Part A — AI Data Center Heat Rejection at a Glance
Every watt that enters an AI data center leaves it as heat. A 100 MW campus running current-generation GPU racks has to move roughly 100 MW of heat out of the building, through a water loop, and into the outdoor air, every hour of the year, including the hottest afternoon of the hottest summer on record. The equipment that does the last step — cooling towers, hybrid coolers or dry coolers, with their pumps, fans and sometimes trim chillers — is called the heat-rejection plant.
For most of the history of enterprise data centers, the heat-rejection plant was a mechanical engineering choice made late in design. For AI campuses at 100 MW and beyond, it has become one of the first decisions that shapes the whole project. It sets how much water the site must secure and discharge, how much land the yard occupies, how loud the property line will be, how much electricity the plant draws on a 105 °F afternoon, and therefore how many megawatts the utility must deliver, how many generators the site must install, and how the facility behaves on the grid.
This guide is Keentel Engineering's in-depth comparison of the three architectures now used for liquid-cooled AI facilities: evaporative cooling towers, hybrid dry coolers with adiabatic or evaporative assist, and closed-loop dry coolers. It covers the thermodynamics, the water balance, the energy balance, and, in more depth than most comparisons, the electrical and grid consequences of each choice. Every major point is backed by a worked example calculated on one reference facility, using US units (°F, gpm, tons, feet and acres) with SI values in parentheses where they help.
Keentel's position. Keentel Engineering is an independent electrical, power systems and MEP engineering firm. We do not sell cooling equipment. We design the electrical systems that feed heat-rejection plants, size utility services and on-site generation for them, study their effect on the grid, and act as owner's engineer on data center projects from 4 kV to 765 kV. That is why this guide treats cooling-plant selection as an electrical, water and permitting decision as much as a mechanical one.
Who this guide is for
Data center developers and owners choosing a site and a cooling strategy before land, water and power are committed.
MEP design teams and owner's engineers who must coordinate mechanical selections with electrical capacity, generator sizing and utility service.
Utilities and transmission planners studying large-load requests whose summer peak depends on the cooling plant.
Municipal water and permitting staff evaluating water supply, discharge and noise for new campuses.
Lenders and investors who need to understand how water, energy and grid risk differ across cooling options.
Operations teams taking over a plant that must stay concurrently maintainable and fault tolerant.
The reference facility used in this guide
All worked examples use one illustrative US campus. The numbers are Keentel's modeling assumptions, not data from any specific site.
| Item | Value (illustrative) |
|---|---|
| IT load | 100 MW, predominantly direct-to-chip liquid cooling through CDUs |
| Heat rejected by the facility water plant | 103 MW (IT plus pump, CDU and residual air-side heat) |
| Facility water temperatures | 86 °F (30 °C) supply, 104 °F (40 °C) return, an 18 °F (10 K) range — ASHRAE class W32 |
| Average load factor | 85% of design IT load over the year |
| Climates studied | Three synthetic hourly climates: hot-humid ("Dallas-like"), hot-dry ("Phoenix-like") and mild-humid ("Ashburn-like") |
| Utility service | 230 kV transmission service, 34.5 kV and 13.8 kV medium-voltage distribution, 480 V mechanical switchboards, 60 Hz |
| Electricity price | $70/MWh (illustrative) |
The synthetic climates are smooth models built for comparison; they are not ASHRAE design data. Any real project must use ASHRAE climatic design conditions and multi-year hourly weather files for the actual site.
Key facts at a glance
| Item | Value or practice | Basis |
|---|---|---|
| US data center electricity use | About 4.4% of US electricity in 2023, rising to an estimated 6.7–12% by 2028 | LBNL, 2024 United States Data Center Energy Usage Report (December 2024) |
| US data center direct water use | On the order of 17 billion gallons in 2023, with substantial growth projected (confirm current figures against the report) | LBNL 2024 report and coverage of it |
| Water metric | Water usage effectiveness (WUE) = annual site water use (liters) ÷ IT energy (kWh) | The Green Grid; ISO/IEC 30134-9:2022 |
| Energy metric | Power usage effectiveness (PUE) = total facility energy ÷ IT energy | The Green Grid; ISO/IEC 30134-2 |
| Liquid-cooling water classes | W17, W27, W32, W40, W45 and W+ (maximum facility water supply temperature in °C) | ASHRAE TC 9.9, Thermal Guidelines for Data Processing Environments, 5th edition |
| Energy standard for data centers | ASHRAE Standard 90.4-2022, including a mechanical load component (MLC) compliance path | ASHRAE |
| Legionella risk management | ASHRAE Standard 188 (water management programs for building water systems, including cooling towers) | ASHRAE |
| Cooling tower thermal testing | CTI ATC-105 (open towers) and ATC-105S (closed-circuit coolers); CTI STD-201 thermal certification | Cooling Technology Institute |
| Cooling tower water-efficiency guidance | Raise cycles of concentration, meter makeup and blowdown, control conductivity | EPA WaterSense at Work §6.3; DOE FEMP Best Management Practice #10 |
| Typical evaporation in a cooling tower | About 1% of circulating flow for each 10 °F of range | EPA WaterSense; industry rule of thumb |
| Grid behavior of large loads | NERC has published an incident review of a large voltage-sensitive load loss and guidance on large-load integration | NERC (2025) |
The core ideas in one table
| Idea | What it means for an AI campus |
|---|---|
| Heat leaves either as evaporated water or as warmed air | Towers reject most heat as latent heat (water vapor); dry coolers reject it as sensible heat (warmer air). Hybrids switch between the two. |
| Wet-bulb sets the tower's limit; dry-bulb sets the dry cooler's | On a 105 °F dry afternoon the wet-bulb may be 75 °F. A tower can still deliver cool water; a dry cooler cannot get below the air temperature. |
| Water and energy trade against each other | Each gallon not evaporated must be paid for with more fan energy, more coil area, warmer water, or chiller energy. |
| The facility water temperature is the master variable | Moving from W32 (86 °F supply) to W40 (104 °F) can eliminate most trim-chiller hours in many US climates. |
| The worst hour sizes the electrical system | Utility service, transformers and generators must carry the cooling plant on the design-day peak, which is exactly when dry plants work hardest. |
| Consumption is not withdrawal | Evaporated water leaves the watershed; blowdown returns to the sewer. Permits and public debate care about both. |
| Liquid cooling makes the loop critical | Direct-to-chip racks overheat in seconds without flow, so pumps, controls and parts of the plant need uninterruptible power and redundancy. |
| No architecture is best everywhere | Climate, water availability, discharge rules, noise limits, grid capacity and tariffs decide the right answer for each site. |
Fact check: what common comparisons get right and what they leave out
Comparisons of evaporative, hybrid and closed-loop plants circulate widely, often as a three-row table with site areas in hectares and temperatures in Celsius. The broad conclusions are sound. Several points need correction or expansion for US engineering practice.
| Common statement | Keentel's engineering check |
|---|---|
| "Evaporative plants have high efficiency." | True for heat-rejection energy: fans run less and water can be colder because towers follow wet-bulb. But towers need larger condenser-water pumps (open-loop static lift) and the water itself carries an energy and cost footprint upstream. "Efficient" should be stated as kW per ton of heat rejected and gallons per MWh, side by side. |
| "Dry coolers use near-zero water." | Near-zero routine evaporative water, yes. But in hot climates a dry plant designed for W32 water needs trim chillers on many hours, and those chillers' electricity has its own water footprint at the power plant. The water saving is real on site; the system-wide picture depends on the grid mix. |
| "Hybrid uses water only during high ambient." | Correct in principle, but the switch-over point is a design choice, not a constant. A hybrid designed for warmer facility water uses far less water than one held to W32. Hybrid pads and sprays also need water treatment and periodic flushing. |
| "Site area ~0.5–1.2 ha for 100 MW." | These figures (about 1.2–3.0 acres) are plausible for the heat-rejection yard alone but exclude setbacks, noise barriers, water storage and treatment, electrical rooms, generator yards and maintenance access. Dry coolers usually need more coil face area than towers for the same heat, not less; compact dry layouts depend on stacking or V-bank designs and on warmer water. |
| "Warm water ~32–40 °C, cooled ~24–30 °C." | Reasonable for many direct-to-chip designs, but these are application-dependent. ASHRAE W-classes and the IT vendor's coolant supply limits govern. A 6–10 K range is typical; a wider range reduces flow and pump energy. |
| "Plume: yes / limited / no." | Plume is mostly a visual and icing issue, but it can matter for permitting near airports and roads. Towers can be specified with plume abatement. |
| Missing: Legionella | Any wet system — towers and the wetted parts of hybrids — needs a water management program under ASHRAE Standard 188 and local health codes. |
| Missing: electrical and grid impact | The cooling plant's summer peak demand differs by a factor of five or more between options. That changes utility service size, generator count and, at campus scale, the transmission study. |
| Missing: noise | Dry coolers move far more air and carry many more fans. Property-line noise often limits dry and hybrid yards more than footprint does. |
Eight findings for decision makers
1. The facility water temperature matters more than the brand of cooler. In Keentel's model, raising the supply from 86 °F (W32) to 104 °F (W40) cut a hybrid plant's design-day demand in the hot-humid climate from about 11.3 MW to 2.6 MW, because it eliminated the trim chillers.
2. Evaporative towers remain the lowest-energy option almost everywhere, at the cost of roughly 1.0–1.3 million gallons of makeup water per day for a 100 MW IT load at full output.
3. Hybrid plants recover 80–94% of the water a tower would use in the three climates we modeled, while keeping peak electrical demand close to a tower plant if they are designed for warm water.
4. Dry plants held to W32 water in hot climates are the worst case for the grid, with design-day cooling demand above 20 MW in our model, almost all of it trim chillers that run exactly when the utility's system peaks.
5. The electrical system must be sized for the worst hour, not the annual average. Annual PUE differences of a few hundredths can hide peak-demand differences of 20 MW.
6. Water is now a permitting and public-acceptance issue, with states and Congress examining data center water reporting. Site selection should treat water rights, discharge permits and drought plans as early as power.
