Part A — AI Loads and Arc Furnaces at a Glance
Utilities are being asked to connect something they say they have never seen: data center campuses of several hundred megawatts whose demand jumps, dips and pulses as artificial intelligence (AI) training jobs start, synchronize, pause and restart. Interconnection engineers describe the challenge in new language — "large electronic loads," "computational loads," "power swings from synchronized GPU clusters" — and regulators have responded with alerts, task forces and new ride-through requirements.
Yet the grid has met a load like this before. For seventy years, steelmakers have connected electric arc furnaces (EAFs) to transmission systems. An arc furnace draws tens to hundreds of megavolt-amperes through electrodes that strike an arc directly on scrap steel. The arc is violently unstable during melting, so the furnace swings its reactive and active power many times a second, flickers lights across a region, injects harmonics and interharmonics, and in some places has excited torsional vibration in nearby turbine-generator shafts. Utilities, furnace builders and equipment makers solved those problems with a toolbox that is still in service: synchronous condensers, static var compensators, STATCOMs, energy storage, series reactors, power-electronic furnace supplies, planning levels for flicker and contractual rules for who may cause how much disturbance at a point of common coupling (PCC).
This guide is Keentel Engineering's technical treatment of that parallel. It explains what an AI training load does to the grid, what an arc furnace does, where the physics is the same and where it is not, and how the arc-furnace playbook should be rescaled and re-weighted — not copied — for AI campuses. Every example uses US voltage classes (13.8, 34.5, 138, 230 and 345 kV) at 60 Hz, and every number is worked through in Keentel's own calculation files.
Keentel's position. Keentel Engineering is an independent power engineering firm. We perform interconnection, power quality, flicker, harmonic, oscillation, ride-through and EMT studies for data centers, steel mills, utilities and renewable plants from 4 kV to 765 kV. We do not sell compensators, batteries, GPUs or software. Our interest is that large loads are connected safely and that the evidence supports the decision.
Who this guide is for
Key facts at a glance
| Item |
Electric arc furnace |
AI training campus |
|---|---|---|
| Typical size per load |
Tens of MVA to a few hundred MVA per furnace |
Hundreds of MW to several GW per campus |
| Dominant swing |
Reactive power (Mvar), with active power |
Active power (MW) at near-unity power factor |
| Character |
Stochastic, broadband, worst during bore-in and melting |
Structured, periodic steps set by training iterations, checkpoints and job starts |
| Main grid symptom historically |
Lamp flicker (Pst, Plt), harmonics, interharmonics |
MW oscillation, load steps, sudden load loss on voltage dips |
| Classic mitigation |
Synchronous condenser, SVC, STATCOM, series reactor, DC furnace |
Power smoothing in the load, storage, STATCOM for voltage, ride-through settings |
| Governing US references |
IEEE 1453 (flicker), IEEE 519 (harmonics) |
IEEE 1453 and IEEE 519 still apply; large-load requirements from NERC and regions are evolving |
| Notable US event |
Decades of flicker complaints and torsional studies |
About 1,500 MW of data center load dropped offline in Northern Virginia in July 2024 (NERC incident review) |
The core ideas in one table
| Idea |
What it means in practice |
|---|---|
| Same PCC physics |
Any large load that changes its current quickly changes voltage, frequency and generator torque near it. The equations do not care whether the load melts steel or trains a model. |
| Different dominant quantity |
Arc furnaces mainly swing Mvar, which moves voltage. AI campuses mainly swing MW, which moves voltage less but pushes on generators, frequency and electromechanical modes. |
| Different spectrum |
Furnace energy is spread broadly across frequencies. AI training energy is concentrated in narrow lines set by the job's iteration rhythm. A narrow line on top of a lightly damped grid mode is the real risk. |
| Different scale |
A large furnace is a few hundred MVA. A training campus can be several gigawatts — comparable to the largest generating units, whose loss the grid is designed to survive. |
| Self-disconnection |
Data center protection and UPS logic can remove the whole load during a grid fault, by design. A furnace does not do that. |
| Software is the new electrode |
The disturbance source is now programmable. Ramp limits, power floors, staggered checkpoints and synthetic load can tame the fluctuation before it ever reaches the grid. |
| Keep the philosophy, change the metric |
The arc-furnace philosophy — planning levels at the PCC and a fair allocation of emission among users — still fits. The lamp-weighted flicker metric does not. MW-oscillation limits by frequency band are a better fit. |
Fact check: what common summaries get right, and what needs care
Short descriptions of the arc-furnace parallel circulate widely. Their core message is sound. Several points need qualification for US engineering practice.
| Common statement |
Keentel's engineering check |
|---|---|
| "The grid met this load before with arc furnaces." |
Largely true for the physics and the toolbox. Arc furnaces produced fast, large, irregular load swings, harmonics and occasional torsional interaction, and the industry developed proven mitigations. The scale and spectrum of AI campuses differ enough that the playbook must be rescaled, not copied. |
| "Furnace flicker comes chiefly from reactive power swings." |
Correct. At a typical transmission PCC with X/R near 10, reactive swings move voltage roughly ten times more than equal active swings. That is why SVCs and STATCOMs worked so well on furnaces (worked example 3). |
| "AI swings are mostly MW, so a STATCOM can hold voltage but cannot cancel them." |
Correct and important, but it needs one refinement. A STATCOM can hold the PCC voltage almost completely for a modest rating — about 34 Mvar for a 227 MW step in Keentel's example. What it cannot do is stop the MW swing from reaching generators, frequency and electromechanical modes. Only stored energy, generation or load-side shaping can do that. |
| "Synchronized training concentrates energy at specific frequencies." |
Correct. Keentel's synthetic profile puts most of the swing energy in a line at the iteration frequency and its harmonics (worked example 1). Whether that matters depends on how the line lines up with the grid's own lightly damped modes. |
| "A furnace is rated in tens or low hundreds of MVA; an AI campus can reach several gigawatts." |
Correct. One training campus can exceed the largest single contingency some regions plan for. |
| "Customer-side protection removed about 1,500 MW in July 2024." |
Correct per NERC's incident review of the July 2024 event in the Eastern Interconnection. Since then a larger event in Northern Virginia in July 2026 was reported at roughly 3–4 GW, and NERC issued a Level 3 alert on large loads in 2026. |
| "Use Pst screening, IEC 61000-3-7 and IEEE 1453." |
Correct for flicker. In US practice IEEE 1453 is the governing guide; IEC 61000-3-7 is the international method it draws on. Flicker screening alone will badly understate the risk from AI loads, because the lamp-weighted metric barely responds to slow MW pulses (worked example 14). |
| "Utilities already specify oscillation limits over a band of roughly 0.1 to 20 Hz." |
Several large-load requirements and industry reports describe oscillation and fluctuation limits over sub-synchronous bands of that order. Exact bands, metrics and limits vary by region and are still being written; confirm the current requirement with the transmission provider. |
Eight findings for decision makers
Key terms
Part B — The Engineering in Depth
1. What an AI training load actually does
An AI training job runs the same mathematical step over and over. Each step, or iteration, has two broad phases. In the compute phase, every accelerator in the cluster works through its share of the model and its share of the data. In the communication phase, the accelerators exchange and combine their results so that every copy of the model stays identical. Compute draws high power. Communication draws less, because many accelerators are waiting on the network. Because the job is synchronized across the whole cluster, thousands of servers move between the two phases at nearly the same instant.
The result, seen from the substation, is a power trace with a strong rhythm. Iteration periods for large models typically range from a fraction of a second to several seconds, depending on model size, batch size, parallelism strategy and network speed. On top of that rhythm sit slower events:
Cooling, power conversion and building loads add a slower, smoother layer. Chilled-water plants and fans respond over tens of seconds to minutes, so they do not follow the iteration rhythm, but they do follow the larger steps.
Worked example 1 — a synthetic per-server training profile
Keentel built a simple, openly described model so that every later example can be traced. It represents one accelerator server (node) with:
| Parameter |
Value used |
|---|---|
| Idle power |
4.6 kW |
| Compute-phase power |
8.6 kW |
| Communication-phase power |
8.0 kW |
| Iteration period |
2.0 s (0.5 Hz) |
| Fraction of the period in compute (duty) |
70% |
| Start-up idle |
0–12 s |
| Checkpoint pause |
140–152 s |
The average training power per node is:
The swing within an iteration is only 0.6 kW peak to peak, about 7% of training power. A rectangular wave of height ΔP and duty d has a fundamental component of amplitude:
A Fourier transform of the simulated training segment, sampled at 60 samples per second, finds the strongest lines at 0.5 Hz (0.306 kW), 1.0 Hz (0.183 kW), 2.5 Hz (0.076 kW) and 2.0 Hz (0.051 kW) per node. The energy sits in a few narrow lines, not spread across the spectrum. The checkpoint pause is a different kind of event: a step of 8.42 − 4.6 = 3.82 kW per node, more than six times the iteration swing.
