for data centers: transfer and restart sequences, UPS performance, generator loading with cooling motors, protective relay settings and power-quality measurements. We coordinate with the commissioning authority so electrical and mechanical tests are run together, the way the facility will actually operate.

18. Common mistakes and a review checklist

Ten mistakes Keentel sees in cooling-plant selection

1. Comparing options on annual PUE alone, without design-day demand, water, noise and generator impact.

2. Fixing the facility water temperature before asking the IT vendor what the hardware can accept, then designing a dry plant for W32 water in a hot climate.

3. Using average weather instead of design and extreme conditions for sizing.

4. Forgetting pump and auxiliary heat when sizing heat rejection.

5. Assuming hybrid water use is negligible without modeling the switch-over strategy against real weather.

6. Leaving the cooling plant off the UPS and ride-through analysis for liquid-cooled racks.

7. Underestimating trim-chiller demand in the electrical service and generator calculations.

8. Ignoring harmonics from hundreds of VFDs until transformers run hot or breakers trip.

9. Treating noise as a late-stage issue, then discovering the dry yard cannot meet the property-line limit.

10. Not metering water separately for makeup, blowdown and adiabatic use, leaving the owner unable to report WUE credibly.

Review checklist
Topic Check
Basis of design IT coolant limits, CDU approach, facility water class and range agreed in writing
Climate ASHRAE design conditions and an owner-specified extreme; multi-year hourly weather used for annual modeling
Heat balance IT plus pump, CDU and air-side heat included
Water Makeup, blowdown, adiabatic use, storage, treatment, discharge and permits quantified
Energy Hourly model including fans, pumps, trim chillers and controls
Electrical Design-day demand, MV feeders, transformers, MCCs, generators and UPS sized from the same model
Power quality Harmonic study with all drives; IEEE 519 compliance at the point of common coupling
Resilience Ride-through study; redundancy matching the Tier objective
Grid Large-load data for the utility, including cooling contribution and ride-through behavior
Site Footprint with clearances, noise screening, plume, setbacks
Public health ASHRAE 188 water management program for wet systems
Testing CTI acceptance tests and integrated systems tests in the specifications

19. Where AI cooling plants are heading

Warmer water. IT vendors are moving toward hardware that tolerates higher coolant temperatures, making W40 and W45 designs more common and chiller-free plants practical in more of the US.

Hybrid as the default compromise. Survey work by the Uptime Institute in 2025 described direct liquid cooling adoption as growing steadily rather than explosively, with many operators running mixed air and liquid estates. Hybrid heat rejection fits that mixed reality.

Water transparency. Federal and state attention to data center water use is likely to make metered, reported WUE a routine permit condition.

Heat reuse. Higher return temperatures make district heating and industrial heat reuse more attractive, turning a waste stream into a community asset in suitable locations.

Grid-aware cooling. Thermal storage and flexible cooling controls will increasingly be used to shape the facility's demand for the utility, not just to save energy.

How Keentel Engineering helps here. Keentel designs electrical systems that are ready for change: spare feeder positions and transformer capacity for future trim or reuse equipment, metering for new reporting rules, and controls integration that lets cooling respond to grid signals.

20. Water sources: potable, reclaimed, groundwater and on-site storage

When towers or hybrids are selected, the source of makeup water becomes a design topic of its own.

Source Advantages Engineering issues
Municipal potable water Reliable, consistent quality, simple permits Competes with community use; highest public scrutiny; cost
Reclaimed (treated wastewater) Reduces demand on potable supply; often favored by regulators Higher dissolved solids and nutrients; lower achievable cycles; more biocide and filtration; separate piping and backflow protection
Groundwater Independent of municipal supply Water rights and pumping permits; hardness and silica may limit cycles; well pumps add electrical load
Captured rainwater or condensate Small supplemental volumes Not enough to carry a large tower plant; storage and treatment needed

Reclaimed water is increasingly common for large campuses because it avoids drawing on drinking-water supplies. Its quality usually forces lower cycles of concentration, so the plant withdraws more water even though the water is not potable. Treatment equipment, additional filtration and the electrical loads to run them should be included in the design from the start.

On-site storage serves two purposes: covering interruptions of the makeup supply, and buffering daily peaks so the supply connection can be smaller. Its pumps, level controls and chemical feed must be on reliable power, because an evaporative plant without makeup water loses capacity within hours.

How Keentel Engineering helps here. Keentel designs the electrical service for water infrastructure on data center campuses — well pumps, booster pumps, reverse-osmosis and filtration skids, chemical feed, storage level controls — and integrates them into the facility's standby power and monitoring systems.

21. Mixed halls: liquid and air cooling in the same facility

Few AI halls are fully liquid cooled. Power supplies, memory, storage, network equipment and some legacy servers still reject heat to air, often 10–30% of the IT load depending on the hardware. That air-side heat is removed by computer room air handlers, fan walls or rear-door heat exchangers, which usually need colder water than the CDUs.

Common arrangements are:

Two water temperatures. A warm facility loop for CDUs and a colder loop for air-side equipment, sometimes produced by a small chiller plant or by a heat exchanger off the warm loop with trim.

Rear-door heat exchangers on warm water where the air-side load per rack is moderate.

Shared plant with blending. One heat-rejection plant serving both loops through mixing valves, which is simpler but forces the plant toward the colder requirement.

The share of air-cooled load matters to heat-rejection selection because it sets how much cold water the site must produce. A plant optimized for warm-water liquid cooling can be undermined by a large air-cooled fraction that needs chilled water on design day. Keentel's companion guide on CDUs discusses the air-side and liquid-side split from the IT perspective.