7. Liquid cooling makes the cooling loop part of the critical power path. Pumps and controls need uninterruptible power and redundancy aligned with the facility's Tier objective.
8. The right answer is site-specific, and the comparison must be done in one consistent model that includes water, energy, peak demand, noise, footprint and lifecycle cost.
Key terms
| Term | Meaning |
|---|---|
| Heat-rejection plant | Equipment that moves heat from the facility water loop to the outdoor air: towers, hybrid coolers, dry coolers, trim chillers, pumps and controls |
| Facility water system (FWS) | The primary loop between the heat-rejection plant and the CDUs |
| Technology cooling system (TCS) | The secondary loop between the CDUs and the IT equipment |
| CDU | Coolant distribution unit, which transfers heat from the TCS to the FWS through a heat exchanger |
| Range | Temperature drop of the water across the heat-rejection equipment (return minus supply) |
| Approach | Leaving water temperature minus the ambient temperature the equipment works against (wet-bulb for towers, dry-bulb for dry coolers) |
| Wet-bulb temperature | The lowest temperature air can reach by evaporating water into it; the limit for evaporative cooling |
| Cycles of concentration (COC) | Ratio of dissolved solids in tower water to those in makeup water; higher cycles mean less blowdown |
| Blowdown | Water deliberately drained from a tower to control dissolved solids |
| Makeup | Water added to replace evaporation, blowdown and drift |
| Adiabatic precooling | Wetting pads or spraying mist into the air entering a dry coil so it approaches the wet-bulb temperature |
| Trim chiller | A mechanical chiller that cools the water the rest of the way when the dry or hybrid plant cannot reach the setpoint |
| WUE | Water usage effectiveness: site water (L) ÷ IT energy (kWh) |
| PUE | Power usage effectiveness: total facility energy ÷ IT energy |
| Design day | The hot (and humid) condition used to size equipment, typically from ASHRAE 0.4% or more severe design data, or an owner-specified extreme |
Part B — The Engineering Guide to Heat-Rejection Plant Selection
1. Why heat rejection is now an electrical, water and grid decision
An air-cooled enterprise data center of the 2010s typically ran at 5–10 kW per rack and used chilled water or direct-expansion units at 45–55 °F. The heat-rejection plant was a set of chillers with cooling towers or air-cooled condensers, chosen mainly on first cost and efficiency. Its electrical demand was a fixed slice of the facility load.
AI training and inference racks changed three things at once.
Density. Racks have moved from tens of kilowatts to well over 100 kW each, and roadmaps go higher. Air cannot carry that heat economically, so direct-to-chip liquid cooling has become the default for high-density AI halls. Keentel's companion guide on coolant distribution units explains the CDU and the two-loop arrangement in detail.
Temperature. Liquid cooling lets the facility water run much warmer than chilled water. Supply temperatures of 77–95 °F (25–35 °C), and in some designs above 104 °F (40 °C), are now common. Warm water can often be cooled by outdoor air alone, which opens the door to chiller-free plants.
Scale. A single campus can now ask a utility for hundreds of megawatts. At that scale the cooling plant's own demand — and how it varies with weather — is large enough to matter to transmission planning.
The result is that the heat-rejection plant now sets several of the project's hardest constraints:
| Constraint | How the cooling plant drives it |
|---|---|
| Water supply and discharge | Towers need about 1 million gallons a day per 100 MW of IT at full output; dry plants need almost none |
| Utility service size | Design-day cooling demand ranges from about 2–4 MW to more than 20 MW per 100 MW of IT across the options |
| Generator plant | Every megawatt of cooling demand on the design day must also be carried by standby generation |
| Land and layout | Yard area, spacing for air recirculation, noise setbacks and maintenance access |
| Permits and public acceptance | Water rights, discharge permits, noise ordinances, plume and visual impact |
| Reliability | For liquid-cooled racks, loss of flow becomes a thermal event in seconds |
| Operating cost | Energy, water, sewer, chemicals and maintenance differ by millions of dollars a year |
How Keentel Engineering helps here. Keentel starts every data center cooling engagement with a constraints map: available water and discharge capacity, utility service and interconnection timeline, generator strategy, noise and setback limits, and the owner's Tier and sustainability targets. The cooling architecture is then selected against those constraints rather than in isolation.
2. The heat-rejection chain, from chip to atmosphere
Heat in a liquid-cooled AI hall moves through five stages:
1. Chip to cold plate. Processors and accelerators conduct heat into cold plates.
2. Cold plate to TCS coolant. The technology cooling system coolant, often 25% propylene glycol or treated water, carries the heat to the CDU.
3. CDU heat exchanger. A plate heat exchanger transfers heat to the facility water system. Its approach (TCS supply minus FWS supply) is typically 4–9 °F (2–5 K).
4. Facility water to the plant. Pumps carry facility water to the heat-rejection yard.
5. Plant to atmosphere. Towers, hybrid coolers or dry coolers reject the heat. Trim chillers, where installed, close the gap on hot hours.
ASHRAE TC 9.9's thermal guidelines classify facility water by its maximum supply temperature.
| ASHRAE class | Maximum facility water supply | Typical heat rejection in US climates |
|---|---|---|
| W17 | 63 °F (17 °C) | Chillers, with economizers |
| W27 | 81 °F (27 °C) | Chillers with economizers; cooling towers in dry climates |
| W32 | 90 °F (32 °C) | Cooling towers; dry coolers in mild climates with trim |
| W40 | 104 °F (40 °C) | Dry coolers or hybrids in most climates, chiller-free most hours |
| W45 | 113 °F (45 °C) | Dry coolers almost everywhere; heat reuse becomes practical |
| W+ | Above 113 °F | Heat reuse, district heating |
The class the facility can accept is set by the IT equipment: the coolant temperature the server maker allows at the cold plate, minus the CDU approach, minus any margin the owner wants. Choosing the class is therefore a joint decision between the IT, mechanical and electrical teams. It is the single largest lever in this guide.
Worked example 1 — Converting the IT load to heat-rejection duty
The heat-rejection plant must reject the IT heat plus the heat added by pumps, CDUs and residual air-side equipment. For the reference facility, Keentel assumes 3 MW of such heat on top of 100 MW of IT:
The IT load alone would be about 28,400 tons. The difference matters: forgetting pump and auxiliary heat undersizes the plant by about 3%, which is the kind of margin a plant needs on the design day.
Worked example 2 — Facility water flow
Water flow for a given heat load and range follows the standard water-side equation, where 500 is the constant for water in gpm, Btu/h and °F:
| Range (ΔT) | Facility water flow | Notes |
|---|---|---|
| 15 °F (8.3 K) | 46,860 gpm | More flow, larger pipes and pumps |
| 18 °F (10 K) | 39,050 gpm (about 2,460 L/s) | Reference design |
| 20 °F (11.1 K) | 35,145 gpm | Less flow, but requires warmer return water |
A wider range cuts flow and pumping energy, and it helps dry coolers by raising the average water temperature in the coil. It is limited by the IT coolant temperature rise the CDUs can deliver.
How Keentel Engineering helps here. Keentel's MEP and electrical teams build a single heat and flow balance from chip to atmosphere, so the IT vendor's coolant limits, CDU approach, facility water class, pipe sizes and pump motors are all consistent. That balance becomes the basis of design for both the mechanical selections and the electrical load list.
3. Evaporative cooling towers: how they work
A cooling tower brings warm facility water into direct contact with outdoor air. A small fraction of the water evaporates, and the latent heat of evaporation cools the rest. Because evaporation is limited by how much moisture the air can absorb, a tower's leaving water temperature approaches the wet-bulb temperature, not the dry-bulb.
Two performance terms describe a tower:
Range — return water temperature minus supply water temperature (18 °F in our reference design).
Approach — supply water temperature minus the entering air wet-bulb temperature. Practical towers are selected for approaches of about 5–10 °F; smaller approaches need much larger towers.
For the reference facility at 86 °F supply and a 7 °F approach, the tower can deliver design water whenever the wet-bulb is at or below 79 °F. Many US locations rarely exceed that wet-bulb, which is why towers can serve W32 water with little or no trim chiller support.
Open towers and closed-circuit coolers
| Type | How it works | Data center use |
|---|---|---|
| Open (direct-contact) tower | Facility or condenser water flows over fill in direct contact with air | Common; normally isolated from the CDUs through a plate heat exchanger so tower water never reaches the IT loop |
| Closed-circuit cooler (fluid cooler) | Facility water flows inside a coil; a separate spray water circuit wets the outside of the coil | Keeps the facility loop clean and sealed; larger and more costly per ton |
| Tower plus plate heat exchanger | Open tower water on one side, clean closed facility loop on the other | The usual arrangement for liquid-cooled AI halls; adds a few degrees of approach |
Keeping the tower water physically separate from the facility loop is standard practice for liquid-cooled IT. Tower water picks up dust, organic material and biological growth; the facility loop and CDUs need clean, chemically stable water.
The water balance of a tower
Makeup water replaces three losses: evaporation (E), blowdown (B) and drift (D). Drift from modern towers with drift eliminators is very small and is neglected here.
Evaporation can be estimated from the heat load. With about 1,000 Btu absorbed per pound of water evaporated, and roughly 85% of the heat rejected as latent heat (the rest is sensible heating of the air):
The widely used rule of thumb — about 1% of the circulating flow for every 10 °F of range, or roughly 0.00085 × gpm × range in °F — gives the same answer for our reference plant.
Blowdown controls dissolved solids. If the makeup water carries a given concentration of minerals and the tower water is allowed to reach COC times that concentration:
Worked example 3 — Makeup water for a 100 MW IT load
With 103 MW of heat at full output, evaporation is about 597 gpm. Blowdown and makeup then depend on the cycles of concentration the water chemistry allows:
| Cycles of concentration | Blowdown | Makeup | Makeup per day at full load |
|---|---|---|---|
| 3 | 298 gpm | 895 gpm | 1.29 million gallons |
| 4 | 199 gpm | 796 gpm | 1.15 million gallons |
| 6 | 119 gpm | 716 gpm | 1.03 million gallons |
| 8 | 85 gpm | 682 gpm | 0.98 million gallons |
Over a year at an 85% average load factor, the reference plant at 4 cycles uses about 356 million gallons of makeup — roughly 1,090 acre-feet — and at 6 cycles about 320 million gallons (980 acre-feet).