These values are illustrative. Real profiles vary by model, framework, accelerator generation and power-management settings, and some measured clusters show iteration swings of tens of percent rather than 7%. The method, not the number, is what transfers to a project.
Worked example 2 — why synchronization matters
If N nodes swing independently, with random phases, their combined amplitude grows only as the square root of N. If they swing together, it grows in direct proportion to N.
| Campus size |
Nodes (at 8.42 kW) |
Coherent 0.5 Hz amplitude |
Incoherent amplitude |
Checkpoint step |
|---|---|---|---|---|
| 100 MW |
11,876 |
3.7 MW |
34 kW |
45 MW |
| 500 MW |
59,382 |
18.4 MW |
75 kW |
227 MW |
For a 100 MW campus, coherence turns a 34 kW ripple into a 3.7 MW oscillation — a factor of about 109, which is √11,876. That is the core reason training loads behave differently from conventional data center loads. Thousands of independent web requests average out. One synchronized training job does not.
Two points follow. First, a campus running many small, unrelated jobs behaves more like the incoherent case; a campus dedicated to one very large job behaves like the coherent case. Second, the checkpoint step, not the iteration ripple, is the largest single MW event in normal operation — 227 MW in seconds for a 500 MW campus in this model.
Figure 1. Synthetic profiles from Keentel's illustrative models: a 100 MVA AC arc furnace over several heats (top) and a 500 MW synchronized training campus with and without a per-node ramp limit (bottom). The furnace trace is stochastic; the training trace is structured.
How Keentel Engineering helps here. Keentel builds a load profile for each campus from the owner's planned workloads, accelerator power data and measured traces where they exist. We separate the iteration rhythm, checkpoint steps, job starts and job ends, and we state which are coherent across the campus. That profile becomes the input to every later study, and it is written so the transmission provider can audit it.
2. What an arc furnace does
An electric arc furnace melts steel scrap with three graphite electrodes (AC furnace) or one electrode and a bottom return (DC furnace). A furnace transformer, typically fed from a 34.5, 69, 138 or 230 kV supply in US practice, steps down to a secondary voltage of several hundred to over a thousand volts. Secondary currents reach tens of kiloamperes.
A heat — one batch of steel — follows a sequence:
From the grid's view, the furnace is a highly variable, low power factor load. During bore-in, the arc can move from near short circuit (electrode touching scrap) to open circuit (arc extinguished) many times per second. The furnace's reactive power swings far more than its active power, because the furnace circuit is dominated by the reactance of the furnace transformer, flexible cables and electrode arms.
The arc's voltage–current characteristic is also strongly nonlinear. It produces harmonics of all orders — even and odd — and interharmonics, especially in the early melting phase. Unbalance between phases is common because each electrode sees a different arc.
Worked example 16 — a synthetic furnace trace
Keentel's synthetic furnace model in Figure 1 draws random power during four "power-on" windows, with a mean of 69.8 MW and a standard deviation of 17.6 MW, clipped between zero and 110 MW. It is not a physical arc model; it is a simple way to show the statistical character of a furnace beside the structured character of a training campus. A real flicker study uses measured furnace data or a validated arc model.
Why the furnace became a reference case
Arc furnaces became the reference case for disturbing loads because they combine every difficult property at once: size, speed, randomness, nonlinearity and unbalance. The flicker meter itself — the instrument that weights voltage fluctuation by how annoying it is to a person watching an incandescent lamp — was developed largely to measure arc-furnace disturbance. Planning levels for flicker, the idea of an emission allocation for each customer at a shared point of common coupling, and the practice of requiring a disturbing customer to pay for its own compensation all grew out of arc-furnace connections.
How Keentel Engineering helps here. For steel mills, Keentel performs flicker, harmonic and unbalance studies using measured furnace data where available, sizes and specifies compensation, and verifies compliance after energization with IEEE 1453 measurements at the PCC.
3. Seventy years of arc-furnace experience: a short history
The parallel between AI loads and arc furnaces is not a loose analogy. Utilities in the United States connected large arc furnaces to transmission systems from the 1950s onward, and the technical literature from that period describes the same symptoms that large-load task forces describe today: rapid load swings, voltage dips felt by other customers, interaction with nearby generators and the need for fast compensation.
The 1950s: synchronous condensers and the first studies
Mid-century papers in the American Institute of Electrical Engineers (AIEE) transactions, including work by C. Concordia and colleagues, examined voltage dips and the response of synchronous machines and synchronous condensers to arc-furnace load swings. The tools of the day were rotating machines. A synchronous condenser raised the short-circuit level at the furnace bus, which reduced the voltage change for a given load swing, and it supplied some reactive power on demand through its excitation system. Its response was limited by machine time constants, so it could not follow the fastest arc fluctuations.
The 1960s and 1970s: the static var compensator
The thyristor made the static var compensator (SVC) possible. A thyristor-controlled reactor in parallel with fixed or switched capacitor banks could change its reactive output within one or two cycles. Some of the earliest industrial SVCs were installed specifically to compensate arc furnaces. Fixed capacitors, usually arranged as harmonic filters tuned near the 2nd, 3rd, 4th or 5th harmonics, supplied steady reactive power and absorbed harmonic currents; the reactor branch varied to cancel the furnace's reactive swings. SVCs typically reduced flicker severity by a factor of about 1.5 to 2, limited by their response time and by the half-cycle granularity of thyristor control.
The 1990s: voltage-source converters arrive
The STATCOM, built from voltage-source converters with turn-off semiconductors, responds faster than an SVC and can control current within a fraction of a cycle. In 1999 a STATCOM was commissioned at a steel plant in Hagfors, Sweden, to compensate an arc furnace; it is widely cited as the first application of the technology to flicker mitigation. Reported flicker reduction factors for STATCOMs on furnaces are in the range of about 3 to 5 or more, depending on control design and the furnace.
Energy storage on the compensator's DC side
Engineers recognized early that a compensator which could exchange active power as well as reactive power would handle the active component of a furnace swing too. Superconducting magnetic energy storage (SMES), battery-backed STATCOMs and supercapacitor-backed compensators were proposed and, in some cases, demonstrated for furnaces and other pulsed industrial loads from the late 1980s through the 2000s. These are the ancestors of today's battery and supercapacitor E-STATCOMs for data centers.
Changing the furnace itself
The other line of development changed the source:
Active-power stabilizers and "watt compensators"
Some installations went further and controlled the furnace's active power swing directly. Thyristor-controlled series reactors acting as active-power stabilizers, and static watt compensators that switch a resistive load bank to fill dips in furnace demand, were used where the active swing disturbed generators or tie-line flows. The principle — burn power deliberately when the process power drops, so the grid sees a steadier load — is exactly what AI campuses now do in software when they hold accelerators at a power floor during communication phases or checkpoints.
Keentel Study Spotlight — learning from the furnace record. Before a large-load study begins, Keentel reviews the disturbance history of the transmission area: existing furnaces, other large industrial loads, compensators already in service and any past flicker or oscillation complaints. Old furnace studies often contain the best available data on local grid damping, resonance and planning levels, and they show which mitigation the utility already trusts.
4. The physics at the PCC: why Mvar and MW behave differently
For a load connected at a bus with Thevenin impedance R + jX behind it, a change in active power ΔP and reactive power ΔQ changes the bus voltage by approximately:
In per unit on a common base this becomes ΔV ≈ R·ΔP + X·ΔQ. On transmission systems X is much larger than R; X/R ratios of 8 to 15 are typical at 138–345 kV. So a megavar moves voltage roughly X/R times as much as a megawatt does.
Worked example 3 — same PCC, two loads
Consider a 230 kV PCC with a three-phase short-circuit level of 5,000 MVA and X/R = 10. On a 100 MVA base:
| Load event |
ΔP |
ΔQ |
ΔV from ΔP |
ΔV from ΔQ |
Total ΔV |
|---|---|---|---|---|---|
| Arc furnace swing |
30 MW |
60 Mvar |
0.06% |
1.19% |
1.25% |
| AI campus checkpoint step |
227 MW |
11 Mvar |
0.45% |
0.22% |
0.67% |
The furnace swing is much smaller in MW yet causes almost twice the voltage change, because it is reactive. The AI step is seven times larger in MW but mostly active, so its voltage effect is smaller — and two-thirds of it comes from the MW component.
The reactive power a compensator must inject to cancel the voltage change completely is:
For the furnace, that is −63 Mvar — more than the furnace's own reactive swing, because the compensator must also offset the small active part. For the AI step, it is only −33.7 Mvar: 22.7 Mvar to offset the active part (227/10) plus 11 Mvar for the reactive part. A STATCOM of a few tens of Mvar can hold the PCC voltage nearly flat during a 227 MW step.