How Keentel Engineering helps here. Keentel's load lists separate liquid-cooled and air-cooled IT heat, so the electrical design reflects the right mix of CDU pumps, air handlers, fan walls and chillers, and so the utility service request is based on the real split rather than a single blended assumption.

22. A specification checklist for owners

Owners who will hire a design team, or review one, can use this checklist to make sure the cooling plant specifications cover what matters.

Specification item What to require
Basis of design Facility water class, range, CDU approach, air-cooled fraction and climate data source stated explicitly
Design condition ASHRAE design value plus an owner-specified extreme, and the required performance at each
Redundancy N+1, N+2 or 2N for coolers, pumps, chillers and water supply, consistent with the Tier objective
Thermal certification CTI STD-201 certification for towers; certified or witnessed ratings for dry and hybrid coolers
Field testing CTI ATC-105 or ATC-105S acceptance tests, or equivalent tests with a defined correction method
Water Maximum annual and peak-day water, cycles of concentration, metering points, storage hours
Water management ASHRAE 188 program, treatment equipment, Legionella sampling and response plan
Noise Maximum sound power per unit and property-line limits with a compliance test
Electrical Motor efficiency classes, VFD type and harmonic performance, MCC ratings, short-circuit ratings, arc flash labeling
Controls Redundant controllers, fail-safe positions, sequences for wet–dry switch-over and restart, BMS points list
Power continuity Which pumps and controls are on UPS; ride-through requirements; restart time limits
Integration Interfaces with CDUs, electrical power monitoring, utility signals and demand-response requests
Testing Integrated systems test scripts, including utility failure, restart and component failures
Documentation As-built drawings, setpoints, water and energy metering data retained for reporting

23. Questions to ask your design team

1. What facility water class did you design for, and has the IT vendor confirmed it in writing?

2. Which weather data did you use for annual energy and water, and which condition did you use for sizing?

3. What is the cooling plant's electrical demand on the design day, separately from the IT load?

4. How many trim-chiller hours does the design need, and what happens to peak demand if the water class can be raised?

5. How much water will the plant use on the peak day and over a year, and where will blowdown go?

6. Which cooling loads are on UPS, and how long can the loop ride through a total loss of heat rejection?

7. What does a harmonic study show at the point of common coupling with all drives running?

8. How many generator sets does the cooling plant add, and how does the restart sequence work?

9. What is the predicted noise level at the nearest property line at night?

10. How will water and energy be metered and reported?

Clear answers to these questions usually reveal whether the cooling architecture was chosen as a system or as a mechanical line item.

24. Operating the plant through the seasons

Selection is only half the story. A heat-rejection plant runs through four seasons, and each brings its own risks.

Summer. The plant runs at or near design capacity on the hottest afternoons. Towers face their highest wet-bulb hours and highest evaporation; hybrids switch into wet mode; dry plants run fans at full speed and call on trim chillers. Operators should verify spare capacity before each heat wave, confirm that redundant units are available rather than out for maintenance, and coordinate with the utility on any demand-response requests. Maintenance that removes capacity should be scheduled outside the summer peak.

Autumn and spring. These are the best windows for planned maintenance: fill and drift eliminator inspection, coil cleaning, fan and motor service, VFD checks and controls testing. They are also the seasons when the plant switches between operating modes most often, so sequences should be watched for hunting between wet and dry operation.

Winter. Towers risk icing on fill, louvers and nearby surfaces; basins need heaters or indoor sumps; plume can become visible. Dry coolers face freezing risk if the loop is water rather than glycol, especially during low-load or standby periods; drain-down or minimum-flow strategies must be tested. Hybrids should drain and dry their wet systems to avoid freezing and biological growth. Winter is also when warm-water plants can most easily support heat reuse.

All year. Water treatment, Legionella monitoring, fan and pump vibration trending, coil fouling checks (rising approach at constant load is the classic sign), drive health and electrical thermography should run continuously. Trending the plant's kW per ton and approach against the commissioning baseline gives early warning of fouling, failed fans or control problems before they become capacity shortfalls on the next design day.

Key operating indicators
Indicator What it reveals
Approach (leaving water minus wet-bulb or dry-bulb) Fouling, airflow problems, failed fans or nozzles
kW per ton of heat rejected Fan and pump efficiency, control tuning
Trim-chiller hours Whether the plant is meeting its warm-water design intent
Makeup and blowdown ratio Actual cycles of concentration and treatment performance
Adiabatic water per wet hour Pad or spray condition and switch-over tuning
Pump differential pressure and flow Strainer fouling, valve problems, air in the loop
Harmonic distortion and drive alarms Drive health and power-quality changes

How Keentel Engineering helps here. Keentel designs metering and power monitoring so these indicators come directly from the electrical and mechanical systems, and helps owners set up NFPA 70B electrical maintenance programs for the cooling plant's switchgear, MCCs, drives and motors alongside the mechanical maintenance plan.