The lesson is that most of a tower's water is evaporated, and evaporation is set by physics. Raising cycles from 3 to 8 saves about a quarter of the makeup, but no chemistry program can eliminate evaporation. The only ways to use much less water are to reject heat sensibly (dry or hybrid) or to reject less heat.
Worked example 4 — Water usage effectiveness
WUE is defined by The Green Grid and in ISO/IEC 30134-9 as annual site water use divided by IT energy:
For the reference tower plant at 4 cycles, annual makeup is about 1.35 billion liters against 745 million kWh of IT energy (100 MW × 8,760 h × 0.85), so WUE ≈ 1.81 L/kWh(about 478 gallons per MWh). At 6 cycles it is about 1.63 L/kWh. These values sit in the range commonly reported for tower-cooled facilities, which is why WUE alone often decides public perception of a project.
Keentel Study Spotlight — Water and energy balance study. For each candidate site, Keentel builds an hour-by-hour model of the facility water loop, the heat-rejection plant and the IT load profile using the site's real weather files. The study reports annual and peak water use, WUE, PUE, design-day electrical demand, trim-chiller hours and lifecycle cost for each architecture, on one consistent basis that the owner, the utility and the water provider can all review.
4. Water chemistry, Legionella and discharge
Every wet heat-rejection system — open towers, closed-circuit coolers and the wetted media of hybrid coolers — is a building water system with public-health obligations.
Water treatment program elements
| Element | Purpose |
|---|---|
| Conductivity-controlled blowdown | Holds dissolved solids at the target cycles of concentration |
| Scale inhibition and pH control | Prevents calcium carbonate and silica scale on fill and coils |
| Corrosion inhibition | Protects steel, copper and galvanized surfaces |
| Biocide program (oxidizing and non-oxidizing) | Controls bacteria, algae and biofilm |
| Filtration (side-stream) | Removes suspended solids and dust |
| Makeup pretreatment | Softening or reverse osmosis where makeup water is hard or high in silica, allowing higher cycles |
| Metering | Separate meters on makeup and blowdown for water accounting and sewer credits |
Legionella
ASHRAE Standard 188 requires a water management program for building water systems, including cooling towers, built around a hazard analysis, control locations, control limits, monitoring and corrective actions. Many states and cities add their own cooling tower registration and testing rules. For hybrid coolers, the spray or pad water is also a potential source of aerosols and must be included in the program, with drain-down and flushing when the wet mode is idle.
Discharge
Blowdown is wastewater. It typically goes to the municipal sewer under an industrial user permit, sometimes after treatment. Large campuses may face limits on total dissolved solids, temperature, and the chemicals in the treatment program, and some municipalities apply sewer charges that exceed the water charge. In water-scarce regions, zero-liquid-discharge treatment or reuse of blowdown may be required, adding electrical load and cost.
Worked example 5 — Annual water and sewer cost
For the reference tower plant at 4 cycles and an 85% load factor, Keentel's model gives about 355.6 million gallons of makeup (355,600 kgal) and 88.9 million gallons of blowdown (88,900 kgal) per year. With illustrative rates of $6.00/kgal for water, $8.00/kgal for sewer and $0.90/kgal for treatment chemicals:
| Item | Annual quantity | Illustrative cost |
|---|---|---|
| Makeup water | 355,600 kgal | $2.13 million |
| Sewer on blowdown | 88,900 kgal | $0.71 million |
| Treatment chemicals | Per kgal of makeup | $0.32 million |
| Total | About $3.2 million per year |
Water costs vary widely across the US, and some utilities offer evaporation credits on sewer charges if evaporation is metered. Even so, at campus scale water is a seven-figure annual line item, comparable to the electricity cost difference between architectures.
How Keentel Engineering helps here. Keentel coordinates the electrical side of water treatment and metering — chemical feed panels, reverse-osmosis skids, side-stream filters, conductivity and flow instrumentation on the SCADA or building management system — and supports owners in documenting water use for permits, sustainability reporting and emerging state disclosure requirements.
5. Hybrid coolers: dry most of the year, wet when it counts
A hybrid cooler is a dry finned-coil heat exchanger with a way to use water only when the air is too hot. There are two common arrangements:
Adiabatic precooling. Wetted pads or fine sprays sit in front of the coil. Water evaporates into the entering air, cooling it toward the wet-bulb before it reaches the dry coil. The coil itself stays dry.
Evaporative (wet) assist. Water is sprayed onto the coil surface, so the coil behaves like a closed-circuit cooler during hot hours.
In both cases the cooler runs dry whenever the outdoor dry-bulb is low enough to meet the setpoint, then switches to wet operation as the temperature rises. The control strategy — when to switch, how many units to wet, and how to stage fans — determines how much water and energy the plant actually uses.
Operating modes
| Mode | When it runs | Water | Fan energy |
|---|---|---|---|
| Dry, reduced fan speed | Cool hours with ample margin | None | Low (fan power falls with roughly the cube of speed) |
| Dry, full fan speed | Warm hours near the dry limit | None | High |
| Adiabatic or wet assist | Hot hours where dry-bulb plus approach exceeds the setpoint | Moderate | High |
| Wet assist plus trim chiller | Extreme hours beyond the adiabatic limit | Moderate | High, plus chiller energy |
A key engineering decision is the switch-over temperature. Switching early saves fan energy but uses water; switching late saves water but runs fans at full speed. Owners with strict water targets choose a late switch-over; owners with tight peak-demand limits choose an earlier one.
Worked example 6 — Hybrid plant operating hours and annual water
Keentel modeled a hybrid plant serving W32 water (86 °F supply) with a 12 °F dry approach and 80% adiabatic effectiveness. In adiabatic mode, water use per hour was taken as 45% of a tower's evaporation at the same load, plus 10% for pad bleed. These are illustrative modeling assumptions, not manufacturer data.
| Synthetic climate | Dry hours | Adiabatic hours | Hours needing trim beyond adiabatic | Annual water | Saving vs. tower at 4 cycles |
|---|---|---|---|---|---|
| Ashburn-like (mild-humid) | 7,296 | 999 | 465 | 22.1 million gal | 94% |
| Dallas-like (hot-humid) | 5,764 | 1,598 | 1,398 | 45.2 million gal | 87% |
| Phoenix-like (hot-dry) | 4,021 | 3,251 | 1,488 | 71.4 million gal | 80% |
Two results stand out. First, a hybrid plant saves most of a tower's water in every climate we modeled. Second, at W32 water the hybrid still needs mechanical trim on 465 to 1,488 hours a year. Those are the hottest hours, and they set the plant's peak electrical demand, as Section 11 shows.
How Keentel Engineering helps here. Keentel reviews hybrid control sequences together with the electrical design, so the switch-over and fan-staging logic respects the owner's water budget and the site's peak-demand limit, and so the controls, sensors and valves needed for wet operation are on the correct power sources.
6. Closed-loop dry coolers and trim chillers
A dry cooler is a finned-tube coil with fans. Facility water (or a water-glycol mixture) flows inside the tubes and is cooled by outdoor air passing over the fins. No water is evaporated in routine operation. Because heat leaves only as sensible heat, the coolest water a dry cooler can deliver is the outdoor dry-bulb temperature plus its approach, typically 8–15 °F at full load.
Strengths and limits
| Strength | Limit |
|---|---|
| No routine water use, no blowdown, no plume, no Legionella exposure from the coil | Leaving water can never be colder than the air; on a 105 °F afternoon the water is at least 113–120 °F |
| Sealed loop stays clean; simple water treatment | Much larger coil face area and many more fans than towers for the same heat |
| Well suited to warm-water liquid cooling (W40, W45) | Highest fan energy per ton, and highest property-line noise |
| Fewer operating staff and chemicals | Needs trim chillers if the facility water class is too cold for the climate |
Glycol
In climates with freezing weather, dry cooler loops often use propylene or ethylene glycol to protect the coils. Glycol lowers specific heat and raises viscosity, so the loop needs more flow for the same heat and the coil transfers heat less effectively.
Worked example 7 — Glycol flow penalty
Using approximate properties near 100 °F for about 30% propylene glycol (specific heat about 0.93 Btu/lb·°F and density about 63.4 lb/ft³, versus 1.00 and 62.0 for water), Keentel's estimate is that the loop needs about 5% more volumetric flow to carry the same heat at the same range. Coil heat transfer also falls because of higher viscosity. The exact derate depends on the coil design, concentration and temperature, so it must come from the manufacturer's selection at the actual fluid. Many designs avoid glycol in the main facility loop by using an intermediate heat exchanger or drain-down freeze protection.
Trim chillers
A trim chiller cools the facility water the rest of the way when the dry coolers cannot reach the setpoint. In a W32 design in a hot climate, trim chillers may carry a large share of the heat on design day. In a W40 or W45 design they may run only a few hours a year, or not at all. Their electrical demand is the single biggest driver of the dry plant's peak load.
How Keentel Engineering helps here. Trim chillers are large motor loads with starting currents, harmonics and power-quality behavior that must be coordinated with the medium-voltage system and the generators. Keentel sizes their feeders and transformers, studies their starting and restart sequences, and includes them in the generator and utility service calculations.
7. Climate: why the same plant behaves differently in Dallas, Phoenix and Ashburn
The choice between evaporative and dry heat rejection is ultimately a choice about which air temperature the plant works against.
Towers work against the wet-bulb. In the US, design wet-bulbs fall in a fairly narrow band (roughly the mid-70s to low-80s °F for most populated regions).
Dry coolers work against the dry-bulb, which varies far more: design dry-bulbs range from the high 80s in the mid-Atlantic to around 110 °F or more in the desert Southwest.
Hybrids work against something in between, depending on how much water they are allowed to use.