That is the encouraging half of the story. The other half is that the STATCOM has done nothing about the 227 MW itself. The generators still see the step. Their rotor angles and speeds still respond. If the step repeats at a frequency near a grid mode, they still oscillate. Voltage support is necessary for AI loads but it is not sufficient.
Figure 2. Voltage change at the same 230 kV PCC for an arc-furnace swing and an AI campus step, split into the part caused by active power and the part caused by reactive power (Keentel worked example 3).
How Keentel Engineering helps here. Keentel computes the PCC impedance for normal and credible outage conditions, separates the active and reactive parts of the load's disturbance, and sizes voltage support only for what voltage support can fix. The active-power part is carried into the oscillation and frequency studies described below, where it belongs.
5. Flicker screening — and why it is the wrong yardstick for AI loads
Flicker is the human perception of light fluctuation caused by voltage fluctuation. The IEC flickermeter, adopted in the United States through IEEE 1453, weights voltage fluctuation by a lamp-and-eye response that peaks near 8.8 Hz and falls steeply below about 1 Hz and above about 25 Hz. Its outputs are the short-term severity Pst (10 minutes) and long-term severity Plt (2 hours). Pst = 1.0 corresponds to the level at which half of observers find the flicker irritating.
The classic arc-furnace screen
For arc furnaces, planners use a simple screening relationship:
where SscF is the furnace's short-circuit power (the apparent power the furnace draws with its electrodes short-circuited) and Ssc is the short-circuit power at the PCC. Kst is an empirical coefficient, commonly taken in the range 48–85 for AC furnaces, with values around 60 often used for screening. For DC furnaces, a value around two-thirds of the AC value is a common planning assumption.
Worked example 4 — screening a furnace
A furnace with SscF = 200 MVA and Kst = 60:
| PCC short-circuit level |
Uncompensated Pst |
|---|---|
| 2,000 MVA |
6.0 |
| 5,000 MVA |
2.4 |
To meet an illustrative transmission planning level of Pst = 0.8 without compensation would require 60 × 200 / 0.8 = 15,000 MVA at the PCC — rarely available. So the furnace needs mitigation:
| Mitigation at 2,000 MVA |
Assumed reduction factor |
Resulting Pst |
|---|---|---|
| None |
1 |
6.0 |
| 100 MVA synchronous condenser (X″ = 0.15 pu) adds about 667 MVA |
— |
4.5 |
| SVC |
about 2 |
3.0 |
| STATCOM |
about 4 |
1.5 |
The table shows why steel mills moved from synchronous condensers to SVCs and then to STATCOMs, and why even a STATCOM may not be enough at a weak bus. It also shows why many furnace connections were made at 230 kV or above. The reduction factors are illustrative; actual performance depends on the furnace, the control design and the network.
Worked example 15 — a DC furnace
Using Kst = 40 for a DC furnace of the same short-circuit power at the 2,000 MVA bus gives Pst = 40 × 200 / 2,000 = 4.0, a third lower than the AC furnace but still far above planning levels without compensation.
Worked example 14 — why flicker misses AI loads
Now apply flicker logic to an AI campus. For a 100 MW campus, the coherent 0.5 Hz amplitude in worked example 2 is 3.67 MW, or 7.34 MW peak to peak. At the 230 kV, 5,000 MVA, X/R = 10 bus:
At a weaker 138 kV bus with 1,500 MVA and X/R = 6, the same swing gives about 0.080%. Both values are tiny compared with the fluctuation needed to register flicker at 0.5 Hz, where the flickermeter is very insensitive. A flicker study would report the campus as harmless.
But the same 3.67 MW oscillation, if it lands on an inter-area mode with 5% damping, is amplified about tenfold in a single-oscillator approximation — on the order of 37 MW of forced oscillation shared among the generators taking part in that mode (worked example 5). The flicker metric was designed to protect people from lamp flicker. It was never designed to protect generators and power system modes from slow MW forcing. That is the central reason the arc-furnace yardstick must change even where the arc-furnace philosophy still applies.
IEEE 1453 planning levels
IEEE 1453-2022 provides indicative planning levels for flicker at medium, high and extra-high voltage. Values often quoted for high voltage are around Pst 0.8 and Plt 0.6, with medium voltage around Pst 0.9 and Plt 0.7. Utilities set their own planning levels and allocate emission limits to individual customers. Always use the transmission provider's current values. IEC 61000-3-7 describes the international approach to emission allocation for fluctuating loads at MV, HV and EHV, and IEEE 1453 draws on it.
How Keentel Engineering helps here. For AI campuses, Keentel still runs the flicker screen — it is required in many interconnection agreements and it protects neighbors with sensitive lighting and equipment — but we report it beside an MW-oscillation assessment, so no one mistakes a low Pst for a clean bill of health.
6. Spectrum and resonance: when a small swing becomes a large one
Figure 3 compares the spectra of Keentel's synthetic furnace and training campus. The furnace spreads its energy across the whole range from a fraction of a hertz to tens of hertz, with no dominant line. The training campus puts almost all its swing energy into a handful of narrow lines at the iteration frequency and its harmonics.
Figure 3. Where the MW swing energy sits in Keentel's synthetic models, compared with typical power system mode ranges. Shaded bands are indicative; actual mode frequencies are system-specific.
A broadband source excites every mode a little. A narrowband source excites the modes near its lines a lot and the rest hardly at all. Whether a training campus is a problem therefore depends on alignment: does any of its lines fall near a lightly damped mode of the power system?
Worked example 5 — resonance gain
For a lightly damped mode with natural frequency fn and damping ratio ζ, a sinusoidal forcing at frequency f is amplified by approximately:
At resonance (r = 1), G = 1/(2ζ).
| Damping ratio ζ |
Gain at resonance |
|---|---|
| 2% |
25 |
| 5% |
10 |
| 10% |
5 |
| Forcing frequency (ζ = 5%) |
Gain |
|---|---|
| At the mode (r = 1.0) |
10.0 |
| 10% below the mode (r = 0.9) |
4.8 |
| Half the mode frequency (r = 0.5) |
1.3 |
Many utilities treat 3–5% damping as the minimum acceptable for electromechanical modes. A campus line sitting on a mode at that damping is amplified five to ten times. Move the line 10% away and the gain halves; move it to half the mode frequency and resonance hardly matters.
This simple model treats the power system as a single oscillator. Real systems have many modes, and the response at a given generator depends on its participation in each mode and its electrical distance from the campus. The point stands: a narrowband forcing source is dangerous only near a weakly damped mode, and the danger is multiplied by the inverse of the damping.
Forced oscillation is not instability
A forced oscillation is different from an unstable mode. The power system can be perfectly stable — every mode damped — and still oscillate continuously because something keeps pushing it. The fix is to remove or reduce the push, or to move it away from the mode, not to retune generator stabilizers. Forced oscillations from malfunctioning plant controllers, steam valves and wind turbine controls have been recorded across the US interconnections, sometimes travelling across hundreds of miles. A synchronized training campus is a forcing source by design.
How Keentel Engineering helps here. Keentel identifies the electromechanical modes near a proposed campus from small-signal studies, from synchrophasor ringdown analysis where the transmission provider shares data, and from earlier oscillation events. We map the campus's expected forcing lines against those modes and their damping, and we report the gain at each line — so the owner knows which workloads matter and which do not.
7. Torsional interaction with turbine-generators
Large steam and combustion turbine-generators have shafts that can twist at mechanical natural frequencies, typically from about 5 Hz to roughly 45 Hz for the lower modes, with very light mechanical damping — often a fraction of a percent. Any electrical disturbance that pushes on the generator's air-gap torque at a torsional frequency can excite these modes. Series capacitors, HVDC converters, poorly tuned power electronics and, historically, arc furnaces have all been examined for torsional interaction.
Arc furnaces became a concern because their broadband swings contain energy at torsional frequencies, and because a few US steel mills sat electrically close to large thermal units. Studies from the arc-furnace era established the practice of screening torsional exposure whenever a large fluctuating load connects near a thermal plant.
Worked example 6 — torsional gain and the forcing available
With the same resonance formula, a torsional mode with 0.1% damping has a gain at resonance of 1/(2 × 0.001) = 500; with 0.5% damping, 100. That is why even small forcing near a torsional mode can matter over long periods, through shaft fatigue rather than immediate failure.