25. Summary of the worked examples

No. Worked example Key result (illustrative)
1 IT load to heat-rejection duty 103 MW of heat, about 29,300 tons
2 Facility water flow 39,050 gpm at an 18 °F range
3 Tower makeup water About 600 gpm evaporated; 1.15 million gal/day makeup at 4 cycles
4 Water usage effectiveness About 1.81 L/kWh at 4 cycles; 1.63 L/kWh at 6
5 Water and sewer cost About $3.2 million per year
6 Hybrid hours and water 80–94% less water than towers across three climates
7 Glycol flow penalty About 5% more flow with about 30% propylene glycol
8 Synthetic design conditions Design dry-bulb from about 89 °F to 109 °F
9 Dry-plant trim on design day From 0% to 100% of heat depending on climate and water class
10 Pump power About 1,135 kW closed loop; 1,445 kW open loop
11 Annual energy and PUE (hot-humid) PUE 1.078 towers, 1.085 hybrid, 1.112 dry at W32
12 Hybrid water in context About 0.23 L/kWh against 1.81 L/kWh for towers
13 Design-day plant demand From about 2.3 MW to about 25 MW per 100 MW of IT
14 Medium-voltage impact 22 MW of cooling is about 1,000 A at 13.8 kV
15 VFD harmonics Estimated TDD about 15% with six-pulse drives, 2% with active front ends
16 Generators for cooling About 2 sets for towers against about 13 for a hot-climate dry plant at W32
17 Thermal ride-through About 2 minutes to rise 9 °F with 150,000 gallons
18 Yard areas in US units About 1.5–2.1 acres for the equipment yard alone
19 Noise screening About 62 dBA at 300 ft from a 72-fan yard
20 Twenty-year lifecycle cost Hybrid lowest in the hot-humid example

Part C — Three In-Depth Anonymous US Case Studies

The following case studies are composites built from conditions Keentel Engineering encounters on data center projects. Locations are described only by region, figures are rounded and illustrative, and no client, site or equipment supplier is identified.

Case study 1 — A 150 MW AI campus in North Texas chooses hybrid heat rejection

Situation

A developer acquired land in the Dallas–Fort Worth region for a 150 MW IT AI training campus, built in three 50 MW phases. The preliminary mechanical concept used open cooling towers with plate heat exchangers serving W32 facility water, a familiar design with low first cost. Two issues arose during site due diligence. The municipal water provider indicated that it could supply the tower makeup water for phase 1 but would need a new supply main and a formal water-use agreement for later phases. The city's sewer authority also flagged blowdown volume and dissolved solids for review. Separately, the utility's preliminary large-load study assumed a total campus demand that left little margin on the planned 345/34.5 kV substation transformers.

Keentel's scope

Keentel was engaged as owner's engineer for the electrical and MEP coordination and to lead a cooling architecture selection study with the mechanical engineer of record.

Analysis

Keentel scaled the reference-facility model to 150 MW of IT, using the site's multi-year hourly weather rather than the synthetic profile in this guide.

Metric (150 MW IT) Towers at W32, 4 cycles Hybrid at W32 Hybrid at W40 Dry at W32 with trim
Peak-day water About 1.7 million gallons Up to about 0.6 million gallons on the hottest days Small, only on extreme days Near zero
Annual water About 530 million gallons About 68 million gallons Well under half the W32 hybrid Near zero
Design-day cooling-plant demand About 5.5 MW About 17 MW About 3.9 MW About 38 MW
Additional generator sets for cooling (2.5 MW) About 3 About 9 About 2 About 19

The IT vendor's roadmap for the planned GPU racks allowed facility water up to 104 °F with the selected CDU approach, which made W40 feasible. Keentel's model showed that a hybrid plant at W40 used adiabatic assist only on the hottest afternoons and needed no trim chillers on the design day.

Electrical consequences

The W40 hybrid kept the cooling plant's design-day demand under 4 MW, about 34 MW less than the dry-at-W32 option. That margin let all three phases fit within the planned substation transformers without an additional unit.

The generator capacity dedicated to the cooling plant dropped to about two 2.5 MW sets for the whole campus, instead of about nineteen for the dry-at-W32 option.

The 480 V mechanical switchboards were designed with active-front-end drives after a harmonic study showed six-pulse drives would push TDD above the IEEE 519 limit at the 34.5 kV point of common coupling under light IT load.

CDU pumps and controls went on the IT UPS; facility pumps went on a dedicated mechanical UPS sized for a 30-second generator transfer, supported by 250,000 gallons of facility loop volume.

Water and permitting

The hybrid's peak-day water demand fit within the existing municipal supply without a new main. Keentel prepared the technical basis for the water-use agreement: modeled hourly demand, peak-day demand at the owner-specified extreme temperature, and a metering plan with separate meters for adiabatic supply, bleed and the small closed-loop makeup. The sewer authority accepted the reduced bleed volume without the pretreatment originally discussed.

Outcome

The owner selected hybrid coolers at W40. Lifecycle cost in Keentel's model was the lowest of the four options once water, sewer, generators and the avoided transformer were counted. The utility revised its study with the lower cooling-plant demand, and the campus water footprint dropped by roughly 85–90% compared with the original tower concept.

Lessons

The facility water class decided the outcome more than the cooler technology.

Water and electrical capacity were both binding constraints; solving one without the other would have failed.

A weather-driven load profile gave the utility confidence to accept a lower peak.

Case study 2 — A 100 MW desert campus: the cost of "zero water" at W32

Situation

An owner planning a 100 MW IT campus in central Arizona committed publicly to zero routine water use for cooling. The initial design used closed-loop dry coolers with large centrifugal trim chillers to deliver W32 facility water, which the first IT supplier required. Late in schematic design, the electrical engineer of record flagged that the cooling plant's design-day demand had grown far beyond the original allowance, and the utility questioned the summer peak in the interconnection application.