ASHRAE publishes climatic design conditions, including 0.4%, 1% and 2% annual cooling dry-bulb and evaporation wet-bulb values, in Chapter 14 of the ASHRAE Handbook — Fundamentals. Data center designs often go beyond the 0.4% values to an owner-specified extreme (for example, an N-year return-period maximum) because the facility must keep running on the hottest day, not just on 99.6% of hours.
Worked example 8 — Design conditions in the three synthetic climates
| Synthetic climate | 99.6th percentile dry-bulb | 99.6th percentile wet-bulb | Highest hour in the model |
|---|---|---|---|
| Ashburn-like | 88.6 °F | 76.7 °F | 94.1 °F |
| Dallas-like | 96.6 °F | 80.6 °F | 101.7 °F |
| Phoenix-like | 108.9 °F | 78.9 °F | 115.2 °F |
These values come from Keentel's synthetic model, not from ASHRAE. Real design values for those regions differ, and actual projects must use the ASHRAE tables and site-specific weather files. The model is useful because it captures the pattern: the Phoenix-like climate has the hottest dry-bulb but not the hottest wet-bulb, which is why towers work well in hot-dry climates and dry coolers struggle there.
8. The facility water temperature is the master variable
If one decision deserves to be made first, it is the facility water class. The warmer the water the IT equipment can accept, the fewer hours any plant needs water or chillers.
Worked example 9 — How much trim does a dry plant need on the design day?
For a dry cooler with a 12 °F approach, the leaving water temperature on the design day is the design dry-bulb plus 12 °F. With an 18 °F range, the trim chiller must remove the heat between that temperature and the setpoint. Keentel's model gives the share of design-day heat that the trim chillers must carry:
| Synthetic climate | Dry cooler leaving water on design day | W32 (86 °F supply) | W40 (104 °F supply) | W45 (113 °F supply) |
|---|---|---|---|---|
| Ashburn-like | 100.6 °F | 81% | 0% | 0% |
| Dallas-like | 108.6 °F | 100% | 26% | 0% |
| Phoenix-like | 120.9 °F | 100% | 94% | 44% |
The table explains much of the industry's move toward warm-water liquid cooling. In a mild climate, moving from W32 to W40 eliminates trim chillers on the design day entirely. In a hot-humid climate, W45 does the same. In the desert Southwest, even W45 leaves a large trim requirement for a pure dry plant, which is why hybrids or towers often remain the practical answer there.
What limits the water temperature
IT equipment limits. The server maker's maximum coolant inlet temperature at the cold plate, often expressed in the ASHRAE W-class the equipment supports.
CDU approach. Each degree of CDU approach reduces the facility water temperature available.
Air-side loads. Even liquid-cooled halls usually have some air-cooled equipment (power supplies, storage, network) needing colder water or separate cooling.
Reliability margin. Owners often hold a few degrees in reserve for fouling, sensor error and future IT generations.
Heat reuse. Warmer return water makes heat reuse for district heating or industrial processes more practical.
Keentel Study Spotlight — Facility water class optimization. Keentel evaluates W27, W32, W40 and W45 options against the IT roadmap, the climate file and the utility tariff, and reports the effect of each on trim-chiller capacity, annual energy, water, generator sizing and the utility service request. Owners see in one table what each degree of warmer water is worth.
9. Energy: fans, pumps, chillers and PUE
The heat-rejection plant consumes electricity in three places: fans, pumps and, where installed, trim chillers.
Fans
Fan power at full speed depends on airflow and static pressure. Towers move the least air per ton because evaporation carries most of the heat; dry coolers move the most because air must warm up by enough degrees to carry all of it sensibly. With variable-frequency drives, fan power falls roughly with the cube of speed (the fan affinity laws):
At 70% speed a fan draws about 34% of its full-speed power. That is why oversizing dry-cooler coil area and running more fans slower is a common and effective energy strategy, at the cost of land and capital.
For the reference facility, Keentel used illustrative full-speed fan demand of 8 kW per MW of heat for towers, 14 kW/MW for hybrids and 20 kW/MW for dry coolers:
| Architecture | Fan demand at full speed (103 MW of heat) |
|---|---|
| Evaporative towers | About 824 kW |
| Hybrid coolers | About 1,442 kW |
| Dry coolers | About 2,060 kW |
Pumps
Pump power follows the standard hydraulic relation, with flow in gpm, head in feet and η the pump efficiency:
Worked example 10 — Facility water pump power
For 39,050 gpm, a pump efficiency of 75% and a motor efficiency of 95%:
| Loop | Total head | Electrical input |
|---|---|---|
| Closed facility loop serving dry or hybrid coolers | 110 ft | About 1,135 kW |
| Open tower loop, including static lift to the tower distribution basin and the plate heat exchanger | 140 ft | About 1,445 kW |
Open towers lose part of their fan-energy advantage to the extra pumping head. In practice designers often separate the condenser-water pumps (tower side) from the facility pumps (CDU side) across a plate heat exchanger, and the two sets together set the plant's pump demand.
Worked example 11 — Annual heat-rejection energy and PUE in the hot-humid climate
Keentel's hour-by-hour model for the Dallas-like climate at W32 water, with VFD fan control and trim chillers at a coefficient of performance of 6, gives:
| Architecture | Fans and pumps | Trim chillers | Annual energy cost at $70/MWh | Facility PUE (model) |
|---|---|---|---|---|
| Evaporative towers | 13,190 MWh | 110 MWh | About $0.93 million | 1.078 |
| Hybrid coolers | 14,580 MWh | 4,160 MWh | About $1.31 million | 1.085 |
| Dry coolers | 17,970 MWh | 21,050 MWh | About $2.73 million | 1.112 |
The PUE values include an assumed 4.5% for electrical distribution losses (transformers, UPS and cables) and 1.5% for lighting, controls and residual air-side cooling, so the heat-rejection plant is the only thing varying between rows.
Two observations follow. First, every option produces a very good PUE by historical standards, because warm-water liquid cooling removes the large chiller loads of older designs. Second, the spread between options — about 26,000 MWh a year, or about $1.8 million at the illustrative price — is driven mostly by trim chillers, not fans. Raising the water to W40 changes the picture: the model then gives about 10,930 MWh and zero trim hours for the hybrid, and about 12,330 MWh for the dry plant.
ASHRAE Standard 90.4
ASHRAE 90.4-2022, Energy Standard for Data Centers , sets minimum efficiency through a mechanical load component (MLC) and an electrical loss component (ELC), rather than a single PUE target. Many states and cities adopt 90.4 through their energy codes (often by reference from ASHRAE 90.1 or the International Energy Conservation Code). Designers should confirm which edition the authority having jurisdiction has adopted and run the compliance calculation early, because the choice of heat-rejection plant directly sets the MLC.
How Keentel Engineering helps here. Keentel's energy calculations use the same load list as the electrical design, so the annual PUE, the ASHRAE 90.4 compliance calculation, the utility demand estimate and the generator sizing are all drawn from one consistent model rather than from separate spreadsheets that drift apart during design.
10. Water: consumption, withdrawal and the new reporting landscape
Consumption versus withdrawal
Water professionals distinguish between withdrawal(water taken from a source) and consumption(water that does not return to the local watershed). Evaporation is consumption. Blowdown is withdrawn but returned to the sewer and, after treatment, usually to the watershed. For the reference tower plant at 4 cycles, about 75% of the makeup is consumed through evaporation and about 25% is returned as blowdown.
That distinction matters in public debate. A facility reporting "1 million gallons a day" may be describing withdrawal, consumption or both. Clear reporting builds trust.
Indirect water
Electricity generation also uses water, particularly thermoelectric plants with evaporative cooling. A dry cooling plant that leans on trim chillers shifts part of its water footprint upstream to the power plant. The size of that indirect footprint depends heavily on the regional generation mix and is outside the site's control, but sophisticated sustainability reporting increasingly includes it.
The reporting and policy landscape
Water use by data centers has become a legislative topic:
The Congressional Research Service published Data Centers and Water: Frequently Asked Questions (report R49057), summarizing federal and state issues.
Several states have reviewed data center water use and permitting; for example, Texas Senate committees examined data center water use in 2026, and state legislative research offices have published overviews of state data center policies.
Proposed federal legislation has sought standardized reporting of data center energy and water use.
Rules are changing quickly, so owners should treat water reporting as a design requirement: meter makeup, blowdown and any adiabatic water separately, log them in the building management system, and keep the data auditable.
Worked example 12 — Hybrid water in context
For the Dallas-like climate, the hybrid plant at W32 uses about 45 million gallons a year against about 356 million gallons for towers at 4 cycles. On a WUE basis that is roughly 0.23 L/kWh against 1.81 L/kWh. Designed for W40 water, the same hybrid would wet its coils on far fewer hours and use less still. For a community water utility, the difference between the two plants is roughly the annual use of a few thousand households (based on typical US household use of the order of 100,000 gallons a year), which is often the number that decides a public hearing.
How Keentel Engineering helps here. Keentel helps owners prepare the technical basis for water supply agreements and discharge permits: peak-day and annual demand, sensitivity to cycles of concentration and to the facility water class, metering design and the data trail regulators increasingly expect.
11. Electrical consequences: the design day sets the service size
The annual energy comparison in Section 9 understates the difference between options. Electrical equipment, utility service and generators must be sized for the worst hour, and for dry plants the worst hour is far worse than the average.
Worked example 13 — Design-day heat-rejection plant demand
Keentel calculated fan, pump and trim-chiller demand at each synthetic climate's design condition, using 0.55–0.75 kW per ton for trim chillers depending on lift. Results in MW of electrical demand for 100 MW of IT:
| Architecture and water class | Ashburn-like | Dallas-like | Phoenix-like |
|---|---|---|---|
| Evaporative towers, W32 | 2.3 | 3.7 | 2.3 |
| Hybrid, W32 | 7.1 | 11.3 | 12.3 |
| Hybrid, W40 | 2.6 | 2.6 | 2.6 |
| Dry, W32 | 21.0 | 25.2 | 25.2 |
| Dry, W40 | 3.2 | 8.1 | 21.1 |
| Dry, W45 | 3.2 | 3.2 | 10.9 |
The spread is a factor of ten. A dry plant held to W32 water adds more than 20 MW of design-day demand — about a fifth of the IT load — and almost all of it is trim chillers running on the hottest afternoons, which are often the utility's system peak hours.