How much forcing does a training campus produce at a torsional frequency? In Keentel's idealized rectangular profile, the 32nd harmonic of the 0.5 Hz iteration rhythm falls at 16 Hz with an amplitude of about 0.011 kW per node. For a 500 MW campus of 59,382 coherent nodes that is about 0.68 MW. Real power-supply and accelerator electronics round the edges of the steps, so real high-frequency content is usually lower than the idealized wave suggests — but faster iteration rhythms, sharper power-management transitions or interaction with converter controls can push it higher. The only reliable answer comes from measured power at high time resolution and a torsional screening study with the actual generator data.
What to screen
How Keentel Engineering helps here. Keentel performs torsional interaction screening for large loads near thermal plants: unit interaction factor screening, frequency scans and, where needed, detailed EMT studies with multi-mass shaft models. We coordinate with generator owners so that data stays confidential and results are actionable on both sides.
8. Load loss: the risk arc furnaces never posed
An arc furnace that sees a voltage dip keeps drawing current; at worst its arcs extinguish briefly and re-strike. It does not deliberately disconnect itself from the grid. A data center does exactly that. Its uninterruptible power supply (UPS) systems are designed to protect the servers from any grid disturbance outside a tolerance window. When the grid voltage dips below the UPS threshold, the UPS transfers the critical load to batteries, and in many designs the facility also starts its standby generators and opens its utility breakers. From the grid's point of view, the load vanishes in a few cycles.
The 2024 Eastern Interconnection event
In July 2024, a fault on a 230 kV transmission line in Northern Virginia was cleared normally, but a sequence of automatic reclosing attempts produced repeated voltage dips. Data center facilities in the area responded by transferring to backup power, and roughly 1,500 MW of load disconnected from the grid. NERC's incident review documented the event and identified the main issues: the load-loss behavior was not represented in planning models, the facilities did not return to grid power promptly or in a coordinated way, and the grid operator had to manage the resulting overfrequency and high voltage. No customer lost service; the data centers ran on their own backup.
Reports in 2026 described a larger event in Northern Virginia in July 2026 with roughly 3–4 GW of data center load lost during a transmission disturbance. NERC issued a Level 2 alert on large loads in 2025 and a Level 3 alert, with essential actions, in May 2026. Treat event magnitudes for the 2026 event as reported values pending NERC's final analysis.
Worked example 8 — frequency after a large load loss
When load disappears, generation briefly exceeds demand and frequency rises. Two first-order quantities describe the event:
where β is the interconnection's frequency response (MW per 0.1 Hz), H the aggregate inertia constant and S the online generation rating.
| Illustrative case |
Load lost |
β (MW/0.1 Hz) |
H (s) |
S (GVA) |
Settling frequency rise |
Initial RoCoF |
|---|---|---|---|---|---|---|
| Large eastern interconnection |
1,500 MW |
2,500 |
4.0 |
700 |
0.060 Hz |
0.016 Hz/s |
| Smaller interconnection |
3,000 MW |
900 |
4.5 |
90 |
0.333 Hz |
0.222 Hz/s |
In a very large interconnection, 1,500 MW is manageable for frequency; the bigger local issues are overvoltage as lightly loaded lines release reactive power and the operational burden of reconnecting the load. In a smaller interconnection, 3,000 MW of sudden load loss is comparable to the largest generation contingencies the system is designed for, but in the opposite direction, and it can drive frequency high enough to trip generation protection if unchecked. All values are illustrative; actual frequency response varies by season, hour and dispatch.
Worked example 9 — how often the trigger happens
Load loss is triggered by voltage dips, and voltage dips are triggered mostly by transmission faults. A rough exposure estimate:
| Item |
Value |
|---|---|
| Fault rate (illustrative, all fault types) |
1.5 per 100 mi-yr |
| Line-miles electrically close enough to cause a deep dip |
300 mi |
| Expected faults per year |
4.5 |
| Clearing time |
Duration at 60 Hz |
|---|---|
| 5 cycles (fast primary protection) |
83 ms |
| 15 cycles (slower primary or zone 2) |
250 ms |
| 30 cycles (breaker failure, remote backup) |
500 ms |
So a campus in a meshed transmission area can expect several deep dips each year, most cleared within about 100 ms. If the facility's ride-through settings trip on any dip deeper than, say, 30% for longer than two cycles, the campus will drop off the grid several times a year. A furnace operator might not even notice those dips.
Keentel Study Spotlight — load-loss and ride-through study. Keentel models the campus as the grid sees it: UPS transfer thresholds and timers, protective relay settings at the substation, standby generator starts, mechanical load response and the reconnection sequence. We simulate the faults the transmission provider requires, report how much load is lost and when it returns, and recommend settings that keep the campus connected for normally cleared faults while still protecting the critical load.
9. Ride-through design for AI campuses
The arc-furnace era never needed a ride-through standard for loads. Large-load requirements now being written by US transmission providers and reliability organizations do. Common elements include:
Where load loss comes from inside the facility
| Element |
Why it trips |
What to change |
|---|---|---|
| UPS input voltage window |
Narrow tolerance window protects downstream equipment |
Widen the window to what the rectifier and batteries can actually tolerate; add time delay |
| UPS transfer and retransfer logic |
Transfer on any disturbance; slow or uncoordinated return |
Ride through short dips on the input; coordinate retransfer with the utility; ramp the return |
| Medium-voltage protection |
Undervoltage relays set tight for equipment protection |
Coordinate pickup and delay with transmission clearing times |
| Automatic transfer schemes |
Transfer to generators on first dip |
Add delay and require sustained loss before transfer |
| Mechanical systems |
Chillers, pumps and fans trip on dips and restart slowly |
Use ride-through-capable drives and staggered restarts |
| Power supplies in servers |
Hold-up time of a few cycles |
Rely on UPS for longer events; confirm hold-up in specifications |
The ITIC (CBEMA) curve, which describes the voltage tolerance expected of information technology equipment, remains a useful reference for the downstream equipment, but it says nothing about how the facility should behave toward the grid. The facility's grid-facing ride-through is now a design requirement in its own right.
Ride-through has to match protection clearing
Worked example 9 shows that normal clearing times range from about 83 ms to 250 ms, with backup clearing up to 500 ms. A ride-through envelope that holds through 150 ms at 0% retained voltage, and longer at partial voltage, covers most normally cleared faults. Reclosing sequences — the trigger in the 2024 event — need special attention: each reclose onto a persistent fault creates a new dip, so the facility logic must tolerate repeated dips within seconds.
How Keentel Engineering helps here. Keentel reviews every element in the chain from the transmission relay to the server power supply, finds the settings that cause unnecessary load loss and recommends changes that meet the transmission provider's ride-through requirement while protecting the facility. We document the result in a form the utility can use in its planning models.
10. Harmonics: one place where the load improved
Arc furnaces are notorious harmonic sources: even and odd harmonics, interharmonics and unbalance, worst during bore-in. Early data centers with six-pulse UPS rectifiers were significant harmonic sources too. Modern large data centers are usually much cleaner, because UPS systems and server power supplies use active front ends with power-factor correction.
IEEE 519-2022 sets current distortion limits at the PCC in terms of total demand distortion (TDD), scaled by the ratio of short-circuit current to maximum demand current, and voltage distortion limits by voltage level.
Worked example 10 — TDD by front-end type
Using illustrative harmonic current spectra at full load:
| Front end |
Main harmonic currents (% of rated) |
TDD |
|---|---|---|
| 6-pulse rectifier |
5th 20, 7th 14, 11th 9, 13th 7, 17th 5, 19th 4 |
27.7% |
| 12-pulse rectifier |
11th 9, 13th 7, 23rd 4, 25th 3.5 |
12.6% |
| Active front end |
5th 1.5, 7th 1.0, 11th 0.8, 13th 0.6, high-frequency 1.5 |
2.5% |
At transmission voltages, IEEE 519 TDD limits are typically a few percent, depending on the short-circuit ratio. A modern campus with active front ends usually meets them comfortably at the fundamental level, but three cautions apply:
Interharmonics are worth a note. AI training's power fluctuation at a fraction of a hertz modulates the fundamental current and produces sidebands very close to 60 Hz — sub-synchronous and super-synchronous components. Those are the same quantities that oscillation-band limits address, seen from the harmonic side.
How Keentel Engineering helps here. Keentel performs IEEE 519 harmonic studies, frequency scans and filter designs for data centers and industrial plants, including supraharmonic assessment and resonance checks on large campus cable networks.
11. The toolbox, translated
Every major arc-furnace mitigation has an AI-campus equivalent. Some transfer almost unchanged; others change role because the dominant quantity has moved from Mvar to MW.