Keentel's scope

Keentel was retained for an independent review of the cooling plant's electrical impact and to evaluate alternatives that would preserve the owner's water commitment as far as possible.

Analysis

Using the site's design and extreme dry-bulb temperatures, Keentel's model reproduced the problem: at W32, dry coolers alone could not meet the setpoint on design day, and trim chillers carried essentially all the heat on the hottest afternoons.

Option (100 MW IT, hot-dry climate) Design-day cooling demand Trim chiller hours per year Annual heat-rejection energy Annual water
Dry at W32 (original) About 25 MW Several thousand About 66 GWh Near zero
Dry at W40 About 21 MW Fewer, but still most hot afternoons About 24 GWh Near zero
Dry at W45 About 11 MW Concentrated on extreme days Lower Near zero
Hybrid at W40 About 2.6 MW None on design day in the model Lowest of the four options Tens of millions of gallons

Keentel also tested the generator plant. Supporting 25 MW of cooling on generators required about 13 additional 2.5 MW sets, with corresponding fuel storage and an air permit for more engine-hours capacity than the owner had planned.

Options presented

Keentel presented three paths to the owner, each with water, energy, peak demand, generator and cost consequences:

1. Keep zero water, move to warmer water. Change the IT hardware selection to equipment rated for W45 coolant, cutting design-day demand to about 11 MW and trim chillers to the most extreme days. This required the IT team to confirm the newer hardware's supply limits and accept somewhat higher component temperatures.

2. Allow limited water on extreme days. Add adiabatic precooling to the dry coolers at W40, using water only on the hottest few hundred hours. This kept annual water low and cut peak demand to under 3 MW.

3. Keep the original design and buy capacity. Accept the higher utility service, generator count and summer energy cost.

Electrical design changes

Whichever path was chosen, Keentel recommended:

moving trim chillers to medium-voltage motors on dedicated 13.8 kV feeders with soft-start equipment to limit voltage dip on restart;

adding a 400,000-gallon buffer tank to cover the chillers' multi-minute restart after a utility outage;

including trim chillers in the large-load ride-through discussion with the utility, because a sudden loss and restart of 20 MW of chillers is visible on the transmission system.

Outcome

The owner chose option 1 for the first building and a variant of option 2 for later buildings, after revising its public commitment to "no routine water use, limited emergency adiabatic assist above a defined temperature." The utility service request was reduced by more than 10 MW, and the generator plant shrank accordingly.

Lessons

A zero-water commitment made before the IT hardware and water class were settled created an expensive electrical problem.

In hot-dry climates, dry plants need warm water to be practical; otherwise the water saving is paid for with grid capacity and energy.

Transparent, conditional water commitments are easier to keep than absolute ones.

Case study 3 — Expanding a 200 MW campus in Northern Virginia with evaporative towers

Situation

An operator in Northern Virginia planned a 200 MW IT expansion next to an existing campus that already used open cooling towers. The operator wanted to keep a common design for maintenance staff and spare parts. The county raised three concerns during review: water supply and discharge, nighttime noise at nearby homes, and winter plume visible from a highway.

Keentel's scope

Keentel was engaged for the electrical design of the expansion's cooling plant and substation, and to support the operator in preparing technical responses to the county's concerns.

Water

Scaling the reference model to 200 MW, Keentel estimated full-load evaporation of about 1,190 gpm. At the existing campus's 4 cycles of concentration, makeup would be about 1,590 gpm (about 2.3 million gallons per day at full load). Working with the water treatment specialist, the design added softening pretreatment to allow 6 cycles, reducing makeup to about 1,430 gpm (about 2.1 million gallons per day) and cutting blowdown by about 40%. The water utility accepted the demand with a requirement for 48 hours of on-site storage, about 4.1 million gallons at the higher cycles, which Keentel incorporated into the site's electrical and controls design (storage pumps on generator-backed power, level instrumentation on the SCADA system).

Noise and plume

The acoustical consultant's model showed that towers, with far fewer fans than an equivalent dry yard, could meet the county's nighttime limit with low-noise fans and a barrier wall on one side. A dry-cooler alternative, studied for comparison, needed roughly three times the fan count and could not meet the limit at the nearest residence without a larger setback the site did not have. Plume abatement coils were specified on the towers nearest the highway.

Electrical design

The expansion's cooling plant, at about 5–7 MW design-day demand, was served from two 34.5/13.8 kV transformers at the new substation, each sized to carry the full plant for concurrent maintainability.

All tower fans and pumps used active-front-end VFDs after a harmonic study.

An arc flash study led to maintenance switches and zone-selective interlocking on the 480 V switchboards, bringing incident energy at fan MCCs to levels that allowed routine maintenance with standard PPE.

Tower water storage pumps, chemical feed and controls were placed on generator-backed distribution with a defined restart sequence.

Outcome

The county approved the expansion with conditions on water reporting and nighttime noise monitoring. The operator kept a consistent tower design across the campus, and its reported WUE for the expansion improved compared with the original buildings because of the higher cycles of concentration.

Lessons

In a humid climate with adequate water and strict noise limits, towers can be the best answer even for operators under water scrutiny.

Cycles of concentration are a real lever, but evaporation itself cannot be reduced except by rejecting heat another way.

Water storage, chemical feed and controls are part of the critical cooling system and belong on reliable power.