Worked example 14 — What that demand means at medium voltage
At 0.92 power factor, Keentel's conversions are:
| Cooling-plant demand | Apparent power | Current at 13.8 kV | Current at 34.5 kV |
|---|---|---|---|
| 2.6 MW (hybrid at W40) | 2.83 MVA | 118 A | 47 A |
| 9.0 MW | 9.78 MVA | 409 A | 164 A |
| 22.0 MW (dry at W32, hot climate) | 23.9 MVA | 1,000 A | 400 A |
A 22 MW cooling plant is not a few extra breakers. It is a dedicated 13.8 kV feeder system or an additional 34.5/13.8 kV transformer, more switchgear lineups, larger generator plant and a larger request to the utility. For a campus already near the limit of an interconnection or a transformer delivery slot, choosing a warmer water class or a hybrid can be the difference between fitting in the available service and waiting years for a larger one.
Interconnection and transmission planning
Utilities study large loads at their requested peak demand. If the cooling plant's design-day demand is 20 MW higher than necessary, the utility will plan for it, allocate upgrade costs against it and, under some tariffs, charge demand or reservation fees on it. Conversely, a utility may ask the customer how its load behaves on extreme days, during voltage disturbances and when cooling equipment restarts. Keentel's guide on studying large loads and generation together covers how those studies work.
Keentel Study Spotlight — Cooling-driven load profile for the utility. Keentel prepares the large-load data utilities now request: an hourly load profile for typical and extreme years, design-day peak with the cooling plant's contribution separated, ramp rates, motor starting and restart behavior, and power quality. Presenting a credible, weather-driven profile often shortens the utility's study and avoids overbuilding the service.
12. Electrical design of the heat-rejection plant
Whatever architecture is chosen, the heat-rejection plant is a large collection of motors: fans, pumps, compressors, chemical feed and controls. Its electrical design deserves the same rigor as the IT power path.
Typical electrical arrangement
| Element | Typical US practice for a 100 MW AI campus |
|---|---|
| Service to the plant | 13.8 kV or 34.5 kV feeders from the campus substation, often A and B sources |
| Transformation | 13.8 kV–480Y/277 V unit substations, sized for the design-day plant demand plus spare capacity |
| Motor control | 480 V motor control centers or switchboards with VFDs for fans and pumps |
| Large chillers | 4.16 kV or 13.8 kV medium-voltage motors on large centrifugal machines; 480 V on smaller units |
| Controls and CDU pumps | Uninterruptible power for controls and for loads whose loss would interrupt coolant flow (see Section 13) |
| Standby | Generator-backed distribution for the whole cooling plant |
Variable-frequency drives and harmonics
Almost every fan and pump in a modern plant runs on a VFD. Six-pulse drives draw non-sinusoidal current that can raise voltage distortion on the 480 V and medium-voltage buses and at the utility point of common coupling. IEEE Std 519-2022 sets limits on voltage distortion and on total demand distortion (TDD) of current, the latter depending on the ratio of available short-circuit current to load current at the point of common coupling.
Worked example 15 — Harmonic contribution of plant VFDs
Consider a 480 V mechanical switchboard with a 5 MW maximum demand, of which 2 MW is fan and pump VFDs. Approximating TDD as the drives' current distortion weighted by their share of demand:
| Drive technology | Typical current distortion of the drive | Estimated TDD at the switchboard |
|---|---|---|
| Standard six-pulse with line reactor | About 35–40% | About 15% |
| Active front end or low-harmonic drive | About 5% | About 2% |
A TDD of 15% would exceed common IEEE 519 limits at many points of common coupling. Active-front-end drives, 18-pulse drives or active filters cost more but avoid harmonic heating of transformers, nuisance tripping and resonance with capacitor banks. The decision should come from a harmonic study, not a rule of thumb. Keentel's guide to harmonics in plain English and IEEE 519 explains the limits and their application.
Arc flash and short circuit
A 480 V switchboard fed by a 3,000 kVA unit substation can see available fault currents of 50–65 kA, and the incident energy at fan and pump MCCs depends heavily on the upstream protective device's clearing time. NFPA 70E requires an arc flash risk assessment and equipment labeling, and the NEC requires arc energy reduction for larger circuit breakers. The cooling plant, which operators service frequently and often while energized, deserves particular attention.
Worked example 16 — Generator sizing for the cooling plant
Standby generators must carry the cooling plant on the design day, including motor restart. Using 2.5 MW generator sets and a 25% allowance for motor starting and future margin:
| Case | Design-day cooling demand | Generator sets of 2.5 MW needed for the cooling plant alone |
|---|---|---|
| Evaporative towers, Dallas-like | 3.7 MW (with trim on extreme hours) | 2 |
| Dry plant at W32, Phoenix-like | 25.2 MW | 13 |
Eleven additional generator sets per 100 MW of IT — plus their fuel storage, air permits, enclosures, paralleling switchgear and maintenance — is a substantial cost that a cooling comparison based only on PUE would miss. Generator count also affects air-quality permitting, because emergency engines have hours-of-operation and emissions limits.
How Keentel Engineering helps here. Keentel designs the cooling plant's electrical distribution, performs short-circuit, protective-device coordination, arc flash (IEEE 1584 and NFPA 70E) and harmonic (IEEE 519) studies, and sizes generator plants with motor-starting and restart sequences that reflect how the mechanical plant actually recovers after a utility outage.
13. Resilience: when the cooling loop becomes part of the critical path
With air cooling, a short loss of cooling gave operators minutes before IT equipment overheated, thanks to the thermal mass of the room air and chilled water. With direct-to-chip liquid cooling, loss of coolant flow at the cold plates can push accelerators to thermal limits in seconds. Keentel's digital-twin study of pump failures showed throttle thresholds reached within seconds after a total loss of flow.
That changes the resilience design:
| Layer | Typical approach |
|---|---|
| TCS pumps in the CDUs | Redundant pumps; on uninterruptible power with the IT load |
| Facility water pumps | N+1 or 2N; on a mechanical UPS or with enough loop thermal mass to ride through generator start |
| Heat-rejection fans | Generator-backed; brief interruption tolerable if the loop has thermal mass |
| Trim chillers | Generator-backed with controlled restart; restart times of several minutes must be covered by loop thermal mass or buffer tanks |
| Controls and sensors | Uninterruptible power, redundant controllers, fail-safe valve positions |
| Water supply (towers) | On-site storage for a defined number of hours; redundant makeup sources |
Worked example 17 — Thermal ride-through of the facility loop
If heat rejection stops completely while the IT load continues, the facility loop warms at a rate set by its water volume. With 351.5 million Btu/h of heat and water at 8.34 lb/gal:
| Facility loop water volume | Temperature rise rate with no heat rejection | Time to rise 9 °F (5 K) |
|---|---|---|
| 150,000 gallons | About 4.7 °F per minute | About 115 seconds |
| 300,000 gallons | About 2.3 °F per minute | About 230 seconds |
Generator start and transfer typically take 10–30 seconds, but a chiller restart may take several minutes. A plant that depends on trim chillers in summer therefore needs either more loop volume (buffer tanks), chillers with fast-restart features, or IT load capping coordinated with the cooling controls. A tower or warm-water dry plant whose fans and pumps restart in under a minute is inherently easier to ride through.
Water storage for evaporative plants
Towers stop working if makeup water is lost. Owners targeting high availability usually provide on-site storage for a defined period (commonly expressed in hours or days at design evaporation) and two independent makeup sources. At about 800 gpm of makeup for 100 MW of IT, 48 hours of storage is roughly 2.3 million gallons, a significant structure with its own footprint and permitting.
Tier considerations
Uptime Institute Tier objectives apply to the cooling plant as much as to the electrical system. A concurrently maintainable (Tier III) plant needs redundant capacity components and distribution paths so any component can be removed for maintenance; a fault-tolerant (Tier IV) plant must also survive a single failure with automatic response and compartmentalization. Water supply, makeup pumps and treatment for evaporative plants must be included in that analysis. Keentel's guide to data center Tiers for MEP engineers discusses these requirements in depth.
Keentel Study Spotlight — Cooling ride-through and restart study. Keentel models the facility loop, CDUs, pumps, heat-rejection plant and generators through a utility outage, generator start, transfer and staged restart, and reports coolant temperatures at the racks over time. The study identifies which loads must be on UPS, how large buffer tanks must be, and how the restart sequence must be programmed so that motor inrush does not overload the generators.
14. Grid interaction: cooling plants and large-load behavior
At campus scale, the cooling plant affects not only how much power the facility draws but how it behaves on the grid.
Voltage disturbances. NERC has published an incident review of a large loss of voltage-sensitive load and guidance on large-load integration. Data centers that transfer to backup power during a grid fault can drop hundreds of megawatts at once. Cooling-plant drives and controls must ride through the same disturbances as the IT systems, or the facility may lose cooling after the grid has already recovered.
Restart surges. After a transfer back to utility power, staged restart of chillers and fans should be coordinated with the utility to avoid sudden demand swings.
Weather-driven peaks. Dry plants add load on hot afternoons that coincide with system peaks. Utilities may ask large loads to reduce demand in emergencies; a plant with thermal storage or warm-water capability can shed cooling load briefly without affecting IT.
Flexibility. Some campuses are negotiating flexible or interruptible service in exchange for faster interconnection. Cooling plants with buffer tanks, ice or chilled-water storage, or warm-water operation give the operator room to shift load. Keentel's guide to grid flexibility covers those arrangements.
How Keentel Engineering helps here. Keentel studies large-load ride-through and restart behavior, including the cooling plant's drives, chillers and controls, and prepares the technical information utilities and transmission planners now request under evolving NERC and regional large-load requirements.
