Case Study 1: Dynamic Load Balancing with 2-Level UPFC in a Transmission Corridor

A black icon of a calendar showing a grid of dates.

May 27, 2025 | Blog

Diagram of power plant to infinite bus transmission showing load balancing via UPFC, with 75 MW in and 45 MW out.

Client: Confidential

Location: Southeastern USA

System Configuration: Single-machine to infinite bus system with parallel lines

Objective: Prevent line overload during rapid generation shifts

Background:

A power plant in the southeastern U.S. experienced overloading on its secondary transmission line (Line 1B) whenever active generation ramped up beyond 120 MW due to seasonal peak demand. The primary line (Line 1) was underutilized due to a lack of dynamic flow control.



This scenario highlights the importance of unified power flow controller (UPFC) solutions for effective power flow control in transmission lines under dynamic operating conditions.

Solution Implemented:

Keentel Engineering deployed a 2-level Unified Power Flow Controller (UPFC) on Line 1, as modeled in the referenced IEEE study. The UPFC’s series compensator regulated active power while the shunt branch maintained DC bus and voltage stability.


The implementation enabled dynamic load balancing in the power system by actively controlling line loading and redistributing power flow.

Technical Highlights:

  • Initial Generation: 75 MW (25 MW via Line 1, 50 MW via Line 1B)
  • Ramped Generation: 140 MW post 100ms demand spike
  • Power Re-routing: UPFC dynamically rerouted power to Line 1, reducing Line 1B stress
  • Control Strategy: Block diagram-based d-q rotating frame control as shown on page 2, Fig. 3

Results:

  • Maintained power flow within the 80 MW thermal limit of Line 1B
  • Enabled flexible generation ramping without reconfiguration
  • Improved system stability and minimized reactive power losses


To implement similar solutions, explore our power system studies services


Case Study 2: Voltage Support in Urban Substation Using Shunt Compensation

Client: Confidential

Location: Midwest USA

System Configuration: 400 kV ring bus with dual supply and dynamic RL load

Objective: Mitigate voltage sag at critical urban bus under fluctuating load

Background:

A major metropolitan area in the Midwest observed voltage dips at a distribution bus (Bus 2) when reactive-heavy RL industrial loads were introduced. The instability risked tripping protection relays and violating utility voltage criteria.


Voltage stability in power systems becomes critical under reactive load conditions, especially in urban substations with fluctuating demand.

Solution Implemented:

Keentel Engineering integrated a 2-level UPFC at Bus 2 using the configuration described in page 3, Fig. 9. The shunt branch regulated reactive power injection, while the series branch maintained power flow balance across Line 1.


The UPFC provided fast voltage support by injecting reactive power, helping maintain stable bus voltage during transient disturbances.

System Parameters:

  • Base Load: 80 MW
  • Disturbance Load: 5 MW + 75 MVAr RL load added at 0.02 sec
  • Control Mechanism: Reactive power control via d-q frame (equation 9, page 2)

Results:

  • Voltage sag was reduced by 12% compared to the non-UPFC case (Fig. 10, page 3)
  • Reactive power injected adaptively, peaking at 0.8 pu during maximum load
  • Voltage restored to nominal value within 50ms of disturbance

A smiling man with glasses and a beard wearing a blue blazer stands in front of server racks in a data center.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.

His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.

Four workers in safety vests and helmets stand with arms crossed near wind turbines.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.

Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.

His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.

Today, as Founder and CEO of Keentel Engineering, Sonny leads a nationwide team of engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering.

Leave a Comment

Related Posts

Keentel Engineering graphic showing damped and undamped subsynchronous oscillations.
By SANDIP R PATEL • October 3, 2026
October 03, 2026 | Blog
NERC and ERCOT compliance guide for natural gas power plants showing power system diagram and grid c
By SANDIP R PATEL • September 30, 2026
Learn NERC and ERCOT compliance requirements for natural gas power plants, including GO/GOP obligations, O&P standards, GADS reporting, and audits.
Data center and high-voltage transmission grid illustrating a large-load interconnection application
By SANDIP R PATEL • September 26, 2026
Learn how to prepare a MISO large-load interconnection package, including PSS®E models, BESS smoothing, harmonic data and transmission-owner requirements.
800 VDC AI data center storage architecture with battery systems, DC power distribution, and electri
By SANDIP R PATEL • September 26, 2026
Learn where storage belongs in an 800 VDC AI data center, including capacitors, flywheels, BESS, fault current, protection, grounding, and EMT design.
SPP HILL and HILLGA framework for large-load developers
By SANDIP R PATEL • September 26, 2026
Learn how SPP’s HILL and HILLGA framework works for large-load projects, including studies, BTM generation, modeling, EMT requirements, and firm service.
IBR time synchronization and IEEE 2800 compliance for disturbance monitoring systems
By SANDIP R PATEL • September 25, 2026
Learn how IBR time synchronization, IEEE 2800, IRIG-B verification, and PTP solutions help meet disturbance monitoring compliance requirements.
Power engineering technical training and professional development for electrical engineers
By SANDIP R PATEL • September 24, 2026
Learn why continuing technical training matters in power engineering, including standards, software skills, PDH requirements, and career growth.
ERCOT new generator commissioning checklist parts 1, 2 and 3
By SANDIP R PATEL • September 22, 2026
2026 ERCOT commissioning guide covering the Commissioning Plan, Checklist Parts 1–3, BESS requirements, TSP/QSE coordination, field testing and COD.
PRC-030-1 NERC IBR compliance guide showing 20 MW event detection threshold and R1 monitoring timeli
By SANDIP R PATEL • September 22, 2026
Learn PRC-030-1 R1 event detection requirements for inverter-based resources, SEL platforms, disturbance monitoring, and audit-ready compliance.