Figure 4. Keentel's map from arc-furnace era tools to their AI-campus equivalents.
| Arc-furnace tool |
What it did for furnaces |
AI-campus equivalent |
Role change |
|---|---|---|---|
| Synchronous condenser |
Raised fault level, supplied Mvar, added inertia |
Synchronous condenser at the campus or nearby |
Now valued more for inertia and fault level than for Mvar |
| SVC |
Cancelled Mvar swings within cycles |
SVC or STATCOM for voltage control |
Still needed, but sized for a smaller ΔQ |
| STATCOM |
Faster Mvar cancellation, higher flicker reduction |
STATCOM with power oscillation control |
Voltage role continues; cannot address MW |
| SMES, battery or supercap compensator |
Active and reactive compensation |
E-STATCOM, BESS, supercapacitor buffer |
Becomes the main hardware answer to MW swings |
| DC furnace, converter-fed furnace |
Decoupled the arc from the grid |
Rectifier front ends, MV-UPS, DC distribution |
Converter can buffer and shape power if designed to |
| Series reactor, active-power stabilizer |
Limited current and active swings |
Power smoothing, ramp limits in the load |
Moves into software and power management |
| Static watt compensator |
Filled dips with resistive load |
Synthetic load, accelerator power floor |
Same principle, software implementation |
| Electrode regulation, slag practice |
Reduced the violent phase |
Workload scheduling, staggered checkpoints |
The process itself becomes the control |
| Pst planning levels and allocation |
Fair share of flicker headroom |
MW oscillation limits by frequency band |
Same philosophy, different metric |
| Interruptible tariffs |
Curtailed furnaces at peak |
Flexible or curtailable service |
Larger scale, faster response possible |
The most important change is in the last four rows. For furnaces, the process was largely fixed and the grid or a compensator absorbed its variability. For AI campuses, the process is software. The cheapest and most effective controls often live in the scheduler, the training framework and the accelerator power-management firmware.
How Keentel Engineering helps here. Keentel compares mitigation options on equal terms — software shaping, storage, compensators, condensers and network reinforcement — with cost, performance and verification for each, so owners do not buy hardware for a problem software can solve, or rely on software for a problem only hardware can solve.
12. Shaping the load at its source
Because the disturbance comes from software, it can be shaped in software. The main techniques are:
Worked example 11 — ramp limits and a power floor
Keentel applied a per-node ramp limit to the synthetic profile and measured the 0.5 Hz line again:
| Ramp limit per node |
0.5 Hz line |
Reduction from 0.306 kW |
|---|---|---|
| 2.0 kW/s |
0.283 kW |
8% |
| 0.5 kW/s |
0.125 kW |
59% |
| 0.2 kW/s |
0.050 kW |
84% |
A ramp limit works by preventing the node from completing its swing within each phase. At 0.5 kW/s, the node cannot fully rise from 8.0 to 8.6 kW during the 0.6 s communication phase, so the swing shrinks. Ramp limiting also softens the checkpoint step: at 0.5 kW/s per node, the 3.82 kW checkpoint drop takes about 7.6 s instead of a fraction of a second.
A power floor works differently. Raising the communication-phase power from 8.0 to 8.4 kW cuts the swing to 0.2 kW and the 0.5 Hz line to 0.102 kW — a two-thirds reduction — at the cost of 1.43% more energy for the node. For a 500 MW campus, that is about 7 MW of continuous extra consumption, so floors are a tool to apply when and where the oscillation risk justifies the cost.
There is a performance trade-off. Ramp limits that slow accelerators during compute phases can lengthen each iteration. Whether that matters depends on how close to power-limited the accelerators are. The owner's compute team, not the electrical engineer, has to confirm the trade-off — which is why load shaping must be agreed early, not imposed after a problem appears.
Who controls the shaping?
Load shaping is only useful if it is reliable. A transmission provider cannot plan around a setting that the next software release might change. Good practice is to:
Keentel Study Spotlight — load-shaping specification. Keentel translates the transmission provider's oscillation and ramp requirements into a load-shaping specification the owner's compute and facilities teams can implement: limits per node and per hall, checkpoint staggering rules, burn sequences on job end, and the monitoring that proves the limits are met.
13. Storage and E-STATCOMs: sized for power, not energy
The arc-furnace era showed that active-power compensation needs stored energy. AI campuses confirm it: the MW swing must come from somewhere, and if not from the generators it must come from a buffer.
Worked example 7 — how much energy does a swing need?
To absorb a sinusoidal swing of amplitude ΔP at frequency f, the buffer charges for one half cycle and discharges for the next. The energy moved in one half cycle is:
For ΔP = 50 MW at 0.5 Hz:
| Quantity |
Value |
|---|---|
| Energy per half cycle |
31.8 MJ = 8.84 kWh |
| Half cycles per day |
86,400 |
| Full cycles per day |
43,200 |
| Depth of discharge per half cycle on a 50 MW / 12.5 MWh battery |
0.071% |
The energy is small; the power and the cycle count are large. A battery sized for 50 MW will handle the swing with tiny depth of discharge, but tens of thousands of shallow cycles per day must be checked against the cell chemistry's cycle-life data and thermal limits. Supercapacitors and flywheels handle very high cycle counts well and are often a better fit for the fastest swings.
Checkpoints are a bigger energy problem. Bridging a 227 MW checkpoint pause of 12 s takes 227 × 12 / 3,600 = 0.757 MWh. Ramping the campus back over 30 s, with the buffer covering the difference, takes 0.946 MWh. Both are within the range of a modest battery, but they require hundreds of megawatts of power capability — almost as much as the campus itself. That is why staggering and ramp limits, which shrink the step in software, are usually combined with storage rather than replaced by it.
E-STATCOM versus separate BESS and STATCOM
An E-STATCOM shares one converter between voltage control and active-power buffering. A separate battery and STATCOM can be optimized independently. The choice depends on rating, footprint, redundancy and the interconnection requirement. Either way, the converter controls must be studied for interaction with the grid, with campus UPS converters and with nearby inverter-based resources.
UPS batteries as a buffer
Data centers already contain large amounts of stored energy in their UPS batteries. Medium-voltage UPS designs and grid-interactive UPS controls can, in principle, use that energy to smooth campus power. Doing so must not reduce the backup time below what the critical load requires, and battery life must be checked for the added cycling. This is the data center equivalent of using the furnace's own converter to buffer its arc.
How Keentel Engineering helps here. Keentel sizes storage and E-STATCOMs for power, energy and cycle life together, using the campus load profile and the required reduction in each oscillation band. We perform the EMT studies that show the buffer's controls are stable alongside UPS converters and the grid.
14. Series devices, active-power stabilizers and grid reinforcement
Some arc-furnace installations used thyristor-controlled series reactors to stabilize furnace active power, typically achieving a reduction in the swing of around 3:1.
Worked example 13 — a 3:1 stabilizer
Applying a 3:1 reduction to the 227 MW checkpoint step leaves 227 / 3 ≈ 76 MW. That is a meaningful improvement, but series devices carry the full campus current continuously, add losses and need careful protection. For AI campuses, the same reduction is usually cheaper to achieve through load shaping and storage.
Network reinforcement is the other traditional lever. Raising the short-circuit level at the PCC reduces voltage effects in proportion. It does nothing for the MW swing reaching generators — the generators still supply the same MW — but it can increase the damping of local modes and reduce the electrical distance to the generators that absorb the swing. Synchronous condensers add inertia and fault level, which slows RoCoF after load loss and stiffens the local voltage.
How Keentel Engineering helps here. Keentel evaluates network reinforcement, synchronous condensers and series devices alongside storage and load shaping, using short-circuit, dynamic and EMT studies, and reports the cost per MW of oscillation reduction for each option.
15. Flexibility: the interruptible furnace becomes the flexible campus
Utilities have long offered steel mills interruptible or curtailable tariffs: lower rates in exchange for the right to curtail the furnace at system peaks. AI campuses can offer the same, and in some cases more, because training jobs can pause and resume, and workloads can sometimes move between sites.
Worked example 12 — the value of flexibility
A 300 MW campus that can reliably curtail 20% (60 MW) on request, valued at an illustrative $150 per MW-day of capacity, earns:
The actual value depends entirely on the market and the tariff; capacity prices vary widely by region and year. More important than revenue, flexible service is increasingly a path to faster interconnection: transmission providers can connect a campus before network upgrades are complete if the campus agrees to curtail under defined conditions.
Flexibility and oscillation control interact. A campus that curtails by stopping jobs abruptly creates exactly the step the grid least wants. Curtailment must be ramped, and the ramp must be coordinated with the transmission operator.
How Keentel Engineering helps here. Keentel models flexible-service arrangements in planning studies, defines the curtailment ramps and conditions that keep the grid secure, and supports owners in negotiating terms the facility can actually meet.