15. Site layout, noise, plume and permitting
Footprint
The heat-rejection yard must fit not only the coolers but also airflow clearances that prevent hot exhaust air from recirculating into the inlets, maintenance access, piping corridors, electrical rooms, water treatment and, for towers, water storage.
Worked example 18 — Converting typical yard areas to US units
| Architecture | Typical yard dimensions (100 MW) | In feet | Yard area |
|---|---|---|---|
| Evaporative towers | About 140 m × 60 m | About 459 ft × 197 ft | About 90,400 ft² (2.1 acres) |
| Hybrid coolers | About 130 m × 55 m | About 427 ft × 180 ft | About 77,000 ft² (1.8 acres) |
| Dry coolers | About 120 m × 50 m | About 394 ft × 164 ft | About 64,600 ft² (1.5 acres) |
Commonly cited site-area ranges of 0.8–1.2 ha (2.0–3.0 acres) for towers, 0.6–1.0 ha (1.5–2.5 acres) for hybrids and 0.5–0.9 ha (1.2–2.2 acres) for dry coolers should be treated with caution. Dry coolers need more coil area per ton than towers, and the compact dry figures assume warm water, stacked V-bank coolers or rooftop placement. On a real site, setbacks for noise and recirculation often dominate.
Noise
Dry and hybrid yards carry many large fans. Sound power from multiple identical sources adds logarithmically, and sound pressure falls with distance:
where r is in meters and the second relation is a simple free-field estimate for a point source.
Worked example 19 — Property-line noise screening
A yard with 72 fans, each with a sound power level of 94 dBA, has a total sound power of about 112.6 dBA. Treating the yard as one point source with no barriers or ground effects:
| Distance to receiver | Estimated sound pressure level |
|---|---|
| 300 ft (91 m) | About 62 dBA |
| 600 ft (183 m) | About 56 dBA |
| 1,000 ft (305 m) | About 52 dBA |
Many local ordinances set nighttime limits at residential property lines in the range of 45–55 dBA. On a constrained site, a dry plant may need low-noise fans, barriers, more coolers running slower, or a larger setback. Noise studies should use proper propagation models with the actual layout; this screening only shows the scale of the issue.
Plume and visual impact
Towers and wet-assisted hybrids can produce a visible plume in cool, humid weather. Plume is rarely a safety issue but can affect permitting near airports and highways and can cause icing on nearby surfaces in winter. Plume-abated towers and dry-mode winter operation for hybrids reduce it.
Permitting checklist
| Permit area | Evaporative | Hybrid | Dry |
|---|---|---|---|
| Water supply agreement or water rights | Major | Moderate | Minor |
| Wastewater discharge (blowdown) | Major | Minor to moderate | Minimal |
| Legionella registration and water management program | Required | Required for wetted media | Generally not for the coils |
| Noise ordinance | Moderate | Moderate to major | Major |
| Air permit for generators | Smaller generator plant | Depends on trim needs | Can be largest |
| Building and energy code (ASHRAE 90.4) | Yes | Yes | Yes |
| Visual and plume impact | Possible | Limited | None |
How Keentel Engineering helps here. Keentel supports permitting with the electrical, energy and load data permit reviewers request, coordinates with acoustical and civil consultants on yard layout and setbacks, and documents generator sizing so that air permits reflect the actual cooling-plant demand rather than conservative guesses.
16. Lifecycle cost and a decision framework
The water–energy trade-off in one picture
Worked example 20 — Twenty-year lifecycle cost in the hot-humid climate
Keentel compared the three architectures for the Dallas-like climate at W32 water. All inputs are illustrative and chosen to show method, not to predict a particular project's costs:
Installed heat-rejection cost: $130/kW of heat for towers (including plate heat exchangers and water storage), $210/kW for hybrids and $185/kW for dry coolers with trim chillers.
Energy at $70/MWh from Worked example 11.
Water, sewer and chemicals from Worked example 5 for towers; adiabatic water at the hybrid's modeled volume; a small allowance for dry-plant fluid and treatment.
Annual maintenance of $450,000 for towers, $380,000 for hybrids and $220,000 for dry coolers.
7% discount rate over 20 years.
| Architecture | Capital cost | Annual operating cost | 20-year present-value cost |
|---|---|---|---|
| Evaporative towers | $13.4 million | $4.55 million | About $61.6 million |
| Hybrid coolers | $21.6 million | $2.02 million | About $43.0 million |
| Dry coolers with trim chillers | $19.1 million | $2.97 million | About $50.5 million |
With these inputs, the hybrid is the lowest lifecycle cost in a hot-humid climate because it avoids most of the tower's water cost without incurring the dry plant's chiller energy. With lower water prices, the tower wins; with W40 water, the dry plant closes the gap sharply because its trim-chiller cost almost disappears. The capital costs here exclude the electrical and generator differences in Sections 11 and 12, which further penalize plants with high design-day demand. The result is sensitive enough that it must be recalculated for each site.
A decision framework
| Question | If the answer is… | It favors… |
|---|---|---|
| Is reliable water available at reasonable cost, with discharge capacity? | Yes, plentiful | Evaporative towers |
| Limited or contested | Hybrid or dry | |
| What facility water class can the IT roadmap accept? | W40 or warmer | Dry or hybrid without trim chillers |
| W32 or colder | Towers or hybrids; dry needs large trim | |
| How hot is the design dry-bulb? | Below about 95 °F | Dry works well with warm water |
| Above about 105 °F | Towers or hybrids | |
| Is the utility service or interconnection constrained? | Yes | Options with low design-day demand: towers, or hybrid/dry at warm water |
| Are noise limits strict at the property line? | Yes | Towers (fewer fans), large setbacks, or low-noise dry coolers |
| Does the owner have public water commitments? | Yes | Dry or hybrid, with transparent WUE reporting |
| Does the site have freezing winters? | Yes | Glycol or drain-down for dry coils; winter plume control for towers |
| Is heat reuse planned? | Yes | Warm-water dry or hybrid plants with higher return temperatures |
Keentel Study Spotlight — Cooling architecture selection study. Keentel's selection study combines the water and energy model, design-day electrical demand, generator and utility service impact, noise screening, footprint and a lifecycle cost comparison into one decision matrix weighted by the owner's priorities. The study is designed to be read by the owner's board, the utility and the permitting authority, not just by engineers.
17. Commissioning and acceptance testing
A heat-rejection plant that looks right on paper can still fall short in the field. Commissioning confirms capacity, controls and resilience before the IT load arrives.
Thermal performance testing
Cooling towers. The Cooling Technology Institute's acceptance test code ATC-105 defines how to field-test an open tower's thermal capability; ATC-105S covers closed-circuit coolers. CTI STD-201 provides third-party certification of rated thermal performance. Specifying CTI-certified equipment and a field acceptance test protects the owner against undersized towers.
Dry and hybrid coolers. Performance should be verified against the manufacturer's rated conditions with calibrated temperature, flow and airflow measurements, and with a defined correction method for ambient conditions on test day.
Integrated systems testing (IST)
For liquid-cooled AI halls, integrated testing typically includes:
| Test | What it proves |
|---|---|
| Load-bank heat test at stepped loads | Plant capacity, approach and control stability at each step |
| Utility failure and generator transfer | Coolant temperature stays within limits through transfer; UPS-backed loads stay running |
| Staged restart on generators | Motor starting does not overload generators; restart sequence is correct |
| Component failure (pump, fan bank, cooler, chiller) | Redundancy works automatically; temperatures stay within limits |
| Wet/dry mode transition (hybrids) | Smooth switch-over without temperature excursions or water hammer |
| Water supply loss (evaporative) | Storage lasts the design duration; alarms and backup makeup sources work |
| Controls failure | Fail-safe positions and redundant controllers behave as designed |
| Power quality | Harmonic distortion and voltage regulation within limits with all drives running |
How Keentel Engineering helps here. Keentel writes and witnesses the electrical portions of integrated systems tests for data centers: transfer and restart sequences, UPS performance, generator loading with cooling motors, protective relay settings and power-quality measurements. We coordinate with the commissioning authority so electrical and mechanical tests are run together, the way the facility will actually operate.
18. Common mistakes and a review checklist
Ten mistakes Keentel sees in cooling-plant selection
1. Comparing options on annual PUE alone, without design-day demand, water, noise and generator impact.
2. Fixing the facility water temperature before asking the IT vendor what the hardware can accept, then designing a dry plant for W32 water in a hot climate.
3. Using average weather instead of design and extreme conditions for sizing.
4. Forgetting pump and auxiliary heat when sizing heat rejection.
5. Assuming hybrid water use is negligible without modeling the switch-over strategy against real weather.
6. Leaving the cooling plant off the UPS and ride-through analysis for liquid-cooled racks.
7. Underestimating trim-chiller demand in the electrical service and generator calculations.
8. Ignoring harmonics from hundreds of VFDs until transformers run hot or breakers trip.
9. Treating noise as a late-stage issue, then discovering the dry yard cannot meet the property-line limit.
10. Not metering water separately for makeup, blowdown and adiabatic use, leaving the owner unable to report WUE credibly.
Review checklist
| Topic | Check |
|---|---|
| Basis of design | IT coolant limits, CDU approach, facility water class and range agreed in writing |
| Climate | ASHRAE design conditions and an owner-specified extreme; multi-year hourly weather used for annual modeling |
| Heat balance | IT plus pump, CDU and air-side heat included |
| Water | Makeup, blowdown, adiabatic use, storage, treatment, discharge and permits quantified |
| Energy | Hourly model including fans, pumps, trim chillers and controls |
| Electrical | Design-day demand, MV feeders, transformers, MCCs, generators and UPS sized from the same model |
| Power quality | Harmonic study with all drives; IEEE 519 compliance at the point of common coupling |
| Resilience | Ride-through study; redundancy matching the Tier objective |
| Grid | Large-load data for the utility, including cooling contribution and ride-through behavior |
| Site | Footprint with clearances, noise screening, plume, setbacks |
| Public health | ASHRAE 188 water management program for wet systems |
| Testing | CTI acceptance tests and integrated systems tests in the specifications |
19. Where AI cooling plants are heading
Warmer water. IT vendors are moving toward hardware that tolerates higher coolant temperatures, making W40 and W45 designs more common and chiller-free plants practical in more of the US.
