Case Study 1: Dynamic Load Balancing with 2-Level UPFC in a Transmission Corridor

A black icon of a calendar showing a grid of dates.

May 27, 2025 | Blog

Diagram of power plant to infinite bus transmission showing load balancing via UPFC, with 75 MW in and 45 MW out.

Client: Confidential

Location: Southeastern USA

System Configuration: Single-machine to infinite bus system with parallel lines

Objective: Prevent line overload during rapid generation shifts

Background:

A power plant in the southeastern U.S. experienced overloading on its secondary transmission line (Line 1B) whenever active generation ramped up beyond 120 MW due to seasonal peak demand. The primary line (Line 1) was underutilized due to a lack of dynamic flow control.



This scenario highlights the importance of unified power flow controller (UPFC) solutions for effective power flow control in transmission lines under dynamic operating conditions.

Solution Implemented:

Keentel Engineering deployed a 2-level Unified Power Flow Controller (UPFC) on Line 1, as modeled in the referenced IEEE study. The UPFC’s series compensator regulated active power while the shunt branch maintained DC bus and voltage stability.


The implementation enabled dynamic load balancing in the power system by actively controlling line loading and redistributing power flow.

Technical Highlights:

  • Initial Generation: 75 MW (25 MW via Line 1, 50 MW via Line 1B)
  • Ramped Generation: 140 MW post 100ms demand spike
  • Power Re-routing: UPFC dynamically rerouted power to Line 1, reducing Line 1B stress
  • Control Strategy: Block diagram-based d-q rotating frame control as shown on page 2, Fig. 3

Results:

  • Maintained power flow within the 80 MW thermal limit of Line 1B
  • Enabled flexible generation ramping without reconfiguration
  • Improved system stability and minimized reactive power losses


To implement similar solutions, explore our power system studies services


Case Study 2: Voltage Support in Urban Substation Using Shunt Compensation

Client: Confidential

Location: Midwest USA

System Configuration: 400 kV ring bus with dual supply and dynamic RL load

Objective: Mitigate voltage sag at critical urban bus under fluctuating load

Background:

A major metropolitan area in the Midwest observed voltage dips at a distribution bus (Bus 2) when reactive-heavy RL industrial loads were introduced. The instability risked tripping protection relays and violating utility voltage criteria.


Voltage stability in power systems becomes critical under reactive load conditions, especially in urban substations with fluctuating demand.

Solution Implemented:

Keentel Engineering integrated a 2-level UPFC at Bus 2 using the configuration described in page 3, Fig. 9. The shunt branch regulated reactive power injection, while the series branch maintained power flow balance across Line 1.


The UPFC provided fast voltage support by injecting reactive power, helping maintain stable bus voltage during transient disturbances.

System Parameters:

  • Base Load: 80 MW
  • Disturbance Load: 5 MW + 75 MVAr RL load added at 0.02 sec
  • Control Mechanism: Reactive power control via d-q frame (equation 9, page 2)

Results:

  • Voltage sag was reduced by 12% compared to the non-UPFC case (Fig. 10, page 3)
  • Reactive power injected adaptively, peaking at 0.8 pu during maximum load
  • Voltage restored to nominal value within 50ms of disturbance

A smiling man with glasses and a beard wearing a blue blazer stands in front of server racks in a data center.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.

Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads 51 engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering

Four workers in safety vests and helmets stand with arms crossed near wind turbines.

Let's Discuss Your Project

Let's book a call to discuss your electrical engineering project that we can help you with.

Man in a blazer and open shirt, looking at the camera, against a blurred background.

About the Author:

Sandip "Sonny" R. Patel, P.E.

IEEE Senior Member · Founder & CEO, Keentel Engineering

In 1995, Sonny Patel earned his Electrical Engineering degree from the University of Illinois. But degrees don't build legacies — action does.

For three decades, he has worked the power industry from every side of the table: 16 years as a utility engineer at Exelon/Commonwealth Edison; generation leadership across hydroelectric, industrial steam turbine, and a 9 GW renewable fleet; NERC Regional Entity Senior Compliance Engineer and Audit Team Lead, auditing some of the nation's largest utilities; and testing and commissioning lead on equipment up to 765 kV — the very top of the North American grid.Utility. Generator. Regulator. Consultant. Few engineers have seen all four seats. Fewer still have sat in them.His experience spans nuclear, hydro, conventional generation, renewables, oil and gas, mining — and today's data centers, where he is authoring a three-book series on data center design. He is a Licensed Professional Engineer in six states and a Licensed Electrical Contractor in Florida (Unlimited EC) — he doesn't just design the work; he's qualified to stand behind its execution.Today, as Founder and CEO of Keentel Engineering, Sonny leads 51 engineers delivering substation design, power system studies, NERC compliance, and commissioning — done right, coast to coast.Three decades. Every side of the table. One standard: accountable engineering

Leave a Comment

Related Posts

12.47 kV pole-mounted distribution transformer assembly designed for U.S. IEEE and NESC utility stan
By SANDIP R PATEL August 20, 2026
Learn U.S. pole-mounted transformer design requirements, including IEEE, ANSI, and NESC standards, voltage classes, grounding, protection, and DER considerations.
PRC-023-6 BESS relay loadability compliance guide
By SANDIP R PATEL August 19, 2026
Understand PRC-023-6 for utility-scale BESS: applicability, the 39-month rule, relay loadability, setting criteria, Category 2 IBRs, and audit evidence.
PRC-029-1 voltage ride-through envelope for inverter-based resources.
By SANDIP R PATEL August 18, 2026
Learn PRC-029-1 compliance requirements for inverter-based resources, including voltage and frequency ride-through, EMT studies, protection settings, and testing.
Solar plant electrical testing and commissioning for utility-scale PV systems
By SANDIP R PATEL August 17, 2026
A technical guide to solar plant electrical testing, commissioning, I-V curves, thermography, insulation testing, cable tests and performance acceptance.
Alt Text: Gas-insulated substation engineering guide covering GIS safety, reliability, VFTO, partial
By SANDIP R PATEL August 16, 2026
Explore GIS substation engineering, including design, SF6 safety, VFTO, grounding, commissioning, testing, GIS vs AIS, and IEEE/IEC standards.
Cable testing before energization engineering guide
By SANDIP R PATEL August 16, 2026
Learn the correct cable testing sequence before energization, including VLF, AC/DC withstand, sheath testing, partial discharge, tan delta, and standards.
substation drawing sets
By SANDIP R PATEL August 16, 2026
Explore how substation drawing sets are developed, reviewed and controlled through engineering studies, design milestones, QA/QC and final construction release.
Grid-forming vs grid-following BESS inverters
By SANDIP R PATEL August 15, 2026
Compare grid-forming vs grid-following BESS inverters, control loops, weak-grid stability, protection, compliance, and interconnection study impacts.
MOD-025 and MOD-026 post-COD verification testing with PSS E and PSCAD dynamic model validation
By SANDIP R PATEL August 15, 2026
Learn MOD-025 and MOD-026 post-COD requirements for generator capability verification, PSS®E and PSCAD model validation, IBR testing, and NERC compliance.