16. The US requirements landscape
Requirements for large loads in the United States are developing quickly. The following summary reflects public documents available in late 2026; confirm the current status of each before relying on it.
| Body |
Item |
What it addresses |
|---|---|---|
| NERC |
Large Loads Task Force (LLTF) |
Characteristics, risks, modeling and possible standards for large loads |
| NERC |
White paper: Characteristics and Risks of Emerging Large Loads (2025) |
Load behavior, ride-through, oscillation, modeling gaps |
| NERC |
Incident Review: Large Load Loss (2024 event) |
About 1,500 MW of data center load lost after a 230 kV fault and reclosing |
| NERC |
Level 2 alert on large loads (2025) |
Recommendations on modeling, ride-through and data |
| NERC |
Level 3 alert on large loads (May 2026) |
Essential actions for registered entities on large-load risks |
| ERCOT |
NOGRR 282 |
Ride-through requirements for large electronic loads |
| ERCOT |
Large-load interconnection process and Q&A |
Study process and data requirements |
| ERCOT |
Board update on interconnection and grid analysis (September 2026) |
Discussion of rapid load fluctuations |
| MISO |
Large Load Working Group materials (April 2026) |
Proposed large-load interconnection reliability requirements |
| ESIG |
Large loads performance requirements report (2026) |
Recommended performance requirements and metrics |
| GridLab |
Large loads interim report (2025) |
Policy and technical options for large loads |
| IEEE |
IEEE 1453-2022 |
Flicker measurement and limits |
| IEEE |
IEEE 519-2022 |
Harmonic limits |
Common themes across these documents:
Utilities and regions differ on thresholds (the size above which a load is "large"), on band definitions and on how strictly requirements apply to existing facilities. Several also distinguish between computational loads and other large loads such as cryptocurrency mining, hydrogen electrolysis and industrial process loads.
How Keentel Engineering helps here. Keentel tracks NERC and regional large-load requirements and maps each requirement to the facility design element that meets it, so owners know which settings, equipment and documents each transmission provider will expect.
17. A better yardstick: MW oscillation limits by frequency band
If the lamp-weighted flicker metric is the wrong yardstick for AI campuses, what replaces it? Keentel's view is that the arc-furnace framework survives intact and only the weighting changes:
Illustrative band structure
| Band |
Typical concern |
Example limit form |
|---|---|---|
| Below 0.1 Hz |
Governor response, area control error, tie-line flows |
Ramp rate in MW/min |
| 0.1–1 Hz |
Inter-area and plant control modes |
MW amplitude limit, tighter near known modes |
| 1–3 Hz |
Local electromechanical modes |
MW amplitude limit |
| 3–20 Hz or wider |
Control interaction, torsional exposure near thermal units |
Amplitude limit or screening requirement |
These bands are illustrative. Transmission providers are still defining them, and several published requirements use different splits and metrics, such as limits expressed as a percentage of facility rating.
Worked example 14, revisited
The 100 MW campus's 3.67 MW line at 0.5 Hz is 3.7% of its rating. If the provider sets a limit of 1% of rating in the 0.1–1 Hz band, the campus needs a reduction of about 73%. The ramp limit of 0.5 kW/s per node (59%) is not enough alone; the 0.2 kW/s limit (84%) or a combination of a moderate ramp limit with a power floor would meet it. That is the kind of calculation that turns a requirement into a design.
How Keentel Engineering helps here. Keentel helps transmission providers develop practical band limits and allocation methods from their own mode data, and helps owners demonstrate compliance with them.
18. The study workflow for an AI campus
The arc-furnace study sequence — screen, model, mitigate, verify — carries over with additions:
1. Data collection. Campus size, phasing, workloads, accelerator generations, UPS and protection design, planned interconnection point and the transmission provider's requirements.
2. Load characterization. Build the campus profile (section 1): iteration lines, checkpoint steps, job starts and ends, coherence assumptions and cooling response.
3. Steady-state and short-circuit studies. Load flow, contingency analysis, short-circuit levels at the PCC under normal and outage conditions.
4. Voltage and flicker screening. ΔV for steps, flicker screening per IEEE 1453 and the transmission provider's planning levels.
5. Mode survey. Identify electromechanical modes, their frequencies, damping and participation near the campus.
6. Forced-oscillation assessment. Map campus lines to modes, compute response at key generators and lines, compare with limits.
7. Torsional screening. Where thermal units are electrically close.
8. Ride-through and load-loss studies. Dynamic simulation of required faults with UPS, protection and generator logic.
9. Harmonic studies. IEEE 519 compliance, resonance and supraharmonics.
10. EMT studies. Where converter controls, weak grids or nearby inverter-based resources make phasor studies insufficient.
11. Mitigation design. Load shaping, storage, compensators, reinforcement; repeat affected studies.
12. Commissioning and verification. Tests and monitoring that prove the campus behaves as modeled.
Keentel Study Spotlight — large-load interconnection study package. Keentel delivers the full sequence above as a single, consistent package, with one campus model used across steady-state, dynamic, EMT and harmonic studies, and a mitigation report that shows how each requirement is met.
19. Modeling large computational loads
Planning models traditionally represent load as a static or composite load model at a bus. That cannot represent a data center's UPS transfer logic, protection, cooling plant response or programmed power shaping. Better practice is to:
Several model structures for computational loads have been proposed by industry groups and vendors. Whatever structure is used, the important thing is that the parameters come from the actual facility design and are updated when settings change.
How Keentel Engineering helps here. Keentel builds facility dynamic models from UPS, protection and cooling design data, tunes them against test results, and delivers them in the formats transmission providers require, with documentation that survives audit.
20. Monitoring and verification
Arc-furnace compliance was verified with flickermeters at the PCC. AI-campus compliance needs more:
How Keentel Engineering helps here. Keentel specifies monitoring systems, develops commissioning test plans, and analyzes recorded data to confirm compliance and update models.
21. Sharing a PCC: steel mills and data centers together
Some data center campuses are being sited near existing steel mills, attracted by the same strong transmission infrastructure. Two disturbing loads at one PCC raise new questions:
How Keentel Engineering helps here. Keentel studies combined loads at shared PCCs, allocates headroom fairly, and designs compensation and settings that keep both facilities compliant.
22. Inside the facility: where the power swing is born and where it can be stopped
It helps to follow the power path from the accelerator back to the PCC, because every stage is a place where the swing can be passed through, amplified, filtered or absorbed.
| Stage |
Typical US arrangement |
Effect on the swing |
Opportunity |
|---|---|---|---|
| Accelerator and board power |
Point-of-load converters on the server board |
Generates the swing; edges set by power-management firmware |
Ramp limits, power floors, frequency avoidance |
| Server power supply |
AC-DC or DC-DC supply in each server or rack shelf |
Small hold-up capacitance; passes the swing almost unchanged |
Little; hold-up covers only a few cycles |
| Rack and row distribution |
Busway, 415/240 V AC or DC distribution at rack level |
Passes the swing |
Rack-level energy storage in some designs |
| UPS |
Low-voltage or medium-voltage double-conversion or line-interactive UPS |
Passes the swing in normal mode unless controlled to smooth it |
Grid-interactive UPS control; battery buffering within backup limits |
| Medium-voltage distribution |
13.8 kV or 34.5 kV switchgear and cables |
Passes the swing; cable capacitance affects harmonics |
Location for STATCOM or BESS connection |
| Main power transformers |
230/34.5 kV or 345/34.5 kV |
Passes the swing; adds reactive losses that grow with load |
Little |
| Campus-level storage or compensator |
BESS, E-STATCOM, supercapacitor bank at 34.5 kV or the high-voltage bus |
Absorbs MW swings, controls voltage |
The main hardware option |
| PCC |
138, 230 or 345 kV |
Where limits are measured |
Monitoring and verification |
Two observations come from this table. First, nothing between the accelerator and the PCC naturally smooths the swing. Unlike a furnace, whose flexible cables and furnace transformer at least add impedance to the arc circuit, a data center's power path is designed to deliver clean, stiff power to the servers. Every element passes the server's demand straight to the grid. Second, there are only three places to stop it: at the source (in firmware), in the UPS (with grid-interactive control) or with dedicated storage at the campus bus. A robust design usually uses at least two of them, so that the campus still meets its limits when one is unavailable.
Cooling: the slow layer
Cooling systems — chillers, cooling towers, pumps, computer-room air handlers and, increasingly, liquid-cooling distribution units — add a slower layer to the profile. They follow the IT load with delays of tens of seconds to minutes, governed by thermal inertia and control loops. For oscillation in the 0.1–3 Hz bands, cooling is effectively constant. For checkpoint steps and job ends, cooling lags: when the IT load drops, cooling continues at high power for a while, then ramps down, which slightly softens the step seen by the grid. For ride-through, cooling is often the weak point, as case study 3 shows, because drives and compressors may trip on dips and restart slowly.