Hybrid as the default compromise. Survey work by the Uptime Institute in 2025 described direct liquid cooling adoption as growing steadily rather than explosively, with many operators running mixed air and liquid estates. Hybrid heat rejection fits that mixed reality.
Water transparency. Federal and state attention to data center water use is likely to make metered, reported WUE a routine permit condition.
Heat reuse. Higher return temperatures make district heating and industrial heat reuse more attractive, turning a waste stream into a community asset in suitable locations.
Grid-aware cooling. Thermal storage and flexible cooling controls will increasingly be used to shape the facility's demand for the utility, not just to save energy.
How Keentel Engineering helps here. Keentel designs electrical systems that are ready for change: spare feeder positions and transformer capacity for future trim or reuse equipment, metering for new reporting rules, and controls integration that lets cooling respond to grid signals.
20. Water sources: potable, reclaimed, groundwater and on-site storage
When towers or hybrids are selected, the source of makeup water becomes a design topic of its own.
| Source | Advantages | Engineering issues |
|---|---|---|
| Municipal potable water | Reliable, consistent quality, simple permits | Competes with community use; highest public scrutiny; cost |
| Reclaimed (treated wastewater) | Reduces demand on potable supply; often favored by regulators | Higher dissolved solids and nutrients; lower achievable cycles; more biocide and filtration; separate piping and backflow protection |
| Groundwater | Independent of municipal supply | Water rights and pumping permits; hardness and silica may limit cycles; well pumps add electrical load |
| Captured rainwater or condensate | Small supplemental volumes | Not enough to carry a large tower plant; storage and treatment needed |
Reclaimed water is increasingly common for large campuses because it avoids drawing on drinking-water supplies. Its quality usually forces lower cycles of concentration, so the plant withdraws more water even though the water is not potable. Treatment equipment, additional filtration and the electrical loads to run them should be included in the design from the start.
On-site storage serves two purposes: covering interruptions of the makeup supply, and buffering daily peaks so the supply connection can be smaller. Its pumps, level controls and chemical feed must be on reliable power, because an evaporative plant without makeup water loses capacity within hours.
How Keentel Engineering helps here. Keentel designs the electrical service for water infrastructure on data center campuses — well pumps, booster pumps, reverse-osmosis and filtration skids, chemical feed, storage level controls — and integrates them into the facility's standby power and monitoring systems.
21. Mixed halls: liquid and air cooling in the same facility
Few AI halls are fully liquid cooled. Power supplies, memory, storage, network equipment and some legacy servers still reject heat to air, often 10–30% of the IT load depending on the hardware. That air-side heat is removed by computer room air handlers, fan walls or rear-door heat exchangers, which usually need colder water than the CDUs.
Common arrangements are:
Two water temperatures. A warm facility loop for CDUs and a colder loop for air-side equipment, sometimes produced by a small chiller plant or by a heat exchanger off the warm loop with trim.
Rear-door heat exchangers on warm water where the air-side load per rack is moderate.
Shared plant with blending. One heat-rejection plant serving both loops through mixing valves, which is simpler but forces the plant toward the colder requirement.
The share of air-cooled load matters to heat-rejection selection because it sets how much cold water the site must produce. A plant optimized for warm-water liquid cooling can be undermined by a large air-cooled fraction that needs chilled water on design day. Keentel's companion guide on CDUs discusses the air-side and liquid-side split from the IT perspective.
How Keentel Engineering helps here. Keentel's load lists separate liquid-cooled and air-cooled IT heat, so the electrical design reflects the right mix of CDU pumps, air handlers, fan walls and chillers, and so the utility service request is based on the real split rather than a single blended assumption.
22. A specification checklist for owners
Owners who will hire a design team, or review one, can use this checklist to make sure the cooling plant specifications cover what matters.
| Specification item | What to require |
|---|---|
| Basis of design | Facility water class, range, CDU approach, air-cooled fraction and climate data source stated explicitly |
| Design condition | ASHRAE design value plus an owner-specified extreme, and the required performance at each |
| Redundancy | N+1, N+2 or 2N for coolers, pumps, chillers and water supply, consistent with the Tier objective |
| Thermal certification | CTI STD-201 certification for towers; certified or witnessed ratings for dry and hybrid coolers |
| Field testing | CTI ATC-105 or ATC-105S acceptance tests, or equivalent tests with a defined correction method |
| Water | Maximum annual and peak-day water, cycles of concentration, metering points, storage hours |
| Water management | ASHRAE 188 program, treatment equipment, Legionella sampling and response plan |
| Noise | Maximum sound power per unit and property-line limits with a compliance test |
| Electrical | Motor efficiency classes, VFD type and harmonic performance, MCC ratings, short-circuit ratings, arc flash labeling |
| Controls | Redundant controllers, fail-safe positions, sequences for wet–dry switch-over and restart, BMS points list |
| Power continuity | Which pumps and controls are on UPS; ride-through requirements; restart time limits |
| Integration | Interfaces with CDUs, electrical power monitoring, utility signals and demand-response requests |
| Testing | Integrated systems test scripts, including utility failure, restart and component failures |
| Documentation | As-built drawings, setpoints, water and energy metering data retained for reporting |
23. Questions to ask your design team
1. What facility water class did you design for, and has the IT vendor confirmed it in writing?
2. Which weather data did you use for annual energy and water, and which condition did you use for sizing?
3. What is the cooling plant's electrical demand on the design day, separately from the IT load?
4. How many trim-chiller hours does the design need, and what happens to peak demand if the water class can be raised?
5. How much water will the plant use on the peak day and over a year, and where will blowdown go?
6. Which cooling loads are on UPS, and how long can the loop ride through a total loss of heat rejection?
7. What does a harmonic study show at the point of common coupling with all drives running?
8. How many generator sets does the cooling plant add, and how does the restart sequence work?
9. What is the predicted noise level at the nearest property line at night?
10. How will water and energy be metered and reported?
Clear answers to these questions usually reveal whether the cooling architecture was chosen as a system or as a mechanical line item.
24. Operating the plant through the seasons
Selection is only half the story. A heat-rejection plant runs through four seasons, and each brings its own risks.
Summer. The plant runs at or near design capacity on the hottest afternoons. Towers face their highest wet-bulb hours and highest evaporation; hybrids switch into wet mode; dry plants run fans at full speed and call on trim chillers. Operators should verify spare capacity before each heat wave, confirm that redundant units are available rather than out for maintenance, and coordinate with the utility on any demand-response requests. Maintenance that removes capacity should be scheduled outside the summer peak.
Autumn and spring. These are the best windows for planned maintenance: fill and drift eliminator inspection, coil cleaning, fan and motor service, VFD checks and controls testing. They are also the seasons when the plant switches between operating modes most often, so sequences should be watched for hunting between wet and dry operation.
Winter. Towers risk icing on fill, louvers and nearby surfaces; basins need heaters or indoor sumps; plume can become visible. Dry coolers face freezing risk if the loop is water rather than glycol, especially during low-load or standby periods; drain-down or minimum-flow strategies must be tested. Hybrids should drain and dry their wet systems to avoid freezing and biological growth. Winter is also when warm-water plants can most easily support heat reuse.
All year. Water treatment, Legionella monitoring, fan and pump vibration trending, coil fouling checks (rising approach at constant load is the classic sign), drive health and electrical thermography should run continuously. Trending the plant's kW per ton and approach against the commissioning baseline gives early warning of fouling, failed fans or control problems before they become capacity shortfalls on the next design day.
Key operating indicators
| Indicator | What it reveals |
|---|---|
| Approach (leaving water minus wet-bulb or dry-bulb) | Fouling, airflow problems, failed fans or nozzles |
| kW per ton of heat rejected | Fan and pump efficiency, control tuning |
| Trim-chiller hours | Whether the plant is meeting its warm-water design intent |
| Makeup and blowdown ratio | Actual cycles of concentration and treatment performance |
| Adiabatic water per wet hour | Pad or spray condition and switch-over tuning |
| Pump differential pressure and flow | Strainer fouling, valve problems, air in the loop |
| Harmonic distortion and drive alarms | Drive health and power-quality changes |
How Keentel Engineering helps here. Keentel designs metering and power monitoring so these indicators come directly from the electrical and mechanical systems, and helps owners set up NFPA 70B electrical maintenance programs for the cooling plant's switchgear, MCCs, drives and motors alongside the mechanical maintenance plan.
25. Summary of the worked examples
| No. | Worked example | Key result (illustrative) |
|---|---|---|
| 1 | IT load to heat-rejection duty | 103 MW of heat, about 29,300 tons |
| 2 | Facility water flow | 39,050 gpm at an 18 °F range |
| 3 | Tower makeup water | About 600 gpm evaporated; 1.15 million gal/day makeup at 4 cycles |
| 4 | Water usage effectiveness | About 1.81 L/kWh at 4 cycles; 1.63 L/kWh at 6 |
| 5 | Water and sewer cost | About $3.2 million per year |
| 6 | Hybrid hours and water | 80–94% less water than towers across three climates |
| 7 | Glycol flow penalty | About 5% more flow with about 30% propylene glycol |
| 8 | Synthetic design conditions | Design dry-bulb from about 89 °F to 109 °F |
| 9 | Dry-plant trim on design day | From 0% to 100% of heat depending on climate and water class |
| 10 | Pump power | About 1,135 kW closed loop; 1,445 kW open loop |
| 11 | Annual energy and PUE (hot-humid) | PUE 1.078 towers, 1.085 hybrid, 1.112 dry at W32 |
| 12 | Hybrid water in context | About 0.23 L/kWh against 1.81 L/kWh for towers |
| 13 | Design-day plant demand | From about 2.3 MW to about 25 MW per 100 MW of IT |
| 14 | Medium-voltage impact | 22 MW of cooling is about 1,000 A at 13.8 kV |
| 15 | VFD harmonics | Estimated TDD about 15% with six-pulse drives, 2% with active front ends |
| 16 | Generators for cooling | About 2 sets for towers against about 13 for a hot-climate dry plant at W32 |
| 17 | Thermal ride-through | About 2 minutes to rise 9 °F with 150,000 gallons |
| 18 | Yard areas in US units | About 1.5–2.1 acres for the equipment yard alone |
| 19 | Noise screening | About 62 dBA at 300 ft from a 72-fan yard |
| 20 | Twenty-year lifecycle cost | Hybrid lowest in the hot-humid example |
Part C — Three In-Depth Anonymous US Case Studies
The following case studies are composites built from conditions Keentel Engineering encounters on data center projects. Locations are described only by region, figures are rounded and illustrative, and no client, site or equipment supplier is identified.