Part D — 30-Question Technical FAQ

1. What is a heat-rejection plant in an AI data center?

It is the equipment that moves heat from the facility water loop to the outdoor air: cooling towers, hybrid coolers or dry coolers, together with their pumps, fans, controls and any trim chillers. In a liquid-cooled AI hall, heat flows from the chips to cold plates, into the technology cooling system, through the CDUs to the facility water, and finally to the heat-rejection plant. Every watt of IT load ends up there.

2. Which is better for AI data centers: evaporative, hybrid or dry cooling?

None is best everywhere. Towers use the least energy and have the lowest design-day electrical demand but consume the most water. Dry coolers use almost no water but need the most fan energy and, if the facility water is too cold for the climate, large trim chillers. Hybrids sit in between and are often the best lifecycle choice in hot or water-constrained regions. Climate, water availability, the facility water temperature the IT equipment accepts, noise limits and utility capacity decide the answer for each site.

3. Why do cooling towers work better than dry coolers in hot weather?

A tower cools water by evaporation, so it works against the wet-bulb temperature. A dry cooler works against the dry-bulb temperature. On a hot, dry afternoon the dry-bulb might be 108 °F while the wet-bulb is 75 °F; a tower can still deliver water in the low 80s °F, but a dry cooler cannot deliver water below about 120 °F with a typical approach.

4. How much water does a cooling tower use for a 100 MW data center?

In Keentel's reference model, rejecting 103 MW of heat evaporates about 600 gpm at full load. With blowdown at 4 cycles of concentration, makeup is about 800 gpm, or roughly 1.15 million gallons a day at full output. Over a year at an 85% load factor that is about 356 million gallons, roughly 1,090 acre-feet. Actual use depends on load, climate, range and water chemistry.

5. What are cycles of concentration and why do they matter?

Cycles of concentration compare the dissolved solids in the tower water to those in the makeup water. Higher cycles mean less blowdown and therefore less makeup. In the reference model, going from 3 to 8 cycles cuts makeup from about 895 gpm to about 682 gpm. Cycles are limited by scaling and corrosion, which depend on makeup water quality; pretreatment such as softening can allow higher cycles.

6. What is WUE and what is a good value?

Water usage effectiveness is annual site water use in liters divided by IT energy in kWh, as defined by The Green Grid and ISO/IEC 30134-9. Tower-cooled facilities commonly report values around 1–2 L/kWh; Keentel's reference tower plant gives about 1.8 L/kWh at 4 cycles. Hybrid and dry plants can be well below 0.5 L/kWh. A "good" value depends on the local water situation; a low WUE in a water-rich region may matter less than a moderate one in a drought-stressed basin.

7. Does a dry cooling plant really use zero water?

It uses essentially no routine evaporative water on site. The closed loop needs occasional makeup for leaks and maintenance, and the plant may have small water uses for cleaning. If the plant relies on trim chillers, their electricity has a water footprint at the power plants that supply it, depending on the regional generation mix.

8. What is a hybrid cooler?

A dry coil with an adiabatic or evaporative assist. It runs dry whenever the air is cool enough and uses water only on hot hours, either by precooling the entering air through wetted pads or sprays, or by wetting the coil. In Keentel's model, hybrids used 80–94% less water than towers across three climates at W32 facility water, and less still at warmer water classes.

9. What facility water temperature should an AI data center use?

As warm as the IT equipment and CDUs allow. ASHRAE defines classes from W17 to W45 and W+. Warmer water reduces or eliminates trim chillers and adiabatic hours. The limit comes from the server maker's maximum coolant temperature at the cold plate, the CDU approach and the owner's margin. Many current direct-to-chip designs operate in the W32 to W40 range, with warmer designs emerging.

10. How much does facility water temperature affect electrical demand?

A great deal. In Keentel's model for a hot-humid climate, a dry plant's design-day demand fell from about 25 MW at W32 to about 8 MW at W40 and about 3 MW at W45, for 100 MW of IT. A hybrid fell from about 11 MW at W32 to about 2.6 MW at W40.

11. Why does the cooling plant matter to the utility?

Because the utility must deliver the facility's peak demand, and the cooling plant's peak can vary by more than 20 MW per 100 MW of IT between options. Dry plants peak on the hottest afternoons, which often coincide with the utility's system peak. The cooling choice therefore affects service size, interconnection studies, upgrade costs and sometimes demand charges.

12. What are trim chillers and when are they needed?

Trim chillers are mechanical chillers that cool facility water the rest of the way when the dry or hybrid plant cannot reach the setpoint. They are needed when the design dry-bulb plus the cooler approach is higher than the required supply temperature. They are the largest contributor to a dry plant's peak electrical demand and to its annual energy in hot climates.

13. How is cooling tower evaporation estimated?

Two ways that agree closely: from the heat load, dividing the latent share of the heat by about 1,000 Btu per pound of water evaporated; or from the rule of thumb of about 1% of circulating flow for every 10 °F of range. For the reference plant, both give about 600 gpm.

14. What is the difference between water withdrawal and water consumption?

Withdrawal is water taken from a source; consumption is water that does not return to the local watershed. Evaporation is consumption. Blowdown is withdrawn but returned to the sewer. In the reference tower plant at 4 cycles, about 75% of makeup is consumed and about 25% is returned as blowdown. Clear reporting should state which number is being quoted.

15. What water treatment does a cooling tower need?

Conductivity-controlled blowdown, scale and corrosion inhibitors, pH control, an oxidizing and non-oxidizing biocide program, side-stream filtration and, where makeup is hard or high in silica, pretreatment such as softening or reverse osmosis. The program must be documented within a water management program that meets ASHRAE Standard 188 and any state or local cooling tower rules.