How Keentel Engineering helps here. Keentel reviews the full power path inside the facility, from accelerator power management to the main transformers, and identifies where the swing can be shaped most cheaply and reliably — and where a second layer of control is needed as a backstop.
23. Lessons from the arc-furnace era that still apply
Seventy years of furnace connections left behind lessons that are not written in any single standard but are part of utility practice. Most apply directly to AI campuses.
Keentel Study Spotlight — baseline and attribution survey. Before a large load connects, Keentel installs or reviews high-resolution monitoring at the proposed PCC and nearby buses to record background voltage fluctuation, harmonics and MW oscillation. The baseline makes later compliance assessment fair to the new customer and to everyone already connected.
24. The economics of mitigation
Engineering decisions about large-load mitigation are ultimately economic decisions under technical constraints. The relative cost of each option is a useful first guide, though actual costs vary widely by project and market.
| Option |
Typical cost driver |
Strength |
Limitation |
|---|---|---|---|
| Firmware load shaping |
Engineering effort; small throughput or energy penalty |
Cheapest per MW of oscillation reduction; acts at the source |
Depends on software discipline; needs monitoring and a backstop |
| Power floor or synthetic load |
Continuous energy cost (about 1.4% of energy in worked example 11) |
Simple and effective for the iteration line |
Ongoing operating cost; increases cooling load |
| Grid-interactive UPS control |
Controls engineering; battery cycling |
Uses equipment already installed |
Must not reduce backup time; battery life impact |
| Campus BESS or E-STATCOM |
Converter rating (MW) more than energy (MWh) |
Handles all bands and checkpoint steps; independent of software |
Capital cost; cycle-life and thermal checks; control interaction studies |
| STATCOM |
Mvar rating |
Solves voltage problems cheaply |
Does nothing for MW swings |
| Synchronous condenser |
MVA rating, civil works, maintenance |
Adds inertia and fault level |
Does not absorb sustained MW swings |
| Network reinforcement |
Lines, transformers, substations |
Raises short-circuit level; may improve damping |
Long lead times; may not fix forced oscillation |
| Flexible service |
Revenue or rate effect; operational constraints |
Can speed interconnection |
Requires reliable, ramped curtailment |
The pattern in Keentel's studies is consistent: software shaping first, storage second, voltage support as required, reinforcement where the network needs it anyway. The order mirrors the furnace experience — process improvement, then fast compensation, then reinforcement — with the important difference that the AI campus's process improvement can be implemented in weeks rather than years.
A simple cost-per-reduction comparison
For a 300 MW campus with a 10 MW line at 0.5 Hz and a limit of 3 MW:
The combination of shaping and a modest buffer is usually the least-cost design that also stays compliant when one layer is unavailable — which is what case study 1 found.
How Keentel Engineering helps here. Keentel presents mitigation options with technical performance and a cost basis side by side, so owners and transmission providers can agree on the least-cost design that meets the requirement and survives equipment outages.
25. Questions to ask at each project stage
| Stage |
Questions for the owner |
Questions for the transmission provider |
|---|---|---|
| Site selection |
How large will the campus grow? Will it run one large job or many small ones? |
What is the short-circuit level under outages? Are there known lightly damped modes or thermal units nearby? |
| Interconnection request |
What load profile, ride-through settings and models can we provide now? |
Which large-load requirements apply, and which version? |
| System impact study |
Is the profile realistic for the hardware we will buy? |
Which bands and limits will be enforced? Is a combined study needed with other large loads? |
| Facility design |
Where will shaping live? Which UPS and protection settings meet ride-through? |
Will the provider accept firmware shaping as a compliance measure? What monitoring is required? |
| Procurement |
Can the UPS, drives and storage meet the ride-through envelope and cycle life? |
What model formats and test evidence are needed? |
| Commissioning |
Which tests will prove shaping, ride-through and storage response? |
What data must be submitted and when? |
| Operation |
What changes in workload, firmware or hardware trigger a review? |
How will exceptions be reported and handled? |
How Keentel Engineering helps here. Keentel supports owners and transmission providers at every stage, from site screening to operational compliance, so that each question is answered before it becomes a delay.
26. Operating the grid with large computational loads
Planning studies decide whether a campus can connect. Operations decide whether it runs safely day to day. The arc-furnace era offers a template here too: large furnaces were often scheduled in coordination with the utility, especially during system emergencies or when compensators were out of service. AI campuses need a similar but faster operating relationship.
Information the transmission operator needs
Coordinated return from backup power
One of the clearest lessons of the 2024 event is that reconnection matters as much as disconnection. A campus that returns hundreds of megawatts to the grid in one step after a disturbance creates a second disturbance. Good practice is an automatic, ramped return — for example over several minutes — that the transmission operator can pause or delay, with staggered return of halls or buildings.
Operating limits during outages
When a critical transmission element is out, or when a mitigation device is unavailable, the campus may need to operate within reduced limits: stricter ramp rates, staggered jobs, a lower maximum demand or a commitment not to start new large jobs. These limits should be agreed in advance and written into operating procedures, so that they can be applied quickly without negotiation.
Event analysis
Every large-load event — a transfer to backup, an oscillation alarm, a ride-through failure — should be analyzed jointly by the owner and the transmission operator, using recorded data from both sides. The findings feed model updates and setting changes. This is the same cycle that steel mills and utilities followed for furnace flicker complaints, carried out at a larger scale and higher speed.
Worked example 8, revisited — reserves for load loss
If a transmission operator must carry a load-loss contingency for a campus that might drop off on a fault, it must keep generation able to reduce output quickly by that amount, or accept the resulting overfrequency. For a 500 MW campus, that is a 500 MW downward-reserve obligation in the area, with associated cost and operating constraints. When ride-through settings remove the load-loss risk for normally cleared faults, as in case study 3, the contingency can be reduced or removed. Ride-through is not just a reliability improvement; it frees operating margin.
Keentel Study Spotlight — operating procedures for large loads. Keentel helps owners and transmission operators write the operating procedures that turn study results into daily practice: data exchange, notice of large changes, ramped return from backup, reduced-capability limits and joint event analysis.
27. Ten common mistakes
1. Treating an AI campus as a constant load in planning studies.
2. Relying on flicker screening alone and concluding the campus is benign.
3. Sizing a STATCOM and assuming it solves the oscillation problem.
4. Ignoring coherence and estimating swings from random aggregation.
5. Overlooking checkpoint steps and job-end drops.
6. Setting UPS input windows tightly without considering transmission fault clearing.
7. Implementing load shaping only in job-level software that can change without notice.
8. Sizing storage for energy instead of power and cycle life.
9. Skipping torsional screening near thermal plants.
10. Studying the campus without the actual protection and UPS settings.
28. A checklist for owners and planners
29. Summary of the worked examples
| No. |
Topic |
Key result |
|---|---|---|
| 1 |
Per-node training profile |
8.42 kW average; 0.5 Hz line 0.31 kW |
| 2 |
Coherent aggregation |
100 MW: 3.7 MW coherent vs 34 kW incoherent; 500 MW checkpoint step 227 MW |
| 3 |
ΔV at 230 kV PCC |
Furnace 1.25%; AI step 0.67%; STATCOM 34 Mvar holds AI voltage |
| 4 |
Furnace Pst screening |
Pst 6.0 at 2,000 MVA; STATCOM brings it to 1.5 |
| 5 |
Resonance gain |
10× at 5% damping |
| 6 |
Torsional gain |
100–500× at 0.1–0.5% damping |
| 7 |
Storage sizing |
8.84 kWh per half cycle for ±50 MW at 0.5 Hz |
| 8 |
Frequency after load loss |
0.06 Hz for 1,500 MW large interconnection; 0.33 Hz for 3,000 MW smaller interconnection |
| 9 |
Fault exposure |
4.5 faults/yr; clearing 83–500 ms |
| 10 |
Harmonic TDD |
27.7% 6-pulse; 2.5% active front end |
| 11 |
Load shaping |
Ramp limits cut 0.5 Hz line 8–84%; floor costs 1.43% energy |
| 12 |
Flexibility value |
$3.29 M/yr for 60 MW |
| 13 |
Active-power stabilizer |
227 MW step reduced to 76 MW |
| 14 |
Flicker blindness |
0.015% ΔV at 230 kV for a 3.7 MW line |
| 15 |
DC furnace |
Pst 4.0 |
| 16 |
Synthetic furnace |
Mean 69.8 MW, std 17.6 MW |
Part C — Three Anonymous US Case Studies
The three cases below are composites built from typical project situations. Names, locations, ratings and numbers have been changed, and no case describes a single real project or client. They show how the arc-furnace playbook was adapted, step by step, in situations Keentel engineers see in practice.