Case study 1 — A 150 MW AI campus in North Texas chooses hybrid heat rejection
Situation
A developer acquired land in the Dallas–Fort Worth region for a 150 MW IT AI training campus, built in three 50 MW phases. The preliminary mechanical concept used open cooling towers with plate heat exchangers serving W32 facility water, a familiar design with low first cost. Two issues arose during site due diligence. The municipal water provider indicated that it could supply the tower makeup water for phase 1 but would need a new supply main and a formal water-use agreement for later phases. The city's sewer authority also flagged blowdown volume and dissolved solids for review. Separately, the utility's preliminary large-load study assumed a total campus demand that left little margin on the planned 345/34.5 kV substation transformers.
Keentel's scope
Keentel was engaged as owner's engineer for the electrical and MEP coordination and to lead a cooling architecture selection study with the mechanical engineer of record.
Analysis
Keentel scaled the reference-facility model to 150 MW of IT, using the site's multi-year hourly weather rather than the synthetic profile in this guide.
| Metric (150 MW IT) | Towers at W32, 4 cycles | Hybrid at W32 | Hybrid at W40 | Dry at W32 with trim |
|---|---|---|---|---|
| Peak-day water | About 1.7 million gallons | Up to about 0.6 million gallons on the hottest days | Small, only on extreme days | Near zero |
| Annual water | About 530 million gallons | About 68 million gallons | Well under half the W32 hybrid | Near zero |
| Design-day cooling-plant demand | About 5.5 MW | About 17 MW | About 3.9 MW | About 38 MW |
| Additional generator sets for cooling (2.5 MW) | About 3 | About 9 | About 2 | About 19 |
The IT vendor's roadmap for the planned GPU racks allowed facility water up to 104 °F with the selected CDU approach, which made W40 feasible. Keentel's model showed that a hybrid plant at W40 used adiabatic assist only on the hottest afternoons and needed no trim chillers on the design day.
Electrical consequences
The W40 hybrid kept the cooling plant's design-day demand under 4 MW, about 34 MW less than the dry-at-W32 option. That margin let all three phases fit within the planned substation transformers without an additional unit.
The generator capacity dedicated to the cooling plant dropped to about two 2.5 MW sets for the whole campus, instead of about nineteen for the dry-at-W32 option.
The 480 V mechanical switchboards were designed with active-front-end drives after a harmonic study showed six-pulse drives would push TDD above the IEEE 519 limit at the 34.5 kV point of common coupling under light IT load.
CDU pumps and controls went on the IT UPS; facility pumps went on a dedicated mechanical UPS sized for a 30-second generator transfer, supported by 250,000 gallons of facility loop volume.
Water and permitting
The hybrid's peak-day water demand fit within the existing municipal supply without a new main. Keentel prepared the technical basis for the water-use agreement: modeled hourly demand, peak-day demand at the owner-specified extreme temperature, and a metering plan with separate meters for adiabatic supply, bleed and the small closed-loop makeup. The sewer authority accepted the reduced bleed volume without the pretreatment originally discussed.
Outcome
The owner selected hybrid coolers at W40. Lifecycle cost in Keentel's model was the lowest of the four options once water, sewer, generators and the avoided transformer were counted. The utility revised its study with the lower cooling-plant demand, and the campus water footprint dropped by roughly 85–90% compared with the original tower concept.
Lessons
The facility water class decided the outcome more than the cooler technology.
Water and electrical capacity were both binding constraints; solving one without the other would have failed.
A weather-driven load profile gave the utility confidence to accept a lower peak.
Case study 2 — A 100 MW desert campus: the cost of "zero water" at W32
Situation
An owner planning a 100 MW IT campus in central Arizona committed publicly to zero routine water use for cooling. The initial design used closed-loop dry coolers with large centrifugal trim chillers to deliver W32 facility water, which the first IT supplier required. Late in schematic design, the electrical engineer of record flagged that the cooling plant's design-day demand had grown far beyond the original allowance, and the utility questioned the summer peak in the interconnection application.
Keentel's scope
Keentel was retained for an independent review of the cooling plant's electrical impact and to evaluate alternatives that would preserve the owner's water commitment as far as possible.
Analysis
Using the site's design and extreme dry-bulb temperatures, Keentel's model reproduced the problem: at W32, dry coolers alone could not meet the setpoint on design day, and trim chillers carried essentially all the heat on the hottest afternoons.
| Option (100 MW IT, hot-dry climate) | Design-day cooling demand | Trim chiller hours per year | Annual heat-rejection energy | Annual water |
|---|---|---|---|---|
| Dry at W32 (original) | About 25 MW | Several thousand | About 66 GWh | Near zero |
| Dry at W40 | About 21 MW | Fewer, but still most hot afternoons | About 24 GWh | Near zero |
| Dry at W45 | About 11 MW | Concentrated on extreme days | Lower | Near zero |
| Hybrid at W40 | About 2.6 MW | None on design day in the model | Lowest of the four options | Tens of millions of gallons |
Keentel also tested the generator plant. Supporting 25 MW of cooling on generators required about 13 additional 2.5 MW sets, with corresponding fuel storage and an air permit for more engine-hours capacity than the owner had planned.
Options presented
Keentel presented three paths to the owner, each with water, energy, peak demand, generator and cost consequences:
1. Keep zero water, move to warmer water. Change the IT hardware selection to equipment rated for W45 coolant, cutting design-day demand to about 11 MW and trim chillers to the most extreme days. This required the IT team to confirm the newer hardware's supply limits and accept somewhat higher component temperatures.
2. Allow limited water on extreme days. Add adiabatic precooling to the dry coolers at W40, using water only on the hottest few hundred hours. This kept annual water low and cut peak demand to under 3 MW.
3. Keep the original design and buy capacity. Accept the higher utility service, generator count and summer energy cost.
Electrical design changes
Whichever path was chosen, Keentel recommended:
moving trim chillers to medium-voltage motors on dedicated 13.8 kV feeders with soft-start equipment to limit voltage dip on restart;
adding a 400,000-gallon buffer tank to cover the chillers' multi-minute restart after a utility outage;
including trim chillers in the large-load ride-through discussion with the utility, because a sudden loss and restart of 20 MW of chillers is visible on the transmission system.
Outcome
The owner chose option 1 for the first building and a variant of option 2 for later buildings, after revising its public commitment to "no routine water use, limited emergency adiabatic assist above a defined temperature." The utility service request was reduced by more than 10 MW, and the generator plant shrank accordingly.
Lessons
A zero-water commitment made before the IT hardware and water class were settled created an expensive electrical problem.
In hot-dry climates, dry plants need warm water to be practical; otherwise the water saving is paid for with grid capacity and energy.
Transparent, conditional water commitments are easier to keep than absolute ones.
Case study 3 — Expanding a 200 MW campus in Northern Virginia with evaporative towers
Situation
An operator in Northern Virginia planned a 200 MW IT expansion next to an existing campus that already used open cooling towers. The operator wanted to keep a common design for maintenance staff and spare parts. The county raised three concerns during review: water supply and discharge, nighttime noise at nearby homes, and winter plume visible from a highway.
Keentel's scope
Keentel was engaged for the electrical design of the expansion's cooling plant and substation, and to support the operator in preparing technical responses to the county's concerns.
Water
Scaling the reference model to 200 MW, Keentel estimated full-load evaporation of about 1,190 gpm. At the existing campus's 4 cycles of concentration, makeup would be about 1,590 gpm (about 2.3 million gallons per day at full load). Working with the water treatment specialist, the design added softening pretreatment to allow 6 cycles, reducing makeup to about 1,430 gpm (about 2.1 million gallons per day) and cutting blowdown by about 40%. The water utility accepted the demand with a requirement for 48 hours of on-site storage, about 4.1 million gallons at the higher cycles, which Keentel incorporated into the site's electrical and controls design (storage pumps on generator-backed power, level instrumentation on the SCADA system).
Noise and plume
The acoustical consultant's model showed that towers, with far fewer fans than an equivalent dry yard, could meet the county's nighttime limit with low-noise fans and a barrier wall on one side. A dry-cooler alternative, studied for comparison, needed roughly three times the fan count and could not meet the limit at the nearest residence without a larger setback the site did not have. Plume abatement coils were specified on the towers nearest the highway.
Electrical design
The expansion's cooling plant, at about 5–7 MW design-day demand, was served from two 34.5/13.8 kV transformers at the new substation, each sized to carry the full plant for concurrent maintainability.
All tower fans and pumps used active-front-end VFDs after a harmonic study.
An arc flash study led to maintenance switches and zone-selective interlocking on the 480 V switchboards, bringing incident energy at fan MCCs to levels that allowed routine maintenance with standard PPE.
Tower water storage pumps, chemical feed and controls were placed on generator-backed distribution with a defined restart sequence.
Outcome
The county approved the expansion with conditions on water reporting and nighttime noise monitoring. The operator kept a consistent tower design across the campus, and its reported WUE for the expansion improved compared with the original buildings because of the higher cycles of concentration.
Lessons
In a humid climate with adequate water and strict noise limits, towers can be the best answer even for operators under water scrutiny.
Cycles of concentration are a real lever, but evaporation itself cannot be reduced except by rejecting heat another way.
Water storage, chemical feed and controls are part of the critical cooling system and belong on reliable power.


