16. Do hybrid coolers need Legionella control?

Yes. Any wetted surface or spray that can create aerosols must be included in the facility's water management program. Hybrid wet systems need treatment, periodic flushing and drain-down when idle, and documented monitoring.

17. Why use a plate heat exchanger between the tower and the CDUs?

To keep open tower water, which picks up dust and biological material, out of the clean facility loop that feeds the CDUs. The exchanger adds a few degrees of approach but protects CDUs and IT equipment from fouling and contamination. It also lets each loop use the right water chemistry.

18. How much more fan energy do dry coolers use?

For the same heat, dry coolers move much more air than towers because they reject heat sensibly. In Keentel's reference assumptions, full-speed fan demand was about 8 kW per MW of heat for towers, 14 kW/MW for hybrids and 20 kW/MW for dry coolers. With VFDs, fans run below full speed most hours, and fan power falls with roughly the cube of speed.

19. Do open tower loops need more pump power?

Usually yes. Water must be lifted to the tower's distribution basin and pass through a plate heat exchanger, adding head. In the reference example, the open loop needed about 1,445 kW of pumping against about 1,135 kW for a closed dry-cooler loop at the same flow, partly offsetting the tower's fan advantage.

20. What PUE can a liquid-cooled AI campus achieve?

With warm-water liquid cooling and an efficient heat-rejection plant, facility PUE in the range of about 1.08 to 1.15 is achievable, depending on climate, electrical losses and how much air-cooled equipment remains. Keentel's reference model gave 1.078 for towers, 1.085 for hybrids and 1.112 for dry coolers at W32 in a hot-humid climate.

21. Does ASHRAE 90.4 apply to AI data centers?

ASHRAE 90.4-2022 is the energy standard for data centers and is adopted by many jurisdictions through their energy codes. It uses a mechanical load component and an electrical loss component rather than a single PUE target. The heat-rejection plant directly affects the mechanical load component. Designers should confirm the adopted edition with the authority having jurisdiction.

22. Should cooling pumps be on UPS?

For direct-to-chip liquid cooling, loss of coolant flow can overheat accelerators in seconds. CDU (TCS) pumps and controls are usually on UPS with the IT load. Facility pumps are often on a mechanical UPS or rely on loop thermal mass through generator start. Fans and chillers are typically generator-backed. The right split comes from a ride-through study.

23. How long can the facility loop ride through a loss of heat rejection?

It depends on loop volume and heat load. For 100 MW of IT with no heat rejection, a 150,000-gallon loop warms about 4.7 °F per minute, reaching 9 °F in about two minutes; a 300,000-gallon loop takes about four minutes. Buffer tanks extend ride-through to cover chiller restarts.

24. How do cooling plants affect generator sizing?

Generators must carry the cooling plant on the design day, including motor starting and restart. In Keentel's example, a dry plant at W32 in a hot-dry climate needed about thirteen 2.5 MW generator sets for cooling alone, against about two for a tower plant. That difference affects capital cost, fuel storage and air permits.

25. Do VFDs on fans and pumps cause harmonic problems?

They can. Hundreds of six-pulse drives can raise current distortion beyond IEEE 519 limits at the point of common coupling and heat transformers. In Keentel's example, six-pulse drives making up 2 MW of a 5 MW switchboard gave an estimated TDD near 15%, against about 2% with active-front-end drives. A harmonic study should guide the drive specification.

26. How much land does a 100 MW heat-rejection yard need?

Typical yard areas quoted for 100 MW are about 2.0–3.0 acres for towers, 1.5–2.5 acres for hybrids and 1.2–2.2 acres for dry coolers. These exclude setbacks, noise barriers, water storage, treatment buildings, electrical rooms and generator yards. On many sites, noise and recirculation clearances matter more than the equipment footprint.

27. Why are dry cooler yards often limited by noise?

Because they carry many fans. Sound power adds logarithmically, so 72 fans at 94 dBA each total about 112.6 dBA. A simple screening estimate gives about 62 dBA at 300 ft and 52 dBA at 1,000 ft, compared with common nighttime limits of 45–55 dBA at residential property lines. Low-noise fans, barriers and setbacks are often required.

28. What NERC issues relate to data center cooling plants?

NERC's work on large loads focuses on how big loads behave during grid disturbances, including sudden transfer to backup power. Cooling-plant drives and controls must ride through the same disturbances as the IT systems, and restart sequences should avoid sudden demand swings. Utilities increasingly request ride-through and restart data from large-load customers.

29. How should cooling plants be tested before the IT load arrives?

With thermal acceptance tests (CTI ATC-105 for towers and ATC-105S for closed-circuit coolers, or equivalent manufacturer-rated tests for dry and hybrid coolers) and integrated systems testing: load-bank heat tests at stepped loads, utility failure and generator transfer, staged restart, component failures, wet–dry transitions and water-supply loss.

30. How does Keentel Engineering help with AI data center cooling plants?

Keentel performs cooling architecture selection studies, hourly water and energy modeling, design-day electrical demand and utility service studies, generator sizing, the electrical design of the cooling plant (MV feeders, unit substations, MCCs, VFDs, UPS), short-circuit, coordination, arc flash and harmonic studies, ride-through and restart studies, large-load data for utilities, permitting support and integrated systems test witnessing, as owner's engineer or engineer of record, from 4 kV to 765 kV.