Case study 1 — A 300 MW training campus in Texas and a 0.5 Hz line that would not go away
The situation
A developer planned a 300 MW AI training campus in central Texas, connected at a new 230 kV switching station looped into an existing double-circuit line. The campus would house one very large training cluster in its first phase, running a single job at a time for weeks — the most coherent workload pattern possible. The transmission provider's large-load requirements, written under the regional ride-through and fluctuation rules, asked for a dynamic model, a ride-through demonstration and evidence that periodic power fluctuations would stay within stated limits in sub-synchronous bands.
The developer's first submission described the campus as a 300 MW constant-power load with a 0.98 power factor, plus a statement that UPS systems would "ride through all grid events." The transmission provider rejected it and asked for a characterized load profile.
What Keentel found
Keentel's first task was to build a credible profile. The developer's compute team supplied accelerator power data from a pilot cluster running a 70-billion-parameter open model training run. The pilot traces showed an iteration rhythm of about 1.8–2.2 s, depending on batch size, with a swing of about 9% of training power between compute and communication phases, and checkpoints every 20–30 minutes lasting 10–15 s.
Scaled to 300 MW with full coherence, the profile gave:
The short-circuit level at the new switching station was about 4,200 MVA with all lines in service and about 2,600 MVA with one circuit out. Voltage effects were modest: the checkpoint step produced a ΔV of about 0.5% with all lines in service and under 1% with a circuit out. Flicker screening gave Pst well below 0.5. On voltage alone, the campus looked benign.
The mode survey told a different story. Small-signal analysis of the regional model, cross-checked against ringdown analysis of synchrophasor records from earlier generator trips, identified a local mode near 0.55 Hz involving two combined-cycle plants and a group of wind plants about 60 miles away, with damping estimated between 4% and 7% depending on dispatch. The campus's 0.5 Hz line sat within 10% of it.
Using the resonance relationship from worked example 5, with r ≈ 0.91 and ζ = 5%, the gain was about five (5.1). A detailed dynamic simulation, injecting the campus profile as a time series, showed sustained MW oscillation of 30–45 MW peak to peak on the combined-cycle units' outputs, and oscillation on a 345 kV tie that exceeded the provider's monitoring alarm threshold. Under the low-damping dispatch, the response was larger still.
Options considered
Keentel evaluated four approaches:
| Option |
Effect on 0.5 Hz line |
Cost and trade-offs |
|---|---|---|
| STATCOM, 60 Mvar |
Held voltage; no effect on MW line |
Moderate cost; did not address the problem |
| Ramp limit and power floor in facility firmware |
Reduced the line by 65–80% |
Low cost; small throughput penalty; required firmware control at facility level |
| Battery E-STATCOM, 60 MW / 15 MWh |
Reduced the line by about 90% with power-oscillation control; bridged checkpoints |
Higher cost; cycle-life analysis required |
| Change iteration rhythm away from the mode |
Moved the line away; gain fell to about 1.5 |
No hardware cost; constrained the compute team; not guaranteed for future jobs |
The solution
The final design combined two layers:
The combination reduced the 0.5 Hz line at the PCC by about 92% in simulation, and the combined-cycle units' oscillation fell below 4 MW peak to peak under the worst dispatch. The checkpoint step seen by the grid fell from 130 MW to about 25 MW, ramped over 20 s.
Keentel also corrected the ride-through design. The original UPS input window would have transferred the campus to batteries for any dip below 85% lasting more than 20 ms. Coordinated with the transmission protection clearing times, the revised settings held the campus on the grid through faults cleared within the provider's required envelope, with a ramped return after longer events.
Verification
Commissioning included staged tests: training at partial scale with shaping disabled and enabled, a deliberate checkpoint with and without staggering, and an E-STATCOM response test. High-resolution PCC monitoring confirmed the line reduction within a few percent of the study prediction. The transmission provider accepted the campus model and added it to its planning cases.
Lessons
Case study 2 — A Midwest mini-mill and a new data center on one 138 kV substation
The situation
A steel company operated a mini-mill in the Midwest with one 120-ton AC arc furnace and a ladle furnace, connected to a 138 kV substation through a dedicated furnace transformer. The mill had an SVC installed in the 1990s, sized for flicker compensation, and a long record of compliance with the utility's flicker allocation. A data center developer purchased land next to the mill and proposed a 150 MW campus, to be served from a new bay on the same 138 kV substation. The campus would host a mix of training and inference workloads.
The utility's concern was straightforward: two disturbing loads on one bus. It asked for a combined study.
What Keentel found
Keentel began with the mill's history. The utility supplied fifteen years of IEEE 1453 measurements at the PCC: with the SVC in service, the 95th percentile Pst during furnace operation was about 0.65, against a planning level of 0.8. With the SVC out of service — which had happened twice for maintenance — Pst exceeded 1.4. The bus short-circuit level was about 2,800 MVA normally, falling to about 1,900 MVA with one 138 kV source out.
The campus's contribution to flicker was negligible, as worked example 14 predicts. But the study found three real issues:
1. UPS sensitivity to furnace fluctuation. The campus UPS design specified a rectifier input window of ±10% with a fast transfer to battery. Measured furnace-induced voltage fluctuation on the bus, during bore-in with the SVC in service, reached about 2–3% in short bursts, and during an SVC outage about 5%. Those were within the window, but the combination of furnace fluctuation with a transmission fault on the outage configuration could push the bus outside the window more often than either alone.
2. Combined voltage swings at the PCC. Furnace ΔQ and campus checkpoint ΔP added at the bus. At 1,900 MVA, a 60 MW campus step coinciding with a furnace bore-in swing produced combined ΔV of about 2%, above the utility's step-change criterion.
3. Harmonic interaction. The SVC's filter banks, tuned near the 2nd, 3rd and 5th harmonics, interacted with the campus's long medium-voltage cable runs, shifting a parallel resonance closer to the 7th harmonic. Background 7th harmonic voltage on the bus would be amplified.
The solution
The solution worked on both sides of the bus:
Verification
After energization, PCC monitoring showed the mill's Pst unchanged, the campus's MW steps within the agreed ramp, and the 7th harmonic voltage on the bus lower than before the campus was built, because of the added filter. During the following year, two transmission faults on the area network caused dips at the bus; the campus rode through both.
Lessons
Case study 3 — A 500 MW Mid-Atlantic campus and the cost of dropping off
The situation
An owner operated a 500 MW data center campus in the Mid-Atlantic region, connected at 230 kV through two transformers and a ring bus. The campus hosted a mix of training and cloud workloads. After the 2024 load-loss event and the large-load alerts that followed, the transmission provider asked large-load customers in its zone to demonstrate ride-through performance and provide validated dynamic models.
The owner's records showed the campus had transferred to backup power three times in the previous two years, each time following a transmission fault, and each time returning to grid power manually over 30–90 minutes. Each event removed 300–420 MW from the grid within a few cycles.
What Keentel found
Keentel's review traced each transfer to specific settings:
A fault exposure estimate, following worked example 9, suggested about four to five faults per year close enough to produce dips below 80% at the campus, consistent with the observed history.
Keentel built a dynamic model of the campus including UPS logic, relay settings, generator start and the mechanical systems, and validated it against the recorded data from two of the three events. The validated model reproduced the load loss timing within one cycle.
Options considered
The study tested settings and equipment changes against the transmission provider's ride-through envelope:
| Change |
Effect |
|---|---|
| UPS rectifier input: ride through dips to 0% for 150 ms and to 70% for 2 s, using battery support without transfer |
Eliminated rectifier-driven load loss for normally cleared faults |
| MV undervoltage relays: coordinated with clearing times and reclosing intervals; transfer only on sustained loss |
Eliminated relay-driven load loss for reclosing sequences |
| Chiller and pump drives: ride-through-capable drive settings, shorter restart lockouts, staggered restarts |
Kept cooling running through short dips |
| Automatic ramped return: after a transfer, return to grid over 10 minutes in coordination with the transmission operator |
Removed the manual delay and the large reconnection step |
| Synchronous condenser at the campus |
Considered for added fault level and inertia; not selected because ride-through changes solved the problem |
The solution
The owner implemented the settings changes in stages over six months, with Keentel reviewing each change before it went live and confirming with the equipment manufacturers that the revised windows were within equipment capability. A small number of older UPS modules could not support the wider window and were scheduled for replacement.
The revised campus model was submitted to the transmission provider and accepted. In the provider's planning cases, the campus now remained connected for all normally cleared faults in the required set, and the load-loss contingency the provider had been carrying for the campus was removed from its operating studies.
Verification
In the year after the changes, two transmission faults produced dips at the campus. The campus stayed on grid power through both, with no UPS transfers and no generator starts. Recorded PCC data confirmed the model's prediction of the campus's power during and after the dips.