How Keentel Engineering Helps

Keentel Engineering supports data center developers, owners, hyperscale and colocation operators, utilities and lenders with the electrical, power systems and MEP engineering behind AI cooling plants, from 4 kV distribution to 765 kV transmission.

Service What Keentel delivers Outcome for the owner
Cooling architecture selection study Hourly water, energy, peak-demand, noise-screening, footprint and lifecycle cost comparison of towers, hybrids and dry coolers A defensible choice the board, utility and permitting authority can review
Facility water class optimization W27–W45 options evaluated against the IT roadmap, climate and tariff Fewer trim chillers, lower peak demand, lower water use
Load calculations and utility service Design-day and annual load profiles with the cooling plant separated; utility service sizing A right-sized service request and faster utility review
Large-load interconnection support Technical data for utility and transmission studies, ride-through and restart behavior, joint load and generation studies Fewer surprises in interconnection studies
Cooling-plant electrical design MV feeders, unit substations, 480 V switchboards, MCCs, VFD specifications, UPS for CDU and facility pumps A plant that keeps coolant flowing through power events
Generator and standby design Generator sizing with motor starting and restart sequences, paralleling, fuel and permit support Fewer unnecessary generators; reliable restart
Power system studies Short-circuit, protective-device coordination, arc flash (IEEE 1584, NFPA 70E), harmonics (IEEE 519), motor starting Safe, compliant, reliable distribution
Resilience and ride-through studies Coolant temperature through outage, transfer and restart; buffer-tank sizing; UPS split Evidence that the design meets the Tier objective
Water metering and reporting support Metering design, SCADA/BMS integration, WUE calculation basis Credible water reporting for permits and stakeholders
Permitting support Technical inputs for water, discharge, noise and air permits Smoother approvals
Owner's engineer Design reviews, specification review, constructability and change management Consistent decisions across mechanical, electrical and IT teams
Commissioning and IST Electrical test scripts, witnessing of transfer, restart and failure tests, power-quality measurement A plant proven before the IT load arrives
NERC and grid compliance support Large-load considerations, coordination with the utility's reliability requirements A facility that behaves well on the grid

Why Clients Choose Keentel


  • Power engineering depth. Our team works on interconnection studies, protection, substations and NERC compliance every day, so the plant design and the grid requirements stay aligned.
  • Independent advice. We do not sell equipment or software. Our recommendations serve the project.
  • Speed with rigor. We use modern design automation for fast iteration and back every result with calculations and studies.
  • Full voltage range. From 4 kV distribution-connected plants to 765 kV transmission interconnections.
  • Calculations you can check. Every recommendation includes its basis, as in the worked examples in this guide.
  • Credentials. Florida registered engineering firm (Firm Registration No. 36853), NSPE, D-U-N-S registered, IEEE Senior Member leadership and BBB Accredited Business with an A+ rating, with offices in Tampa, Austin, Sacramento and Baltimore.


Talk to Keentel Engineering


Planning a ground-mount solar or solar-plus-storage project, or reviewing a design before you fix the EPC price? Keentel can tell you what the grid will accept, what the plant will produce, and what it will take to build it right.


  • Phone: (813) 389-7871
  • Email: contact@keentelengineering.com
  • Book a 15-minute call: calendly.com/keentel-engineering/15min
  • Web: keentelengineering.com


References


All facts drawn from these sources are paraphrased. Standards status was checked against publisher listings in November 2026; confirm the current edition adopted by your authority having jurisdiction before relying on any requirement.


Codes and standards


  • NFPA 70, National Electrical Code, Articles 690 (Solar Photovoltaic Systems), 691 (Large-Scale Photovoltaic Electric Power Production Facility) and 705 (Interconnected Electric Power Production Sources). https://www.nfpa.org (codes and standards)
  • NFPA 70E, Standard for Electrical Safety in the Workplace. https://www.nfpa.org (codes and standards)
  • NFPA 855, Standard for the Installation of Stationary Energy Storage Systems. https://www.nfpa.org (codes and standards)
  • IEEE 80, Guide for Safety in AC Substation Grounding. https://standards.ieee.org (search by standard number)
  • IEEE 2778-2020, Guide for Solar Power Plant Grounding for Personnel Protection. https://standards.ieee.org/ieee/2778/7140
  • IEEE 1584-2018, Guide for Performing Arc-Flash Hazard Calculations. https://standards.ieee.org (search by standard number)
  • IEEE 2800-2022, Standard for Interconnection and Interoperability of Inverter-Based Resources Interconnecting with Associated Transmission Electric Power Systems. https://standards.ieee.org (search by standard number)
  • IEEE 1547-2018, Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces. https://standards.ieee.org (search by standard number)
  • IEEE 519-2022, Standard for Harmonic Control in Electric Power Systems. https://standards.ieee.org (search by standard number)
  • UL 2703, Mounting Systems, Mounting Devices, Clamping/Retention Devices, and Ground Lugs for Use with Flat-Plate Photovoltaic Modules and Panels; UL 3703, Solar Trackers; UL 1741, Inverters, Converters, Controllers and Interconnection System Equipment; UL 9540 and UL 9540A. https://www.ul.com/services/pv-mounting-systems-certification ; https://standards.globalspec.com/std/14552111/ul-3703
  • ASCE 7-22, Minimum Design Loads and Associated Criteria for Buildings and Other Structures; ASCE 49, Wind Tunnel Testing for Buildings and Other Structures. https://www.asce.org
  • National Electrical Safety Code (NESC), IEEE C2. https://standards.ieee.org/products-programs/nesc/


Regulatory


  • FERC Order No. 827, Reactive Power Requirements for Non-Synchronous Generation, 2016. https://www.ferc.gov
  • FERC Order No. 2023, Improvements to Generator Interconnection Procedures and Agreements, 2023. https://www.ferc.gov/explainer-interconnection-final-rule
  • NERC Reliability Standards PRC-024, PRC-028, PRC-029, PRC-030, MOD-026, MOD-032 and MOD-033, and NERC registration criteria for inverter-based resources. https://www.nerc.com


Data and research


  • Lawrence Berkeley National Laboratory, U.S. Utility-Scale Solar, 2025 Data Update (Bolinger et al.). https://emp.lbl.gov/publications/us-utility-scale-solar-2025-data ; slides: https://emp.lbl.gov/sites/default/files/2025-10/Utility%20Scale%20Solar%202025%20Edition%20Slides.pdf
  • Lawrence Berkeley National Laboratory, Land Requirements for Utility-Scale PV: An Empirical Update on Power and Energy Density, 2022. https://emp.lbl.gov/sites/default/files/emp-files/land_requirements_for_utility-scale_pv.pdf
  • NREL, Land-Use Requirements for Solar Power Plants in the United States, 2013. https://www.osti.gov/biblio/1086349
  • NREL, Solar Photovoltaic System Cost Benchmarks (Q1 2024 benchmarks). https://www.energy.gov/eere/solar/solar-photovoltaic-system-cost-benchmarks ; https://www.osti.gov/biblio/3007269
  • NREL, Annual Technology Baseline: Utility-Scale PV. https://atb.nrel.gov/electricity/2024/utility-scale_pv
  • SEIA and Wood Mackenzie, Solar Market Insight Report 2025 Year in Review, 2026. https://seia.org/research-resources/solar-market-insight-report-2025-year-in-review/ ; SEIA news release: https://seia.org/news/report-u-s-adds-43-gw-of-new-solar-capacity-in-2025/


Related Keentel guides


  • Designing Ground-Mount Solar PV for Wind Resilience
  • Build Quality Sets Solar O&M Costs (EPC workmanship)
  • Cluster Interconnection Studies
  • Power Plant Controller Compliance
  • PRC-029-1 and IEEE 2800: Settings to Closed Loop
  • System Strength Metrics
  • Temporary vs Transient Overvoltages
  • BESS DC Sizing and C-Rate; BESS ROI and Value Stacking
  • NERC Compliance Services Guide
  • NEC 2026 Field Guide



Disclaimer


This article is provided by Keentel Engineering for general technical education. It is not engineering, legal or financial advice for any specific project. Codes, standards, NERC requirements, interconnection rules and their effective dates change; confirm the current edition adopted by your authority having jurisdiction, transmission provider and Regional Entity before relying on any value here. Worked examples use illustrative inputs, including a synthetic production profile, and are not forecasts for any site. Case studies are composites with identifying details removed or changed. Keentel Engineering accepts no liability for decisions made on the basis of this article without a project-specific review.



A smiling man with glasses and a beard wearing a blue blazer stands in front of server racks in a data center.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.

His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.

Four workers in safety vests and helmets stand with arms crossed near wind turbines.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.

Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.

His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.

Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.

Leave a Comment

Related Posts

Ground-Mount Solar Engineering: Complete Design Guide
By SANDIP R PATEL • November 26, 2026
Explore ground-mount solar engineering, from site selection and string sizing to collector design, grounding, battery storage and grid interconnection.
Gas turbine backlog and equipment lead times for power generation projects in 2026.
By SANDIP R PATEL • November 26, 2026
Explore the 2026 gas turbine backlog, equipment lead times, GSU supply constraints, interconnection challenges, NERC testing and project delay costs.
PLECS and Ansys simulation workflow for solid-state transformer engineering.
By SANDIP R PATEL • November 26, 2026
Explore how PLECS and Ansys support solid-state transformer simulation, thermal modeling, power loss analysis, control design, and engineering validation.
Solid-state transformer design through EVT with efficiency vs load comparison chart
By SANDIP R PATEL • November 25, 2026
Explore solid-state transformer design, SiC architecture, protection, insulation and EVT testing for data centers and EV charging with Keentel Engineering.
SCADA architecture for power systems showing telemetry latency, RTU, IED and ICCP communication
By SANDIP R PATEL • November 25, 2026
Explore SCADA architecture for power and process systems, including DNP3, IEC 61850, telemetry latency, alarms, time sync, NERC CIP and OT security.
Transient stability studies graph comparing rotor angles and fault clearing times in power systems
By SANDIP R PATEL • November 24, 2026
Explore transient stability studies, IEEE and NERC standards, generator models, critical clearing time, breaker protection and power system stability analysis.
Joint load and generation interconnection studies showing N-1 transmission line loading scenarios Co
By SANDIP R PATEL • November 24, 2026
Learn how joint load and generation interconnection studies work, including PJM Fast Energization, MISO LARS, co-location risks and grid modeling.
Grid flexibility load duration curve showing peak demand reduction and capacity needs
By SANDIP R PATEL • November 22, 2026
Explore dependable grid flexibility with battery storage, virtual power plants, managed EV charging and flexible loads to cut peak demand and grid costs.
Temporary vs transient overvoltages chart showing TOV, lightning, switching and insulation limits
By SANDIP R PATEL • November 22, 2026
Compare temporary vs transient overvoltages, including TOV, lightning and switching surges, insulation coordination, surge arresters and NERC PRC-026.